667
|
Thursday, June 07, 2018, 09:21 |
Aaron Schmidt | | | | | | | Problems/Solutions | Pump down empty chamber. Anode check | TM2 Source tray still in.
Thursday, June 07, 2018, 09:20: Roughing.
Thursday, June 07, 2018, 12:42: Turbo |
|
|
668
|
Tuesday, June 12, 2018, 11:38 |
Aaron Schmidt | | | | | | | In progress | Source Tray re-installation | Re-installation of the ISAC Test Stand
Source tray. The TM2 ST was removed.
Tuesday, June 12, 2018, 10:15: Disconnect |
|
|
669
|
Tuesday, June 19, 2018, 10:30 |
Aaron Schmidt | | | | | | | Done | RGA repair | Monday, June 18, 2018, 10:00: RGA removed
from ISAC TS. Handed to Travis C. Communications
issues found |
|
|
670
|
Thursday, June 21, 2018, 16:32 |
Anders Mjos | | LP-FEBIAD | | | 41790-9 | 42752-5 | In progress | Heating target | Thursday, June 21, 2018, 16:30: Short between
ANODE and EE. Do not use until repaired.
Thursday, June 21, 2018, 16:32: Ramping |
|
|
672
|
Monday, July 09, 2018, 10:44 |
Aaron Schmidt | | LP-FEBIAD | | | 41790-9 | 42752-5 | In progress | Coil Test July | Monday, July 09, 2018, 10:43: Rouging.
Monday, July 09, 2018, 13:14: Turbo
pumps on. |
|
|
673
|
Thursday, July 12, 2018, 08:24 |
Aaron Schmidt | | LP-FEBIAD | | | 41790-9 | 42752-5 | In progress | Power outage / restart | Power outage (07/11/2018 @ approx 21:53)
shut down the test stand.
|
|
|
674
|
Thursday, July 12, 2018, 10:11 |
Aaron Schmidt | | LP-FEBIAD | | | 41790-9 | 42752-5 | In progress | Coil Test #5 | *** REVIEW Elog entry #673 Power
outage & restart ***
Thursday, July 12, 2018, 10:10: Opened |
|
|
677
|
Friday, August 10, 2018, 10:56 |
Aaron Schmidt | | | | | | | Problems/Solutions | New PS installation and Cathode BIAS set | Friday, August 10, 2018, 10:25: Remove
TBHT 500 PS and replace with TBHT 600 PS.
Friday, August 10, 2018, 10:50: Switch |
|
|
678
|
Tuesday, August 14, 2018, 11:03 |
Aaron Schmidt | | LP-SIS | | | 41177-3 | 42752-6 | | Voltage Tests (Ta target) | Tuesday, August 14, 2018, 10:55: Auto ramping
TGHT @ 6 A per min to 40 A.
Tuesday, August 14, 2018, 11:03: |
|
|
679
|
Tuesday, August 21, 2018, 12:54 |
Anders Mjos | | | | | | | Problems/Solutions | 9-pin connection configuration | Pin configuration between top 9-pin connector
on Source Tray and terminal in high voltage
rack. Measured 2018-08-21 by Aaron and Anders |
|
|
680
|
Wednesday, August 22, 2018, 15:20 |
Aaron Schmidt | | LP-SIS | | | 41177-3 | | | Voltage Tests (Ta Target) | Wires reconfigured / set
Wednesday, August 22, 2018, 13:10:
Roughing. |
|
|
681
|
Wednesday, August 29, 2018, 11:36 |
Aaron Schmidt | | | | | | | | Epics / putty crash. | Wednesday, August 29, 2018, 11:35: EPIC's
crashed.... epically.
Unable to restart Putty or TS controls. |
|
|
682
|
Friday, August 31, 2018, 10:16 |
Aaron Schmidt | | | | | | | Problems/Solutions | RGA connection loss. | Friday, August 31, 2018, 10:10: The RGA
will not re-connect to the computer. Manually
turned it off while under vacuum to protect |
|
|
687
|
Tuesday, October 02, 2018, 13:39 |
Aaron Schmidt | | LP-FEBIAD | | | 41790-9 | 42752-5 | In progress | Test FEBIAD w/ Silver bolts & sealed end caps w/ stoppage | Silver bolts used on Coil, TGHT, &
TBHT.
End caps in target |
|
|
688
|
Monday, October 15, 2018, 14:23 |
Aaron Schmidt | | LP-FEBIAD | | | 41790-9 | 42752-5 | In progress | Test FEBIAD w/ Silver bolts & sealed end caps | Anode / Cathode BIAS PS polarity reversed
by John Chow. PS: Negative
Monday, October 15, 2018, 14:12: |
|
|
689
|
Monday, October 15, 2018, 14:38 |
Aaron Schmidt | | | | | | | Problems/Solutions | Anode / Cathode PS to Negative | Monday, October 15, 2018, 13:00-14:00 Anode
/ Cathode BIAS PS polarity reversed by John
Chow. |
|
|
690
|
Monday, October 22, 2018, 07:18 |
Aaron Schmidt | | | | | | | | TS restart after power outage | Friday, October 19, 2018, 10:00 (Approx):
Site wide power outage. TS completely shut
down. |
|
|
691
|
Monday, October 22, 2018, 11:07 |
Aaron Schmidt | | LP-FEBIAD | | | 41790-9 | 42752-5 | In progress | Test FEBIAD w/ Silver bolts & sealed end caps | Restarted post power outage.
Water & Turbos on.
Monday, October 22, 2018, 10:55: |
|
|
692
|
Monday, October 29, 2018, 10:56 |
Aaron Schmidt | | LP-FEBIAD | | | 41790-9 | 42752-5 | Problems/Solutions | TS communications issues. | Sometime around 00:30 Sunday, October 28,
2018, the ISAC test stand lost communication
to the PLC and shut down abruptly. |
|
|
693
|
Monday, October 29, 2018, 11:03 |
Aaron Schmidt | | LP-FEBIAD | | | 41790-9 | 42752-5 | Done | Test FEBIAD w/ Silver bolts & sealed end caps | Restarting FEBIAD
Monday, October 29, 2018, 10:56:
Restart roughing & Turbo pumps. |
|
|