  667   Thursday, June 07, 2018, 09:21 Aaron Schmidt      Problems/SolutionsPump down empty chamber. Anode checkTM2 Source tray still in.
Thursday, June 07, 2018, 09:20: Roughing.
Thursday, June 07, 2018, 12:42: Turbo
 20180608_100402.jpg20180608_100835.jpg20180608_100840.jpg20180613_080550.jpg20180613_080605.jpg 
  668   Tuesday, June 12, 2018, 11:38 Aaron Schmidt      In progressSource Tray re-installationRe-installation of the ISAC Test Stand
Source tray. The TM2 ST was removed.
Tuesday, June 12, 2018, 10:15: Disconnect
 TS_Source_Tray_re-installed_2018_-_(Leak_found).docx 
  669   Tuesday, June 19, 2018, 10:30 Aaron Schmidt      DoneRGA repairMonday, June 18, 2018, 10:00: RGA removed
from ISAC TS. Handed to Travis C. Communications
issues found
  
  670   Thursday, June 21, 2018, 16:32 Anders Mjos LP-FEBIAD  41790-942752-5In progressHeating targetThursday, June 21, 2018, 16:30: Short between
ANODE and EE. Do not use until repaired.
Thursday, June 21, 2018, 16:32: Ramping
 TS-2018-06-19-10-30.rgaTS_Source_tray_2018_-_Check_2.docx 
  672   Monday, July 09, 2018, 10:44 Aaron Schmidt LP-FEBIAD  41790-942752-5In progressCoil Test July Monday, July 09, 2018, 10:43: Rouging.
Monday, July 09, 2018, 13:14: Turbo
pumps on.
  
  673   Thursday, July 12, 2018, 08:24 Aaron Schmidt LP-FEBIAD  41790-942752-5In progressPower outage / restartPower outage (07/11/2018 @ approx 21:53)
shut down the test stand.
  
  674   Thursday, July 12, 2018, 10:11 Aaron Schmidt LP-FEBIAD  41790-942752-5In progressCoil Test #5 *** REVIEW Elog entry #673 Power
outage & restart ***
Thursday, July 12, 2018, 10:10: Opened
  
  677   Friday, August 10, 2018, 10:56 Aaron Schmidt      Problems/SolutionsNew PS installation and Cathode BIAS setFriday, August 10, 2018, 10:25: Remove
TBHT 500 PS and replace with TBHT 600 PS.
Friday, August 10, 2018, 10:50: Switch
  
  678   Tuesday, August 14, 2018, 11:03 Aaron Schmidt LP-SIS  41177-342752-6 Voltage Tests (Ta target)Tuesday, August 14, 2018, 10:55: Auto ramping
TGHT @ 6 A per min to 40 A.
Tuesday, August 14, 2018, 11:03:
  
  679   Tuesday, August 21, 2018, 12:54 Anders Mjos      Problems/Solutions9-pin connection configurationPin configuration between top 9-pin connector
on Source Tray and terminal in high voltage
rack. Measured 2018-08-21 by Aaron and Anders
  
  680   Wednesday, August 22, 2018, 15:20 Aaron Schmidt LP-SIS  41177-3  Voltage Tests (Ta Target)  Wires reconfigured / set 
Wednesday, August 22, 2018, 13:10:
Roughing. 
  
  681   Wednesday, August 29, 2018, 11:36 Aaron Schmidt       Epics / putty crash.Wednesday, August 29, 2018, 11:35: EPIC's
crashed.... epically.
Unable to restart Putty or TS controls.
  
  682   Friday, August 31, 2018, 10:16 Aaron Schmidt      Problems/SolutionsRGA connection loss.Friday, August 31, 2018, 10:10: The RGA
will not re-connect to the computer. Manually
turned it off while under vacuum to protect
  
  687   Tuesday, October 02, 2018, 13:39 Aaron Schmidt LP-FEBIAD  41790-942752-5In progressTest FEBIAD w/ Silver bolts & sealed end caps w/ stoppageSilver bolts used on Coil, TGHT, &
TBHT.
End caps in target
 FEBIAD_Coil_Test_6_-_POS_Cathode.docxTS-2018-10-11-10-37.rga 
  688   Monday, October 15, 2018, 14:23 Aaron Schmidt LP-FEBIAD  41790-942752-5In progressTest FEBIAD w/ Silver bolts & sealed end caps Anode / Cathode BIAS PS polarity reversed
by John Chow. PS: Negative
Monday, October 15, 2018, 14:12:
 FEBIAD_Coil_Test_6-2_-_Neg_Cathode.docxTS-2018-10-15-14-15.rga 
  689   Monday, October 15, 2018, 14:38 Aaron Schmidt      Problems/SolutionsAnode / Cathode PS to NegativeMonday, October 15, 2018, 13:00-14:00 Anode
/ Cathode BIAS PS polarity reversed by John
Chow.
  
  690   Monday, October 22, 2018, 07:18 Aaron Schmidt       TS restart after power outageFriday, October 19, 2018, 10:00 (Approx):
Site wide power outage. TS completely shut
down. 
  
  691   Monday, October 22, 2018, 11:07 Aaron Schmidt LP-FEBIAD  41790-942752-5In progressTest FEBIAD w/ Silver bolts & sealed end caps Restarted post power outage.
Water & Turbos on.
Monday, October 22, 2018, 10:55:
 epics-plot-whiteout-181028_1322.PNGepics-whiteout-181028_1322.PNGFEBIAD_COIL_Test_6-3_Caps_in.docxTS-2018-10-22-09-47.rga 
  692   Monday, October 29, 2018, 10:56 Aaron Schmidt LP-FEBIAD  41790-942752-5Problems/SolutionsTS communications issues.Sometime around 00:30 Sunday, October 28,
2018, the ISAC test stand lost communication
to the PLC and shut down abruptly.
  
  693   Monday, October 29, 2018, 11:03 Aaron Schmidt LP-FEBIAD  41790-942752-5DoneTest FEBIAD w/ Silver bolts & sealed end capsRestarting FEBIAD
Monday, October 29, 2018, 10:56:
Restart roughing & Turbo pumps.
  