Entry  Friday, January 26, 2018, 13:59, Aaron Schmidt, , LP-SIS, , , (Blank), 42752-3, Done, HV test 1 2018_HV_test_1.docx
Entry  Monday, January 29, 2018, 10:07, Aaron Schmidt, , LP-SIS, , , (Blank), 42752-3, Done, Power outage / HV test 2 2018_HV_test_2.docx
Entry  Tuesday, January 30, 2018, 06:51, Aaron Schmidt, , LP-SIS, , , (Blank), 42752-3, Done, HV test 3 2018_HV_test_3.docx
Entry  Wednesday, January 31, 2018, 09:53, Aaron Schmidt, , , , , (Blank), 42752-3, Done, Wire moved. 
Entry  Thursday, February 08, 2018, 14:44, Carla Babcock, , , , , , , Done, Conditioning station power supply integrated into EPICS 
Entry  Tuesday, April 17, 2018, 11:02, Aaron Schmidt, , , , , , , Done, Roughing pump issue. 
Entry  Thursday, April 19, 2018, 12:55, Fernando Maldonado, , , , , , , Done, Re-wiring Anode PS 20180420_104954.jpg
Entry  Friday, April 20, 2018, 13:20, Carla Babcock, , , , , , , Done, BIAS* fan sounds like it is dying  
Entry  Tuesday, June 19, 2018, 10:30, Aaron Schmidt, , , , , , , Done, RGA repair 
Entry  Monday, October 29, 2018, 11:03, Aaron Schmidt, , LP-FEBIAD, , , 41790-9, 42752-5, Done, Test FEBIAD w/ Silver bolts & sealed end caps 
Entry  Monday, March 11, 2019, 13:56, Aaron Schmidt, , , , , , , Done, TGHT PS replaced 
Entry  Monday, April 15, 2019, 14:42, Aaron Schmidt, , LP-SIS, , , , 42972-1, Done, Conditioning UC#27 HS & test FS#3 UC#27_&_FS#3_check.docxTS-2019-04-16-08-20.rga
Entry  Tuesday, April 23, 2019, 14:39, Aaron Schmidt, , LP-SIS, , , , 42752-8, Done, Conditioning UC#28 HS  TS-2019-04-24-07-30.rgaUC#28_HS.docx
Entry  Monday, June 03, 2019, 14:13, Aaron Schmidt, , , , TM4, 395530-3, 42752-5, Done, TMS:TP6 Turbo pump issue. (Ok now) 
Entry  Monday, June 10, 2019, 14:34, Aaron Schmidt, , , , , , , Done, Removed TM4 Source Tray 
Entry  Monday, June 10, 2019, 14:35, Aaron Schmidt, , , , , , , Done, Optics Tray / EZL inspection. 20190610_135100.jpg20190610_135926.jpg20190610_135045.jpg20190610_135517.jpg
Entry  Thursday, June 13, 2019, 14:05, Aaron Schmidt, , , , , , , Done, Spare TGHT PS installed. 
Entry  Wednesday, June 19, 2019, 17:25, Fernando Maldonado, , , , , , , Done, Thermocouple connection 
Entry  Saturday, June 22, 2019, 17:05, Luca Egoriti, p2n, , , , , , Done, Test stand installation 
Entry  Tuesday, July 02, 2019, 18:25, Fernando Maldonado, , , , , , , Done, Blank on FEBIAD gas line installed 20190702_182254.jpg