  364   Monday, March 17, 2014, 19:10 Anders MjosTa#42LP-SISITWTM440282-139956-1 / 39956-9 (base / lid)In progressConditioning

NOTE:

TBHT Power Supply is 600A. EPICS thinks it is 500. Multiply current setting with 1.2 for actual current to the tube.

Time stamp on OM-DAQPRO-5300 is on hour behind (daylight savings).

 


All bolts torqued to 130 in lbs. TGHT and TBHT bolts tightened and loosened 3x.

Monday, March 17, 2014, 19:10: Roughing

Monday, March 17, 2014, 19:30: Turbos started

 Monday, March 17, 2014, 19:38: Turbos at speed. 

Monday, March 17, 2014, 19:40: Vacuum at 1.3E-5 T


BY R.M.

Tuesday, March 18, 2014, 10:10: Vacuum 2.87e-07 T

Tuesday, March 18, 2014, 10:12: Heatshield Water Circuit turned on

Tuesday, March 18, 2014, 10:25: Vacuum 2.85e-07 T

By AM

Tuesday, March 18, 2014, 16:06:

Conditioned high voltage BIAS to 30kV. BIAS:RDCUR 37 uA.

Started heater auto-ramping. TBHT to 50A at 1A/min. TGHT to 100A at 2 A/min.

Vacuum at 2.7E-7 T

Tuesday, March 18, 2014, 17:06: TBHT and TGHT reached 50A and 100A respectively. Local readback on TBHT is 58A (as expected - see note above). Vacuum is gradually coming down.


Operation stable over night. TSG:CBC needed to be restarted. Switched off over night.

Wednesday, March 19, 2014, 08:21: Continue heating to 85A / 250 A TBHT/TGHT.

Wednesday, March 19, 2014, 09:12

Water temperatures 27 - 28 deg C, and flow Rates
4.0 l/m HS+MSP
6.4 l/m TBHT
5.1 l/m COIL+EE
5.6 l/m TGHT

Wednesday, March 19, 2014, 09:57: Continue heating to 170 A / 500 A, TBHT/TGHT

Wednesday, March 19, 2014, 09:58: Opened IV4

Wednesday, March 19, 2014, 09:58: Restarted Q1.

Wednesday, March 19, 2014, 10:11: Switched FC0 bias to negative

Wednesday, March 19, 2014, 10:30: Q1 restarted. Possible spark. Small vacuum response on IG1

Wednesday, March 19, 2014, 10:49: Some sparking

Wednesday, March 19, 2014, 12:43: Continue heating to 190A / 580 A TBHT/TGHT.

Wednesday, March 19, 2014, 13:00: TBHT voltage limited. Increased limit to 2.3V

Water temperatures and flow rates
35 C 4.0 l/m HS+MSP
28 C 6.4 l/m TBHT
28 C 5.1 l/m COIL+EE
30 C 5.6 l/m TGHT

Wednesday, March 19, 2014, 13:32: Local read back on PS: 223A / 580A TBHT/TGHT

Water temperatures and flow rates
37 C 4.0 l/m HS+MSP
28 C 6.4 l/m TBHT
29 C 5.1 l/m COIL+EE
31 C 5.6 l/m TGHT

Wednesday, March 19, 2014, 14:30: Measured ~2E-7 A 23Na on FC6 and 2E-7 A on FC0. Vacuum on IG1 4.2E-8 T

Wednesday, March 19, 2014, 14:58: TBHT was voltage limiting. Increased voltage limit to 2.4 V

Target will condition over night.


Thursday, March 20, 2014, 10:07: Measured ~1.4E-8 A 23Na on FC6 and 2E-7 A on FC0. Vacuum on IG1 8.3E-7 T

Water temperatures and flow rates
35 C 4.0 l/m HS+MSP
27 C 6.4 l/m TBHT
27 C 5.1 l/m COIL+EE
29C 5.6 l/m TGHT

Thursday, March 20, 2014, 10:13: Starting mass scan 200 - 0

Local current  on PS (TBHT/TGHT): 227 A / 580 A

At about 10:15 to 10:20 the TGHT:RDVOL dropped from 7.2 - 7.1 V.

Thursday, March 20, 2014, 11:05: Mass scan finished.

Water temperatures and flow rates
36 C 4.0 l/m HS+MSP
28 C 6.4 l/m TBHT
29 C 5.1 l/m COIL+EE
30 C 5.6 l/m TGHT

Thursday, March 20, 2014, 13:20

Water temperatures and flow rates
34.8 C 4.0 l/m HS+MSP
26.1 C 6.4 l/m TBHT
26.8 C 5.1 l/m COIL+EE
28.4 C 5.6 l/m TGHT

Thursday, March 20, 2014, 13:24: Conditioning EE to -2kV

Thursday, March 20, 2014, 13:26: EE at -2kV and 694 uA

Thursday, March 20, 2014, 13:36: Lowering EE back to -1.4kV

Thursday, March 20, 2014, 13:38: Starting the cool down of the target at 2 A/min

Thursday, March 20, 2014, 15:08: Closed IV4


Friday, March 21, 2014, 08:32: Lowered BIAS, EE and EZL to 0. TGHT and TBHT off.

Friday, March 21, 2014, 08:33: Stopped turbos. Vacuum at 1.3E-7 T

Friday, March 21, 2014, 13:10: Venting

Attachment 1: Ta#42_Test_Stand.docx
Attachment 2: OMEGA_OM-DAQPRO-5300_21-Mar-14_13.56.35.dlp
  363   Wednesday, March 12, 2014, 10:20 Rick Maharaj      Donereplace heatshield waterline loop

A new Heatshield waterline loop was manufactured and installed to replace the old one which had a leak.

Chamber vacuum currently being roughed down.

Wednesday, March 12, 2014, 10:41: Started turbos.

Wednesday, March 12, 2014, 10:5:0 Turbos at speed. TP1A timed out once.

Wednesday, March 12, 2014, 10:51: Vacuum at 2.6E-5 T.  


By AM

Thursday, March 13, 2014, 10:20: Opened water. Vacuum stable at 9.3E-7 T.

Venting chamber to investigate slow pump down.

Thursday, March 13, 2014, 10:21: Stopped turbos.

Thursday, March 13, 2014, 11:15: Venting

 

By RM

HS loop wiped with methanol, door seals wiped.

Thursday, March 13, 2014, 11:47: Pump down Started

Thursday, March 13, 2014, 12:05: Turbos started

Thursday, March 13, 2014, 12:09: TP1B at speed

Thursday, March 13, 2014, 12:12: TP1A at speed

Thursday, March 13, 2014, 12:13: IG1 turned on Vacuum at 7.2E-06


By AM

Monday, March 17, 2014, 12:55 : Stopped turbos. Vacuum at 2.4E-7 T. 

Monday, March 17, 2014, 17:39: Venting

 

  362   Tuesday, March 11, 2014, 09:03 Anders Mjos      Problems/SolutionsLeak on water line for Heat Shield

Tuesday, March 11, 2014, 09:03: Venting to investigate

  361   Friday, March 07, 2014, 11:38 Anders Mjos      Problems/SolutionsTMS:TP2 stopped over night

See fault report 7240


Tuesday, March 11, 2014, 09:04: Stopping TMS:TP6. Vacuum at 9.7E-6 T.


Wednesday, March 12, 2014, 10:22: Venting TMS section for TP2 replacement.

Edi replaced TP2

Wednesday, March 12, 2014, 15:36: Roughing TMS section.

Wednesday, March 12, 2014, 15:45: Starting turbos.

Wednesday, March 12, 2014, 15:49: Turbos at speed. Vacuum at 3.6E-5 T.

Wednesday, March 12, 2014, 15:55: Vacuum at 1.5E-5 T.

  360   Wednesday, February 12, 2014, 09:01 Anders Mjos      In progressTesting Cleaning sample

Wednesday, February 12, 2014, 08:55: Stopped turbos 

Wednesday, February 12, 2014, 11:28: Venting

Installed one sample. No cleaning. Connection tabs wiped with alcohol to prevent making the source tray dirty.

Wednesday, February 12, 2014, 13:17: Started roughing

Wednesday, February 12, 2014, 13:38: Started turbos

Wednesday, February 12, 2014, 13:42: TP1B at speed. Vacuum at 5.4E-5 T

Wednesday, February 12, 2014, 13:46: TP1A at speed. Vacuum at 1.9E-5 T 

Wednesday, February 12, 2014, 13:48: Vacuum at 1.7E-5 T


EPICS white-out due to ER0 activity. Graham assisted in getting the system back up.


Wednesday, February 12, 2014, 15:16 : Vacuum at 4.8E-6 T 


Friday, February 27, 2014

Leak checked doors. No leak found.


Friday, February 28, 2014, 08:42: Opened up water supply. Major vacuum response.

Friday, February 28, 2014, 08:42: Stopped turbos

Friday, February 28, 2014, 10:19: Venting

Removed cleaning sample.

Friday, February 28, 2014, 11:38: Pumping down empty chamber

Friday, February 28, 2014, 11:56 : Starting Turbos

Friday, February 28, 2014, 12:05 : Turbos at speed

Friday, February 28, 2014, 12:06: Vacuum at 1.7E-5 T 


Monday, March 03, 2014, 09:28  : Vacuum leak on waterline (HS) still present. Stopping turbos for investigation.


Tuesday, March 04, 2014, 09:58: Venting

Replaced Cu-gaskets with Parker SST gaskets.

Tuesday, March 04, 2014, 11:03: Roughing

Tuesday, March 04, 2014, 11:26: Starting Turbos

Tuesday, March 04, 2014, 11:35: Turbos at speed. (TP1A timed out once)

Tuesday, March 04, 2014, 11:36: Vacuum at 1.6E-5 T


Thursday, March 06, 2014, 08:21: Vacuum leak no waterline (HS) still present. Stopping turbos.

  359   Wednesday, February 05, 2014, 11:27 Anders Mjos      Problems/SolutionsEmittance Rig installation

Wednesday, February 05, 2014, 11:27 : Stopped turbos

  • 2x spacers ITD0468 1/8" THK installed to shift the wire scanner screen closer to the wire scanner. (ITD0469 1/16" THK spacers not used).
  • Emittance Rig installed. Manually actuated from out -> in -> out position. No interference observed.
  • Replaced two insulators on wire scanner screens that broke in the installation process. New insulators kindly donated from ISIS.

By Anders and Ayan.

Wednesday, February 05, 2014, 16: Roughing


Thursday, February 06, 2014, 08:42: Turbos started

Thursday, February 06, 2014, 08:50: Turbos at speed. IG6 6.2E-6 T, IG1 1.3 E-6 T

Attachment 1: Spacers_Installed.jpg
Spacers_Installed.jpg
Attachment 2: Emittance_Rig_Inside.jpg
Emittance_Rig_Inside.jpg
Attachment 3: Emittance_Rig_Outside.jpg
Emittance_Rig_Outside.jpg
  358   Thursday, January 30, 2014, 15:38 Anders Mjos      Problems/SolutionsStarting turbos after CuLCW shut off

Anders Mjos wrote:

CuLCW will be shut off tomorrow. Valved off water supply to MB1 and TSG to minimize air into the system. Turbos are off.

Opened up for water flow.

Thursday, January 30, 2014, 15:30: Started turbos

Thursday, January 30, 2014, 15:34: TP2 and TP6 at speed. Vacuum at 2.5E-5 T

Thursday, January 30, 2014, 15:34: TP1B at speed. Vacuum at 1.3E-5 T

Thursday, January 30, 2014, 15:38: TP1A at speed. Vacuum at 1.6E-6 T

  357   Wednesday, January 29, 2014, 14:42 Anders Mjos      Problems/SolutionsValved off water to TSG and TMS:MB1

CuLCW will be shut off tomorrow. Valved off water supply to MB1 and TSG to minimize air into the system. Turbos are off.

  356   Friday, January 24, 2014, 10:49 Anders Mjos      Problems/SolutionsVenting the optics section to investigate Emittance Rig installation

Friday, January 24, 2014, 10:49 : Stopped turbos. Vacuum at 2.5E-7 T 

Friday, January 24, 2014, 12:52: Venting

Finished evaluating emittance rig installation.

Friday, January 24, 2014, 14:25: Roughing.

The Cu-tubing for cooling the Turbo pumps broke off during disassembly. New ferrules could not be located on site and may have to be ordered.

The system will be left under roughing vacuum over the weekend.


Wednesday, January 29, 2014

Cooling for Turbo pumps reconnected.

  355   Thursday, January 16, 2014, 15:00 Anders Mjos      Problems/SolutionsFlow and temperature meter

Flow and temperature meter previously installed on cooling circuits. See attachment for details.

Typical values at 95 psi in and 10 psi out. Cyclotron off.

Device
Temp
[°C]

Flow
[lpm]

Heat Shield and Mounting Support Plate 25 3.9
Tube Heater 25 6.2
Coils and Extraction Electrode 25 5.0
Target Heater 25 5.5

 

Attachment 1: Vortex_Flow_Meter_Config.docx
  354   Tuesday, January 14, 2014, 08:58 Anders Mjos    40282-539230-1DoneHeating Test

Tuesday, January 14, 2014, 08:57: Stopping turbos. Vacuum at 1.2E-7 T

Tuesday, January 14, 2014, 13:32: Venting 

Ta-tube installed. All bolts torqued to 130 in lbs

Thermocouples installed. CH2/3 left/right swapped with respect to previous test.

CH1 1/2: welded outside tube centre - type C
CH2 4/5: inside probe right side - type C
CH3 6/7: inside probe left side - type C
CH4 8/9: welded on leg - type K

Tuesday, January 14, 2014, 15:10: Roughing 
Tuesday, January 14, 2014, 15:33: Starting turbos.
Tuesday, January 14, 2014, 15:42: Turbos at speed
Tuesday, January 14, 2014, 15:43: Vacuum at  2.3E-5 T


Wednesday, January 15, 2014, 10:32: Opened water. Vacuum stable at 2.9E-7 T.


Monday, January 20, 2014

Started heating the Target-tube. 

Pressure increase observed on water supply around 10. Supply ~100psi, return ~7 psi


Tuesday, January 21, 2014

Continue heating from 250 A

Tuesday, January 21, 2014, 15:47: TGHT at 580 A, 7.23 V


Wednesday, January 22, 2014

Target-tube cooled down over night. Will went to investigate TC connections.

Wednesday, January 22, 2014, 08:38 : Turbos stopped. Vacuum at 1.3E-7 T

  353   Thursday, January 02, 2014, 11:53 Anders Mjos      Problems/SolutionsThe computer will not boot Windows

The computer has been brought over to PC support for diagnostics. 

Hard Drive was found to be corrupted. A new HD will be installed and Windows upgraded to a newer version.


Thursday, January 16, 2014

The PC has gotten a new HD with Windows 8.

Xming and PuTTY installed and configured for access to EPICS controls

  352   Friday, December 20, 2013, 15:46 Anders Mjos      Problems/SolutionsWater switched off for the holidays
  351   Wednesday, December 18, 2013, 12:04 Anders Mjos    40282-539230-1DoneHeating Test

 Wednesday, December 18, 2013, 12:04: Turbos stopped

Wednesday, December 18, 2013, 13:19: Venting

Ta-tube installed. All bolts torqued to 130 in lbs

Thermocouples installed.

CH1 1/2: welded outside tube centre - type C
CH2 4/5: inside probe left side - type C
CH3 6/7: inside probe right side - type C
CH4 8/9: welded on leg - type K

Wednesday, December 18, 2013, 14:41: Roughing

Initial temperatures
CH1  28.1
CH2  30.7
CH3  31.3
CH4  31.0

Wednesday, December 18, 2013, 15:50: Starting turbos.

Wednesday, December 18, 2013, 15:58: Turbos at speed.

Wednesday, December 18, 2013, 16:00: Vacuum at 9.3E-6 Torr


Thursday, December 19, 2013, 09:35  : Opened water for HS. Vacuum stable at 2.5E-7 Torr. Flow ~ 3.9 l/min

temperatures
CH1  26.3
CH2  Un
CH3  28.7
CH4  30.5

Thursday, December 19, 2013, 16:50: Ta-tube at 500A ~ 1380 deg C.

temperatures
CH1  33.6
CH2  1319.3
CH3  1443.4
CH4  20.1


Heated to 580A

Friday, December 20, 2013, 10:48: Started cool down at 2A/min.

Friday, December 20, 2013, 15:46: Switched off TGHT.

  350   Thursday, December 12, 2013, 09:01 Anders Mjos      Problems/SolutionsVacuum excursion over night

Monday, December 16, 2013, 08:53
Some additional smaller magnitude excursions have been observed since the fist on on Dec. 12th. See attached plot. 

Attachment 1: VacuumExcursion-2013-12-12.png
VacuumExcursion-2013-12-12.png
Attachment 2: VacuumExcursion-2013-12-16.png
VacuumExcursion-2013-12-16.png
  349   Wednesday, December 04, 2013, 09:22 Anders Mjos      In progressTesting impedance with the new TBHT P/S

Wednesday, December 04, 2013, 09:21 : Turbos stopped. Vacuum at  1.2E-7 Torr

Wednesday, December 04, 2013, 12:35: Venting

Copper bars installed w/ 130 in lbs torque

Wednesday, December 04, 2013, 13:06: Roughing

Wednesday, December 04, 2013, 15:16: Turbos started. Vacuum at 0.03 Torr

Wednesday, December 04, 2013, 15:23: Turbos at speed.

Wednesday, December 04, 2013, 15:26: Vacuum at  5E-6 Torr


Thursday, December 05, 2013

Impedance measured on TGHT and TBHT (~2.5 mOhm and ~2.0 mOhm). Readback on TBHT gives an impedance of ~2.5 mOhm. This is higher than the previous test. Local current on TBHT shows 60A more than the readback at 300A.  The vacuum did not come down as low as usual, which likely means there is a leak.

Thursday, December 05, 2013, 13:15: Turbos stopped.


Friday, December 06, 2013, 13:11: Venting

Gaskets on doors cleaned.

Friday, December 06, 2013, 13:40: Roughing

Friday, December 06, 2013, 13:59: Starting turbos

Friday, December 06, 2013, 14:07: Turbos at speed.

Friday, December 06, 2013, 14:09: Vacuum at 1.4 E-5 Torr


Monday, December 09, 2013, 08:46: Vacuum at 2.0 E-5 Torr 

  348   Monday, December 02, 2013, 15:21 Anders Mjos      Problems/SolutionsXantrex 10V 600A installed and in Cathode Negative mode

By Ray Dube. 

  347   Monday, December 02, 2013, 08:36 Anders Mjos      Problems/SolutionsSources archiver started
  346   Wednesday, November 27, 2013, 08:27 Anders Mjos      Problems/SolutionsEPICS whiteout

Since yesterday around 4pm. Due to attempt to use the TMS:ER0 device.

IOC rebooted this morning. Archivers restarted.

  345   Wednesday, November 20, 2013, 08:57 Anders Mjos      Problems/SolutionsBacking pressure TSG:CG1A and CG1B elevated

 

Anders Mjos wrote:

Pressure around 140 mTorr. The pressure started increasing early November 2nd. Will continue to monitor.

Tuesday, November 12, 2013, 09:51 UPDATE
 Backing pressure further increased to ~ 350 mTorr over the weekend. Vacuum group has been informed and will replace the pump this week.

 

 The backing pump (TSG:RP1) was replaced yesterday by Anthony Ip. Backing pressure is down to 1 mTorr on TSG:CG1A