Entry  Tuesday, March 19, 2013, 12:34, Anders Mjos, SiC#28, , ITE, TM4, , , Done, Installation of SiC#28 LP-RFQ grab.n5HwXJ.png20130321_heating_and_signal.PNG
Tuesday, March 19, 2013, 12:32 : Turbos off (vaccum at 2E-7 Torr)
Tuesday, March 19, 2013, 13:35: Venting
Target SiC#28 LP-RFQ inserted
    Reply  Thursday, March 21, 2013, 15:05, Sebastian Raeder, SiC#28, , ITE, TM4, , , Done, 2nd heating of SiC#28 LP-RFQ - short resolved 20130322_heating.png20130322_massscan_transmission.png20130322_massscan_suppression1.png20130322_suppression2.pnglegs.JPG
 

    
        
            
            Anders Mjos wrote:
Entry  Monday, March 25, 2013, 11:39, Anders Mjos, Ta#39, LP-SIS, ITW, TM1, , , Done, Ta#39 commissioning 
Target installed with 130 in lbs torque on all bolts.
Monday, March 25, 2013, 11:36: Roughing
Monday, March 25, 2013, 11:54: Starting turbos
Entry  Wednesday, April 10, 2013, 12:14, Anders Mjos, Ta#40, HP-SIS, ITE, TM4, 38295-4, , Done, Conditioning Ta#40 
 Wednesday, April 10, 2013, 12:13: Stopped turbos in preparation for venting the chamber.
Wednesday, April 10, 2013, 13:05: Venting
Wednesday, April 10, 2013, 13:37: Ta#40 installed with 130 in lbs torque on all bolts.
    Reply  Thursday, April 18, 2013, 13:50, Anders Mjos, Ta#40, HP-SIS, ITE, TM4, 38295-4, , Done, Ta#40 stored under vacuum 
Target installed at the Test Stand after an inspection in the lab. EE was cleand. All bolts torqued to 130 in lbs
Thursday, April 18, 2013, 13:48: Rouging
Thursday, April 18, 2013, 14:11: Starting turbos
Entry  Wednesday, May 29, 2013, 12:10, Anders Mjos, CTL FEBIAD, HP-FEBIAD, , , 38481-5, , Done, CTL Test Photo_2013-06-13_10_33_42_AM.jpg
Wednesday, May 29, 2013, 12:09: Debiased to insert temp logger
Wednesday, May 29, 2013, 14:40: Temp logger installed
CH1 COIL
Entry  Thursday, June 13, 2013, 10:19, Anders Mjos, , , , , , , Done, Pumping down empty chamber 
Thursday, June 13, 2013, 10:17: Roughing.
Thursday, June 13, 2013, 10:52: Turbos started
Thursday, June 13, 2013, 11:00 : Both turbos at speed.
Entry  Wednesday, July 10, 2013, 10:21, Anders Mjos, SiC#29, HP-FEBIAD-CTL, ITE, TM4, 38481-6, 39956-4, Done, Testing SiC#29 CTL Target 
Wednesday, July 10, 2013, 10:20 : Turbos off. Vacuum at 1.3 E-7 T
Wednesday, July 10, 2013, 11:23: Venting chamber 
Wednesday, July 10, 2013, 12:00: Vented
Entry  Friday, August 30, 2013, 15:09, Anders Mjos, NiO#2, HP-FEBIAD, ITE, TM3, 39530-6, 39069-4, Done, Conditioning of NiO#2 2013-09-12_NiO#2_TBHT_jump.PNG
Friday, August 30, 2013, 15:09 : Turbos stopped in preparation for installation. 
Friday, August 30, 2013, 16:22: Venting
Friday, August 30, 2013, 17:08: Roughing with NiO#2
Entry  Monday, September 16, 2013, 17:07, Anders Mjos, NiO#2, HP-FEBIAD, ITE, TM3, 39530-6, 39069-4, Done, Conditioning NiO#2 take 2 
The GE on the Source tray and EE on the target was cleaned. The target will be conditioned again to verify if sparking has been reduced. Torque 120 in
lbs
Monday, September 16, 2013, 17:05: Roughing. The roughing pump is somewhat noisy.
Entry  Wednesday, September 18, 2013, 16:18, Anders Mjos, , HP-FEBIAD, , , Tube only, 38307-9, Done, Test Target - FEBIAD COIL 
Wednesday, September 18, 2013, 16:18: Starting turbos
Wednesday, September 18, 2013, 16:26 : Turbos at speed
Wednesday, September 18, 2013, 16:28 : Vacuum at 2.8 E-5 T
Entry  Friday, September 27, 2013, 11:41, Anders Mjos, Ta#41, HP-SIS, ITW, TM4, 39069-5, 38817-10, Done, Ta#41 Conditioning Ta#41_EE_After_Test_Stand.pdf
Friday, September 27, 2013, 11:41: Roughing
Friday, September 27, 2013, 12:08: Turbos started
Friday, September 27, 2013, 12:16: Turbos at speed.
Entry  Tuesday, October 15, 2013, 16:17, Anders Mjos, , , , , , , Done, TGHT and TB HT test bar test 
HS line is looped. Cu-test bars installed on TGHT and TBHT. Torqued all bolts  to 120 in lbs.
Tuesday, October 15, 2013, 16:17: Roughing
Tuesday, October 15, 2013, 16:39: Turbos started.
Entry  Wednesday, December 18, 2013, 12:04, Anders Mjos, , , , , 40282-5, 39230-1, Done, Heating Test 
 Wednesday, December 18, 2013, 12:04: Turbos stopped
Wednesday, December 18, 2013, 13:19: Venting
Ta-tube installed. All bolts torqued to 130 in lbs
Entry  Tuesday, January 14, 2014, 08:58, Anders Mjos, , , , , 40282-5, 39230-1, Done, Heating Test 
Tuesday, January 14, 2014, 08:57: Stopping turbos. Vacuum at 1.2E-7 T
Tuesday, January 14, 2014, 13:32: Venting 
Ta-tube installed. All bolts torqued to 130 in lbs
Entry  Wednesday, March 12, 2014, 10:20, Rick Maharaj, , , , , , , Done, replace heatshield waterline loop 
A new Heatshield waterline loop was manufactured and installed to replace the old one which had a leak.
Chamber vacuum currently being roughed down.
Wednesday, March 12, 2014, 10:41: Started turbos.
Entry  Thursday, April 03, 2014, 16:46, Aurelia Laxdal, TiC#4, HP-SIS, ITE, TM3, , , Done, HV and Heaters Conditioning ITE-TM3-TiC#4-HP-SIS_Test_Stand_Conditioning.docx
HV and Heaters Conditioning had finished. The target was cooled down and it's ready for the on-line installation.
Entry  Friday, April 04, 2014, 17:01, Rick Maharaj, UC#9, LP-SIS, ITW, TM1, , 39230-3, Done, Conditioning Heatshield for UCx#9 
Friday, April 04, 2014, 16:26: Heatshield/Ionsource assembly for UC LP SIS  installed in test stand with Ta tube as heat load.
Friday, April 04, 2014, 16:29: Chamber roughing started
Friday, April 04, 2014, 16:51: Turbos started
Entry  Wednesday, April 23, 2014, 14:16, Anders Mjos, , , , , , , Done, Cu-strip cleaning test - sample #1, not cleaned Front_2014-04-24_2_05_56_PM.jpgSide_2014-04-24_2_06_12_PM.jpg
Wednesday, April 23, 2014, 14:15: Roughing
Wednesday, April 23, 2014, 14:34 : Starting turbos
Wednesday, April 23, 2014, 14:42 : Turbos at speed
Entry  Tuesday, May 20, 2014, 12:39, Anders Mjos, , , , , , , Done, FEBIAD Cathode Negative BIAS configuration 