  509   Thursday, May 12, 2016, 13:32 Aaron SchmidtSiCLP-SIS  41077-3  EE new insulator Test, No PE , Dirty EE.Thursday, May 12, 2016, 13:00: Begin Roughing.
Thursday, May 12, 2016, 13:40: Turbo
Pumps started
  
  511   Friday, June 03, 2016, 14:50 Aaron Schmidt       Pumping down empty chamber.Friday, June 03, 2016, 14:50: Turbo pumps
started.
Friday, June 03, 2016, 15:22: 
  
  512   Thursday, June 09, 2016, 14:56 Aaron Schmidt LP-SIS     TUBE ONLYThursday, June 09, 2016, 14:50: Begin roughing.
Thursday, June 09, 2016, 15:34: Turbo
pumps started.
 Tube_only_SIS_test.zip 
  513   Friday, June 10, 2016, 12:42 Anders Mjos      Problems/SolutionsFC0 BIAS probelm Graham Waters is looking into this
problem. The IOC has been rebooted a couple
of times.
  
  514   Tuesday, June 14, 2016, 10:46 Aaron Schmidt LP-SIS     TUBE ONLY - NO PLASMA ELECTRODETuesday, June 14, 2016, 10:46: Begin roughing.
Tuesday, June 14, 2016, 11:16: Turbo
pumps started.
 Tube_only_SIS_test-all-160615.zip2016-06-13.zip2016-06-15.zipre-em-plots.zip 
  515   Thursday, June 16, 2016, 14:34 Aaron Schmidt LP-SIS     TUBE ONLY (3)Thursday, June 16, 2016, 14:33: Roughing.
Plasma Electrode re-attached. Salts replaced.
Thursday, June 16, 2016, 15:12: Turbo
 Tube_only-full-fernando_test-160617-PE-RPE.zipTube_only-full-fernando_test-160617-WPE.zip 
  516   Monday, June 20, 2016, 14:36 Aaron Schmidt       Pump down empty chamber.Monday, June 20, 2016, 12:50: roughing
down
Monday, June 20, 2016, 14:30: Turbo
  
  517   Friday, June 24, 2016, 08:07 Aaron Schmidt       Emittance scanner check/repair.Friday, June 24, 2016, 08:06: Ion gauge
IG6 OFF. Turbo pumps TP6 and TP2 off.
Friday, June 24, 2016, 09:58: Venting.
  
  519   Wednesday, June 29, 2016, 16:28 Aaron Schmidt       Pump down empty chamber.Wednesday, June 29, 2016, 16:28 : Roughing

Thursday, June 30, 2016,
08:44: Turbo pumps on.
  
  520   Wednesday, July 06, 2016, 10:42 Anders Mjos      Problems/SolutionsEmittance scanner check/repair.Dave Morris increased the current from
~ 1 A to ~2.5 A. This seem to solve the problem
with the in/out drive of the emittance meter
  
  521   Monday, July 11, 2016, 13:51 Aaron Schmidt     41751-7 Tube only - NEW EE w/insulatorsMonday, July 11, 2016, 13:49: Begin roughing.



 Tube_only_test_-_with_insulators_&_new_EE_Maldonado_160712.zip160713.zip 
  522   Thursday, July 14, 2016, 13:22 Aaron Schmidt     41751-7 Tube only - NEW EE w/insulators - No PEThursday, July 14, 2016, 14:41:  Roughing
started.
Thursday, July 14, 2016, 15:41: Turbo
 Tube_only_Test_-__New_Insulators-No_PE-160715.zip160716.zip 
  523   Monday, July 18, 2016, 12:20 Aaron Schmidt     41751-7 Tube only - No EE - No PEMonday, July 18, 2016, 12:19: Roughing.
Monday, July 18, 2016, 13:13: Turbo
pumps on.
 Tube_only_-_No_EE_-_No_PE.zip 
  524   Tuesday, July 19, 2016, 15:15 Aaron Schmidt     41751-7 Tube only - No EE - With PETuesday, July 19, 2016, 15:14: Roughing.
Tuesday, July 19, 2016, 15:48: Turbo
pumps started.
 Tube_only_-_No_EE_-_With_PE.zip 
  525   Thursday, July 21, 2016, 09:51 Aaron Schmidt LP-FEBIAD     Febiad Test - NEW COIL - No PEThursday, July 21, 2016, 08:55: Roughing.
Thursday, July 21, 2016, 09:50: Turbo
pumps started.
  
  526   Thursday, July 28, 2016, 08:21 Anders Mjos      Problems/SolutionsTMS:MB1 time outFault report submitted. 9156
Thursday, July 28, 2016, 09:55: Controls
group resolved the issue by cycling the power
  
  527   Thursday, July 28, 2016, 11:12 Aaron Schmidt       Pump down empty chamber.Thursday, July 28, 2016, 10:00 Roughing.   
  529   Monday, August 08, 2016, 09:48 Aaron Schmidt    41882-441751-1 HS Test Full CleanHeat Shield Test (Fully Cleaned).
For all 6 tests:
-Start Turbo pumps & Ion gauge
 HS_41751-1_TEST.docxTS-2016-08-08-11-45.rga20160824_144103.jpg20160824_144106.jpg 
  530   Wednesday, August 10, 2016, 08:09 Aaron Schmidt    41882-441751-2 HS Test Full CleanHeat Shield Test (Fully Cleaned).
For all 6 tests:
-Start Turbo pumps & Ion gauge
 HS_41751-2_TEST.docxTS-2016-08-10-11-45.rga20160824_143539.jpg 
  531   Friday, August 12, 2016, 14:40 Aaron Schmidt      Problems/SolutionsEmittance scanner communicationsWednesday, July 27, 2016, 16:06:  Spark
around 15:10 or 16:05
Emittance rig communications affected.
  