ID |
Date |
Author |
Target/No.# |
Source |
Station |
Module |
Target Oven W.O# |
Heat Shield W.O# |
Status |
Subject |
509
|
Thursday, May 12, 2016, 13:32 |
Aaron Schmidt | SiC | LP-SIS | | | 41077-3 | | | EE new insulator Test, No PE , Dirty EE. | Thursday, May 12, 2016, 13:00: Begin Roughing.
Thursday, May 12, 2016, 13:40: Turbo Pumps started
Thursday, May 12, 2016, 13:46: Ion gauge switched on.
Friday, May 13, 2016, 08:33: Opened water supply for heat shield. Vacuum stable at 3.70E-7 T.
Device |
Temp
[C] |
Flow
[lpm] |
HS + MSP |
28.9 |
4.06 |
TBHT |
29.0 |
3.20 |
COIL + EE |
28.5 |
5.24 |
TGHT |
28.5 |
5.72 |
Friday, May 13, 2016, 10:01: Auto ramping TGHT/TBHT to 420A/220A @ 2A/min.
Friday, May 13, 2016, 13:55
Device |
Temp
[C] |
Flow
[lpm] |
HS + MSP |
33.7 |
3.95 |
TBHT |
29.8 |
3.16 |
COIL + EE |
29.0 |
5.17 |
TGHT |
30.0 |
5.72 |
Monday, May 16, 2016, 11:29:
Device |
Temp
[C] |
Flow
[lpm] |
HS + MSP |
33.7 |
4.06 |
TBHT |
29.4 |
3.18 |
COIL + EE |
28.7 |
5.18 |
TGHT |
29.8 |
5.77 |
Monday, May 16, 2016, 15:59:
Device |
Temp
[C] |
Flow
[lpm] |
HS + MSP |
33.8 |
4.02 |
TBHT |
29.9 |
3.20 |
COIL + EE |
29.1 |
5.21 |
TGHT |
30.1 |
5.77 |
Note: RGA misread.
Tuesday, May 17, 2016, 15:15:
Device |
Temp
[C] |
Flow
[lpm] |
HS + MSP |
33.8 |
4.02 |
TBHT |
30.6 |
3.29 |
COIL + EE |
29.0 |
5.16 |
TGHT |
30.1 |
5.74 |
Note: RGA Misread.
Wednesday, May 18, 2016, 14:30: IV4 open. FC0 open
Wednesday, May 18, 2016, 14:58: FC0 closed.
Device |
Temp
[C] |
Flow
[lpm] |
HS + MSP |
33.8 |
4.02 |
TBHT |
29.3 |
3.15 |
COIL + EE |
29.0 |
5.14 |
TGHT |
30.0 |
5.72 |
Thursday, May 19, 2016, 16:26:
Device |
Temp
[C] |
Flow
[lpm] |
HS + MSP |
33.8 |
4.06 |
TBHT |
29.3 |
3.15 |
COIL + EE |
28.8 |
5.17 |
TGHT |
30.0 |
5.77 |
Friday, May 20, 2016, 14:59:
Device |
Temp
[C] |
Flow
[lpm] |
HS + MSP |
33.8 |
4.02 |
TBHT |
29.6 |
3.20 |
COIL + EE |
28.8 |
5.14 |
TGHT |
30.0 |
5.79 |
Tuesday, May 24, 2016, 15:31:
Device |
Temp
[C] |
Flow
[lpm] |
HS + MSP |
33.8 |
4.02 |
TBHT |
29.9 |
3.18 |
COIL + EE |
29.0 |
5.15 |
TGHT |
30.1 |
5.72 |
Thursday, May 26, 2016, 15:18:
Device |
Temp
[C] |
Flow
[lpm] |
HS + MSP |
34.0 |
4.02 |
TBHT |
30.6 |
3.28 |
COIL + EE |
29.0 |
5.14 |
TGHT |
30.0 |
5.75 |
Friday, May 27, 2016, 15:27: IV4 Closed
Device |
Temp
[C] |
Flow
[lpm] |
HS + MSP |
33.8 |
4.02 |
TBHT |
32.2 |
3.42 |
COIL + EE |
28.7 |
5.22 |
TGHT |
29.7 |
5.77 |
Monday, May 30, 2016, 08:35:
Device |
Temp
[C] |
Flow
[lpm] |
HS + MSP |
33.8 |
4.05 |
TBHT |
29.9 |
3.25 |
COIL + EE |
28.7 |
5.18 |
TGHT |
29.7 |
5.78 |
Monday, May 30, 2016, 08:54: Auto ramp down TGHT/TBHT @ 2A/1A per min to 0A.
Tuesday, May 31, 2016, 08:25: Ion gauge off. Turbo pumps off.
Wednesday, June 01, 2016, 09:10: Venting
Wednesday, June 01, 2016, 9:45: Water lines purged, power off. |
511
|
Friday, June 03, 2016, 14:50 |
Aaron Schmidt | | | | | | | | Pumping down empty chamber. | Friday, June 03, 2016, 14:50: Turbo pumps started.
Friday, June 03, 2016, 15:22: RGA on.
Monday, June 06, 2016, 15:40: RGA still connected. OK. Screen shot saved. Vacuum @ 8.5E-07T
Wednesday, June 08, 2016, 15:26: RGA off
Wednesday, June 08, 2016, 15:29: Ion gauge off. Turbo pumps off.
Thursday, June 09, 2016, 12:44: Venting -AM |
512
|
Thursday, June 09, 2016, 14:56 |
Aaron Schmidt | | LP-SIS | | | | | | TUBE ONLY | Thursday, June 09, 2016, 14:50: Begin roughing.
Thursday, June 09, 2016, 15:34: Turbo pumps started.
Thursday, June 09, 2016, 15:42: Ion gauge on.
Friday, June 10, 2016, 08:27: RGA on.
Friday, June 10, 2016, 08:35: Water opened. RGA ok. Vacuum stable @ 1.9E-7T
Friday, June 10, 2016, 08:50: BIAS/EZL/EE to 30/13/1.5kV.
Friday, June 10, 2016, 08:52: Auto ramping TBHT only @ 2A min to 50A.
Friday, June 10, 2016, 10:02: Auto ramping TBHT only @ 1A min to 100A.
Friday, June 10, 2016, 11:14: Continue ramping to 150 A -AM
Friday, June 10, 2016, 11:28: Stopped ramping ag 110 A -AM
Monday, June 13, 2016, 08:12: Auto ramping TBHT only @ 1A min to 150A.
Monday, June 13, 2016, 09:59: Ramping to 150 A - AM
Monday, June 13, 2016, 15:51: Ramping down.
Tuesday, June 14, 2016, 07:47: IV4 Reset. Ion gauge off. Turbos off.
Tuesday, June 14, 2016, 07:52: Power/sources off. Water purged.
Tuesday, June 14, 2016, 09:20: Venting. |
513
|
Friday, June 10, 2016, 12:42 |
Anders Mjos | | | | | | | Problems/Solutions | FC0 BIAS probelm | Graham Waters is looking into this problem. The IOC has been rebooted a couple of times. |
514
|
Tuesday, June 14, 2016, 10:46 |
Aaron Schmidt | | LP-SIS | | | | | | TUBE ONLY - NO PLASMA ELECTRODE | Tuesday, June 14, 2016, 10:46: Begin roughing.
Tuesday, June 14, 2016, 11:16: Turbo pumps started.
Tuesday, June 14, 2016, 11:23: Ion gauge on.
Wednesday, June 15, 2016, 07:45: Water opened. RGA ok. Vacuum stable @ 1.9E-7T. Power/sources on.
Wednesday, June 15, 2016, 08:24: BIAS / EZL / EE to 30 / 13 / 1.5 kV
Wednesday, June 15, 2016, 08:24: Ramping TBHT to 120 A at 1 A/min
Wednesday, June 15, 2016, 10:23: EZL P/S was not on. Switched on and set to 13 kV
Wednesday, June 15, 2016, 15:05: Ramping down.
Thursday, June 16, 2016, 08:57: IV4 reset. RGA off. Ion gauge off. Turbo pumps off.
Thursday, June 16, 2016, 13:22: Water lines purged. Power/sources off. Venting. |
515
|
Thursday, June 16, 2016, 14:34 |
Aaron Schmidt | | LP-SIS | | | | | | TUBE ONLY (3) | Thursday, June 16, 2016, 14:33: Roughing. Plasma Electrode re-attached. Salts replaced.
Thursday, June 16, 2016, 15:12: Turbo pumps started.
Thursday, June 16, 2016, 15:22: Ion gauge on.
Friday, June 17, 2016, 08:32: Water opened. RGA ok. Vacuum stable @ 2.4E-7T. Power/sources on.
Saturday, June 18, 2016, 09:31: Cool down started.
Monday, June 20, 2016, 09:48: Sources/power/voltages off.
Monday, June 20, 2016, 10:06: IV4 reset. Water lines purged.
Monday, June 20, 2016, 10:11: RGA off. Ion gauge off. Turbos off.
Monday, June 20, 2016, 11:50: Venting |
516
|
Monday, June 20, 2016, 14:36 |
Aaron Schmidt | | | | | | | | Pump down empty chamber. | Monday, June 20, 2016, 12:50: roughing down
Monday, June 20, 2016, 14:30: Turbo pumps on. Ion gauge on.
Monday, June 27, 2016, 09:00: Ion gauge off. Turbo pumps off. |
517
|
Friday, June 24, 2016, 08:07 |
Aaron Schmidt | | | | | | | | Emittance scanner check/repair. | Friday, June 24, 2016, 08:06: Ion gauge IG6 OFF. Turbo pumps TP6 and TP2 off.
Friday, June 24, 2016, 09:58: Venting.
Friday, June 24, 2016, 10:17: Remove emittance scanner for inspection.
Friday, June 24, 2016, 10:20: Roughing.
Disassemble, inspect.
Move bearing along screw. Acetone to break down old grease. Wiped clean. Move bearing back and forth, use pick to remove dirt. Re-grease.
Clean, and reassemble.
Test emittance scanner (outside of vacuum) . Draw in OK. Draw out OK.
Friday, June 24, 2016, 13:35: Venting.
Install emittance scanner.
Friday, June 24, 2016, 14:10: Roughing.
Test. Draws in fine. Draw out fails 3/4 of the way back up.
Friday, June 24, 2016, 14:32: Turbo pumps started.
Friday, June 24, 2016, 14:37: Ion gauge on.
Work to continue when more information is found on emittance scanner motor & history. |
519
|
Wednesday, June 29, 2016, 16:28 |
Aaron Schmidt | | | | | | | | Pump down empty chamber. | Wednesday, June 29, 2016, 16:28 : Roughing
Thursday, June 30, 2016, 08:44: Turbo pumps on.
Thursday, July 07, 2016, 13:11: Turbo pumps off. Ion gauge off.
Monday, July 11, 2016, 12:50: Venting. ERROR on PuTTY.
Monday, July 11, 2016, 13:05: IOC WHITEOUT?
Monday, July 11, 2016, 13:25 All returned to normal. |
520
|
Wednesday, July 06, 2016, 10:42 |
Anders Mjos | | | | | | | Problems/Solutions | Emittance scanner check/repair. | Dave Morris increased the current from ~ 1 A to ~2.5 A. This seem to solve the problem with the in/out drive of the emittance meter |
521
|
Monday, July 11, 2016, 13:51 |
Aaron Schmidt | | | | | | 41751-7 | | Tube only - NEW EE w/insulators | Monday, July 11, 2016, 13:49: Begin roughing.
10 µL: K & Rb added
5 µL: Cs added
Monday, July 11, 2016, 14:59 : Turbo pumps started.
Monday, July 11, 2016, 15:33 : Ion gauge on.
Tuesday, July 12, 2016, 08:13 : RGA on.
Tuesday, July 12, 2016, 08:18 : Water, power/sources on. Vacuum stable at 3.2E-7 T. No response on RGA.
Tuesday, July 12, 2016, 08:35: Auto-ramping TBHT only @ 1A/min to 110A. EZL/EE/BIAS to 13/1.5/30 kV.
Wednesday, July 13, 2016, 08:17: Reduced TBHT to 100 A -AM
Wednesday, July 13, 2016, 18:15: Auto-cool @ 1.5A/min
Thursday, July 14, 2016, 08:20: Sources/power off
Thursday, July 14, 2016, 08:27: RGA off, IV4 closed, Ion gauge off. Turbo pumps off. Water lines closed.
Thursday, July 14, 2016, 12:57: Venting
|
522
|
Thursday, July 14, 2016, 13:22 |
Aaron Schmidt | | | | | | 41751-7 | | Tube only - NEW EE w/insulators - No PE | Thursday, July 14, 2016, 14:41: Roughing started.
Thursday, July 14, 2016, 15:41: Turbo pumps started.
Thursday, July 14, 2016, 15:58: Ion gauge & RGA on.
Friday, July 15, 2016, 08:15: Water, power/sources on. Vacuum stable at 3.9E-7 T. No response on RGA.
Friday, July 15, 2016, 08:25: Optics on. BIAS/EZL/EE to 30/13/1.5kV
Friday, July 15, 2016, 08:30: Auto-ramp TBHT to 110A @ 2A/min
Friday, July 15, 2016, 11:19; Auto-ramp TBHT to 130A @ 2A/min
Friday, July 15, 2016, 11:21: IV4 opened
Monday, July 18, 2016, 09:03: TBHT cooling started @ 2A/min
Monday, July 18, 2016, 09:04: RGA disconnected/Filament off.
Monday, July 18, 2016, 10:16: Sources off. IV4 closed. Turbo pumps off.
Monday, July 18, 2016, 11:17: Venting. Note* Global reset used each time VV1 was opened and closed. VV1 becomes non-responsive otherwise.
Monday, July 18, 2016, 11:25: Water purged. Power off/lockout. |
523
|
Monday, July 18, 2016, 12:20 |
Aaron Schmidt | | | | | | 41751-7 | | Tube only - No EE - No PE | Monday, July 18, 2016, 12:19: Roughing.
Monday, July 18, 2016, 13:13: Turbo pumps on.
Monday, July 18, 2016, 13:18: Ion gauge on.
Tuesday, July 19, 2016, 08:28: Power/Water on. No response on RGA. Vacuum stable @ 2.63E-7 T.
Tuesday, July 19, 2016, 08:43: Optics on. BIAS/EZL/EE on 30/13/0 kV. Auto-ramp TBHT to 110A @ 2 A/min.
Tuesday, July 19, 2016, 10:15: Auto-ramp TBHT to 130A @ 2 A/min.
Tuesday, July 19, 2016, 13:325: Auto-ramp down TBHT @ 2 A/min - AM
Tuesday, July 19, 2016, 13:36: Optics and BIAS / EZL / EE off -AM.
Tuesday, July 19, 2016, 14:28: Turbos off/Turbo vent.
Tuesday, July 19, 2016, 14:33: Venting.
|
524
|
Tuesday, July 19, 2016, 15:15 |
Aaron Schmidt | | | | | | 41751-7 | | Tube only - No EE - With PE | Tuesday, July 19, 2016, 15:14: Roughing.
Tuesday, July 19, 2016, 15:48: Turbo pumps started.
Tuesday, July 19, 2016, 15:55: Ion Gauge on.
Wednesday, July 20, 2016, 08:15: RGA On.
Wednesday, July 20, 2016, 08:25: Power/water on. No response on RGA. Vacuum stable @ 2.7E-7 T
Wednesday, July 20, 2016, 08:28: Sources on BIAS/EZL/EE @ 30/13/0 Kv
Wednesday, July 20, 2016, 08:31: Auto-ramping TBHT @ 2A/min.
Wednesday, July 20, 2016, 13:01: Auto-Cooling TBHT @ 3A/min.
Wednesday, July 20, 2016, 14:45: Sources off.
Wednesday, July 20, 2016, 14:47: RGA off. IV4 Closed.
Wednesday, July 20, 2016, 14:49: Turbos off.
Wednesday, July 20, 2016, 14:53: Power off. Water line purged.
Thursday, July 21, 2016, 07:52: Venting |
525
|
Thursday, July 21, 2016, 09:51 |
Aaron Schmidt | | LP-FEBIAD | | | | | | Febiad Test - NEW COIL - No PE | Thursday, July 21, 2016, 08:55: Roughing.
Thursday, July 21, 2016, 09:50: Turbo pumps started.
Thursday, July 21, 2016, 09:54: Ion Gauge on.
Thursday, July 21, 2016, 11:12: RGA on.
Thursday, July 21, 2016, 15:12: Water lines opened. No response on RGA. Vacuum stable @ 5.7E-7 T
Friday, July 22, 2016, 08:40: Opening gas lines.
Friday, July 22, 2016, 09:09: Power/Sources on. BIAS/EZL/EE @ 30/13/1.5 kV . Coil @ 50 A . Anode @ 200 V.
Friday, July 22, 2016, 09:13: IV4 open. Auto ramping TGHT/TBHT to 580/270 A @ 2A/per min.
Friday, July 22, 2016, 09:18: Heat shield flow rate @ 3.82 lpm
Friday, July 22, 2016, 12:10: TBHT ramped to 300 A -AM
Friday, July 22, 2016, 14:08: TBHT ramped to 310 A -AM
Monday, July 25, 2016, 09:39:
Device
|
Temp
[C] |
Flow
[lpm] |
HS + MSP |
38.0 |
3.82 |
TBHT |
27.9 |
2.96 |
COIL + EE |
27.7 |
4.94 |
TGHT |
29.7 |
5.51 |
Monday, July 25, 2016, 16:29: Changed the tune to improve mass resolution.
Wednesday, July 27, 2016, 14:37: Spark tripped off IG6
Wednesday, July 27, 2016, 14:38: BIAS / EZL / EE to 40 / 17.5 / 2 kV
Wednesday, July 27, 2016, 14:51: BIAS / EZL / EE to 45 / 19 / 2.5 kV
Wednesday, July 27, 2016, 15:00: BIAS / EZL / EE to 50 / 21.6 / 2.5 kV
Wednesday, July 27, 2016, 16:06: Spark around 15:10 or 16:05 knocked out magnet (RED)
Wednesday, July 27, 2016, 17:0: BIAS / EZL / EE to 30 / 13 / 1.5 kV. Ramping down target
Thursday, July 28, 2016, 08:03 : Turn off sources. Close IV4. Turn off Ion gauge. Turbos off.
Thursday, July 28, 2016, 09:09: Source gas control off. Venting.
|
526
|
Thursday, July 28, 2016, 08:21 |
Anders Mjos | | | | | | | Problems/Solutions | TMS:MB1 time out | Fault report submitted. 9156
Thursday, July 28, 2016, 09:55: Controls group resolved the issue by cycling the power on the canbus controller |
527
|
Thursday, July 28, 2016, 11:12 |
Aaron Schmidt | | | | | | | | Pump down empty chamber. | Thursday, July 28, 2016, 10:00 Roughing. |
529
|
Monday, August 08, 2016, 09:48 |
Aaron Schmidt | | | | | 41882-4 | 41751-1 | | HS Test Full Clean | Heat Shield Test (Fully Cleaned).
For all 6 tests:
-Start Turbo pumps & Ion gauge as soon as available on ISAC TEST STAND VACUUM Screen.
-Start Roughing by 10:10am +/- 1 minute and ensure previous HS started venting by 9:15am to meet timeline.
HS# 41751-1 . OR, Acetone, Methanol. TGHT only.
No insulators, bracket, or gripper arms. Blank/Plate. No source cup.
Monday, August 08, 2016, 09:58: Ta#49 removed from test stand.
Monday, August 08, 2016, 10:07: 41751-1 placed into test stand. Door open for 9 minutes.
Monday, August 08, 2016, 10:10: Roughing.
Monday, August 08, 2016, 10:18: BV1B OPEN. Opened @ 88T.
Monday, August 08, 2016, 10:40: Both Turbo pumps started.
Monday, August 08, 2016, 10:45: Ion gauge on. TP1B @ speed 42 KRPM.
Monday, August 08, 2016, 10:48: TP1A @ speed 38 KRPM.
Monday, August 08, 2016, 11:45: RGA on. Vacuum @ 2.02E-6T
Tuesday, August 09, 2016, 08:14: Water lines opened. No response on RGA. Vacuum stable @ 1.99E-7T
Tuesday, August 09, 2016, 08:19: Power/sources on.
Tuesday, August 09, 2016, 08:30: TGHT auto-ramping to 580A @ 2A/min. Vacuum stable @ 1.99E-7T
Tuesday, August 09, 2016, 11:15: Screen shots and check made @ 329-330A
Tuesday, August 09, 2016, 13:20: TGHT @ 580A. Vacuum @4.23E-7T
Tuesday, August 09, 2016, 16:00: Auto-cooling @ 2A/min. Vacuum @ 3.77E-7T
Wednesday, August 10, 2016, 08:00: Vacuum @ 1.70E-7T. RGA off. Ion gauge off. Turbos off.
Wednesday, August 10, 2016, 09:14: Venting. |
530
|
Wednesday, August 10, 2016, 08:09 |
Aaron Schmidt | | | | | 41882-4 | 41751-2 | | HS Test Full Clean | Heat Shield Test (Fully Cleaned).
For all 6 tests:
-Start Turbo pumps & Ion gauge as soon as available on ISAC TEST STAND VACUUM Screen.
-Start Roughing by 10:10am +/- 1 minute and ensure previous HS started venting by 9:15am to meet timeline.
HS# 41751-2 . OR, Acetone, Methanol. TGHT only.
No insulators, bracket, or gripper arms. Blank/Plate. No source cup.
Wednesday, August 10, 2016, 09:47: 41751-1 removed from test stand. Exchange target & End plates to 41751-2
Wednesday, August 10, 2016, 10:07: 41751-2 placed into test stand. Door open for 20 minutes.
Wednesday, August 10, 2016, 10:10: Roughing.
Wednesday, August 10, 2016, 10:13: Doors finally sealed for roughing.
Wednesday, August 10, 2016, 10:23: BV1B OPEN. Opened @ 59T.
Wednesday, August 10, 2016, 10:45: Both Turbo pumps started.
Wednesday, August 10, 2016, 10:50: Ion gauge on. TP1B @ speed 42 KRPM.
Wednesday, August 10, 2016, 10:53: TP1A @ speed 38 KRPM
Wednesday, August 10, 2016, 11:45: RGA on. Vacuum @ 3.56E-6T
Thursday, August 11, 2016, 08:16: Water lines opened. No response on RGA. Vacuum stable @ 2.34E-7T
Thursday, August 11, 2016, 08:19: Power/sources on
Thursday, August 11, 2016, 08:30: TGHT auto-ramping to 580A @ 2A/min. Vacuum stable @ 2.36E-7T
Thursday, August 11, 2016, 11:15: Screen shots and check made @ 329-330A.
Thursday, August 11, 2016, 13:25: TGHT @ 580A. Vacuum @4.16E-7T
Thursday, August 11, 2016, 15:54: Screen shots and check made @ 580A. Vacuum @4.43E-7T and increasing. Cool in Am.
Friday, August 12, 2016, 08:30: Auto-cooling started @ 2A/min. Vacuum @ 3.88E-7T
Friday, August 12, 2016, 13:20: Cooling Complete. Vacuum @ 2.16E-7T.
Friday, August 12, 2016, 13:33: Water lines purged. Power/sources off.
Monday, August 15, 2016, 08:07: Turbo pumps, Ion gauge, and RGA off.
Monday, August 15, 2016, 09:14: Venting. |
531
|
Friday, August 12, 2016, 14:40 |
Aaron Schmidt | | | | | | | Problems/Solutions | Emittance scanner communications | Wednesday, July 27, 2016, 16:06: Spark around 15:10 or 16:05
Emittance rig communications affected.
Enter 100 on Dac -- Reads: -500
Enter -100 on Dac -- Reads: -500. No response
@ 10V
Friday, August 12, 2016, 15:53: Soft reboot on Emittance rig communications
Calibrate
test scan & park
Enter: 100 on Dac -- Reads 100
Enter: 200 on Dac -- Reads 200
Enter: 0 on Dac -- Reads 0
Enter: -200 on Dac -- Reads -200
Fixed |
|