Entry  Tuesday, January 02, 2018, 09:18, Anders Mjos, , , , , , , Problems/Solutions, Starting system 
Tuesday, January 02, 2018
Cycled power for TCSIOC and PLCIOC
TP2 and TP6 started
Entry  Thursday, December 21, 2017, 15:12, Anders Mjos, , , , , , , , Powered down devices 
Powered down vacuum gauge and turbo pump controllers
Entry  Wednesday, December 20, 2017, 09:11, Aaron Schmidt, , LP-SIS, , , (Blank), 42752-3, Done, Holiday Shut Down 
Power/sources already off. The water cooling is currently left on.
Wednesday, December 20, 2017, 09:07: RGA off.
Wednesday, December 20, 2017, 09:08: Both Ion gauges and all 4 turbo pumps off.
Entry  Tuesday, December 12, 2017, 08:32, Aaron Schmidt, , LP-SIS, , , (Blank), 42752-3, Done, Pump down w/ possible outgas Empty_Chamber_-_Silver_bolts_removed.docxTS-2017-12-12-09-00.rgaTS-2017-12-13-06-50.rga
Check achievable vacuum. Watch for spikes on RGA. Silver bolts removed from the chamber. Vented steel screws in.
Tuesday, December 12, 2017, 08:23: Doors open from previous test. (Open for 7 minutes)
Tuesday, December 12, 2017, 08:30: Doors closed. Roughing.
Entry  Monday, December 04, 2017, 08:29, Aaron Schmidt, , , , , , , Problems/Solutions, Power outage 20171205_103324.jpg
Power outage over the weekend. Reboot PLC and systems.
Monday, December 04, 2017, 08:22: Turbo pumps TMS:TP6 & TP2 Restarted.
Monday, December 04, 2017, 08:28: Time out on turbo pump TP1B.
Entry  Friday, December 01, 2017, 14:31, Aaron Schmidt, , LP-SIS, , , (Blank), 42752-3, In progress, Silver plated bolts test / Outgas TS 1st_silver_bolts_test.docxTS-2017-12-05-08-10.rga
Chamber 'open state, no turbos' 2 weeks. Testing Silver plated 3/8"-16x1" (SCR, SHC, 18-8, AG) bolt on the TBHT.
Friday, December 01, 2017, 14:26: Roughing. BV1B open.
Friday, December 01, 2017, 14:27: BV1A open
Entry  Wednesday, November 15, 2017, 10:56, Aaron Schmidt, , , , , , , Problems/Solutions, TMS:TP6 replacement 
Turbo pump TP6 requires replacement.
Wednesday, November 15, 2017, 09:55: Turbo (TP2) off. Ion gauge off.
Wednesday, November 15, 2017, 10:55: Venting
Entry  Monday, October 30, 2017, 08:54, Anders Mjos, , , , , , , Problems/Solutions, TMS:TP6 shut down due to high noise 
The turbo pump will need replacement.
Entry  Tuesday, October 24, 2017, 11:38, Anders Mjos, , , , , , , , FEBIAD coil magnetic field measurment FEBIAD_Coil_Field_Measurement_2017-10-25.xlsx171025-First-Run.xlsx
with Fernando
Tuesday, October 24, 2017: Testing setup with triple coil
Wednesday, October 25, 2017: Field mapping at 70 A and current/field measurements on triple coil.
Entry  Monday, October 16, 2017, 11:46, Aaron Schmidt, , , , , , , In progress, Pump down empty chamber Test EE 
Monday, October 16, 2017, 11:45: Roughing.
Monday, October 16, 2017, 12:05: Turbo pumps started.
Monday, October 16, 2017, 12:10; Ion gauge on.
Entry  Friday, October 13, 2017, 15:53, Aaron Schmidt, SiC#37, HP-FEBIAD, ITE, TM4, 39530-10, 41751-4, In progress, Conditioning SiC#37 (ii) 10x
Previous short fixed. Grid clamp removed. Grid tack welded.
Friday, October 13, 2017, 15:49: Roughing.

By Anders
Entry  Tuesday, October 10, 2017, 14:56, Aaron Schmidt, , , , , , , In progress, FEBIAD Anode bias configuration 
Unable to hold Anode voltage after power supply change out.
Tuesday, October 10, 2017, 14:55: The Test Stand has been configured for Anode bias and the electrical connections have been wired according  to ISK4523D
REV 6.
Entry  Tuesday, October 10, 2017, 13:10, Aaron Schmidt, , , , , , , , Gas bottles 
Tuesday, October 10, 2017, 09:30:  Install/swap gas bottles. Elog.
Removed smallest Neon leak. Neon Bottle Serial #11231. Leak rate calibrated @ 1.59e-07 atm*CC/sec (02/09/2016)
In use:
Entry  Friday, October 06, 2017, 12:14, Aaron Schmidt, SiC#37, HP-FEBIAD, ITE, TM4, 39530-10, 41751-4, In progress, Conditioning SiC#37 9x
NOTE* : The right coil terminal terminates into the heat shield. DO NOT TURN ON COIL.
Friday, October 06, 2017, 12:12: Roughing. * Note on installation. Middle TBHT prong 'stuck' to insulator slightly and was moved to fit. Fit ok
in Jig.
Entry  Monday, September 25, 2017, 14:10, Aaron Schmidt, , , , , , , , Pump down empty chamber 
Monday, September 25, 2017, 14:10: Roughing.

Wednesday, September 27, 2017, 08:23: Turbo pumps on

Friday, October 06, 2017, 09:04: Ion gauge off. Turbos off.
Entry  Wednesday, September 20, 2017, 14:11, Aaron Schmidt, Ta#54, HP-SIS, ITW, TM2, 42218-10, , In progress, Conditioning Ta#54 6x
Wednesday, September 20, 2017, 14:08: Roughing.
Wednesday, September 20, 2017, 14:28: Turbos on.
Wednesday, September 20, 2017, 14:33: Ion gauge on.
Entry  Thursday, August 17, 2017, 12:45, Anders Mjos, , , , , , , Problems/Solutions, TBHT power supply removed  
 The Xantrex 10V 600 A power supply for the TBHT has been moved to ITE to replace the failed TGHT power supply
    Reply  Monday, August 21, 2017, 16:20, Anders Mjos, , , , , , , Problems/Solutions, TBHT power supply removed  


    
        
            Anders Mjos wrote:
        
        
            
             The Xantrex 10V 600 A power supply for the TBHT has been moved to ITE to replace the failed TGHT
Entry  Tuesday, August 15, 2017, 08:41, Aaron Schmidt, Ta#55, LP-SIS, , , 42218-11, 42738-2, In progress, TBHT sight in test 
Heat TGHT to 580 A & TGHT to  200 A for view port test.
Tuesday, August 15, 2017, 08:40: Roughing.
Tuesday, August 15, 2017, 08:59: Both Turbo pumps started.
Entry  Thursday, August 03, 2017, 17:00, Anders Mjos, , , , , , , Problems/Solutions, Vacuum system tripped on power interruption 
 Thursday, August 03, 2017, 17:00: Restarted TPs
Entry  Wednesday, July 19, 2017, 09:13, Aaron Schmidt, Ta Targets, , , , , , Done, Ion Peaks Magnet_peaks.xlsx
Attached is a recent list of Ta targets with their extracted ions peaks.