375
|
Thursday, May 08, 2014, 15:09 |
Anders Mjos | | | | | | | Problems/Solutions | SOURCES archiver reported stopped | Archiver restarted. |
|
309
|
Monday, June 03, 2013, 15:00 |
Anders Mjos | | | | | | | Problems/Solutions | SOURCES ARCH Restarted | SOURCES ARCH was found not running |
|
1041
|
Tuesday, December 17, 2024, 09:46 |
Dave Neilson | | | | | | 45235-26 | In progress | SIS P2N source cup testing | Monday, December 16, 2024, 3:34 Target
loaded in test stand. Confirmed correct connection
to mass marker power supply through multipin. |
|
457
|
Monday, July 13, 2015, 17:19 |
Anders Mjos | | LP-SIS | | | | | In progress | SIS Cup insulator clamping test | Monday, July 13, 2015, 17:09: Roughing
Monday, July 13, 2015, 17:51: Turbos
started |
|
640
|
Monday, February 26, 2018, 09:13 |
Carla Babcock | | | | | | | | Running list of changes to the ISAC test stand for >60kV operation | 1. Al corona shield installed over end
of the HV duct to suppress discharges from
the sharp edge of the duct. |
6x |
264
|
Wednesday, January 09, 2013, 14:13 |
Anders Mjos | Empty | | | | | | | Rouging | Wednesday, January 09, 2013, 14:12: Roughing
empty chamber |
|
805
|
Wednesday, August 05, 2020, 10:01 |
Aaron Schmidt | | | | | | | Problems/Solutions | Roughing pump swap out. | Wednesday, August 05, 2020, 10:00: TP6
& TP2 off. IG6 off.
Wednesday, August 05, 2020, 12:20: |
|
655
|
Tuesday, April 17, 2018, 11:02 |
Aaron Schmidt | | | | | | | Done | Roughing pump issue. | Tuesday, April 17, 2018, 10:57: Vacuum
not coming down. @ 1.514T . Backing valves
have been closed. |
|
181
|
Thursday, August 23, 2012, 11:59 |
Anders Mjos | | | | | | | Problems/Solutions | Roughing blows the fuse for both roughing pumps. | The fuse for both roughing pumps blows
when roughing the chamber. With the help
from Edi: disconnect the exhaust port on |
|
968
|
Thursday, May 25, 2023, 13:47 |
Aaron Schmidt | | | | | | | | Rough down empty chamber | Thursday, May 25, 2023, 13:47: Roughing. |
|
970
|
Thursday, June 08, 2023, 14:22 |
Aaron Schmidt | | | | | | | | Rough down empty chamber | Thursday, June 08, 2023, 14:22: Roughing. |
|
473
|
Thursday, October 15, 2015, 11:19 |
Anders Mjos | | | | | | | Problems/Solutions | Right side TGHT connector block removed | The keensert has been worn out and will
be replaced.
The keensert was re-tapped and the |
|
756
|
Thursday, August 29, 2019, 14:47 |
Fernando Maldonado | | | | | | Ferran's heat shield | Problems/Solutions | Rewiring-Baking out | Thursday, August 29, 2019, 14:47 : Changing
back to the nominal wiring
Thursday, August 29, 2019, 17:01: |
|
1025
|
Wednesday, October 09, 2024, 13:29 |
Dave Neilson | | | | | 44691-8 | 45235-26 | | Retainer tests - with mass marker target | Wednesday, October 09, 2024, 11:28
Target loaded, remote power supply
added for mass marker, negative channel on |
|
140
|
Wednesday, July 11, 2012, 15:30 |
Anders Mjos | | | | | | | Problems/Solutions | Restarting turbos after power bump | Wednesday, July 11, 2012, 15:27: Started
TSGTP1A and 1B
Wednesday, July 11, 2012, 15:31: |
|
281
|
Monday, March 04, 2013, 09:11 |
Anders Mjos | | | | | | | Problems/Solutions | Restarted turobos after planned power outage | Started archivers
Started turbos
Switched on ion gauges |
|
255
|
Wednesday, December 19, 2012, 11:24 |
Anders Mjos | | | | | | | Problems/Solutions | Restarted turbos in TMS section after power bump | Sources arch restared |
|
460
|
Saturday, August 29, 2015, 14:33 |
Anders Mjos | | | | | | | Problems/Solutions | Restarted IOC after power outage | Saturday, August 29, 2015, 15:50:
Turbos started |
|
836
|
Monday, January 04, 2021, 08:17 |
Aaron Schmidt | | | | | | | | Restart TS | Restarting TS after holidays & planned
power outage.
Monday, January 04, 2021, 08:17: |
|
455
|
Monday, July 06, 2015, 09:29 |
Anders Mjos | | | | | | | Problems/Solutions | Replaced out gassing gauge on the backing line | |
|