289
|
Thursday, March 28, 2013, 13:55 |
Anders Mjos | Empty | | | | | | In progress | Pumping down empty chamber | Thursday, March 28, 2013, 13:55: Roughing
Thursday, March 28, 2013, 14:36: Starting turbos (vacuum at ~0.100 T)
Thursday, March 28, 2013, 14:44: Both turbos at speed
Thursday, March 28, 2013, 14:46: Vacuum at 5.2E-6 Torr |
296
|
Thursday, April 25, 2013, 13:32 |
Anders Mjos | Empty | LP-FEBIAD | | | Tube Only | 38307-9 | In progress | FEBIAD Coil test | Same target as in e-log entry https://elog.triumf.ca/TIS/Test-Stand/106
Thursday, April 25, 2013, 13:54: Roughing
Thursday, April 25, 2013, 14:25: Started turbos
Thursday, April 25, 2013, 14:33: Turbos at speed
Thursday, April 25, 2013, 14:33: Vacuum at 8.8E-6 T
Friday, April 26, 2013, 08:25: Cooling water supply opened. Vacuum stable at 2.2E-7 T
Friday, April 26, 2013, 13:35: Gas lines evacuated.
Testing Coil current vs Temperature before heating
COIL:RDCUR at 1.95A
COIL:RDVOL at 1.47V
COIL T/C at 86 deg C and still slowly increasing
Tuesday, April 30, 2013
Testing Coil current vs Temperature before heating
COIL:RDCUR at 3.96A
COIL:RDVOL 3.2 V Vacuum starts to increase (base 1.4E-7
COIL:RDVOL 3.8 V T/C at 150 C vacuum at 5E-7
COIL:RDCUR at 3.47A to reduce out-gassing T/C at 175 C
Tuesday, April 30, 2013, 12:39
COIL:RDCUR at 3.96A T/C 225 C
COIL:RDVOL 5.0 V T/C at 250 C vacuum at 6.2E-7
Tuesday, April 30, 2013, 13:00
COIL:RDCUR at 4.25A COIL:RDVOL at 5.7V T/C 290 C
Tuesday, April 30, 2013, 13:10
COIL:RDCUR at 4.15A COIL:RDVOL at 5.75V T/C 310 C
Tuesday, April 30, 2013, 14:53
COIL:RDCUR at 4.15A COIL:RDVOL at 5.85V T/C 320 C
Tuesday, April 30, 2013, 16:30
COIL:RDCUR at 4.15A COIL:RDVOL at 5.89V T/C 328 C
Wednesday, May 01, 2013, 08:16
COIL:RDCUR at 4.15A COIL:RDVOL at 5.95V T/C 350 C - P/S is voltage limited at 5.95V
Ramping down current to 0. T/C logger is required elsewhere.
Friday, May 03, 2013, 12:07: Pumping out gas line through vacuum chamber.
The anode cable has been reconnected (see e-log entry 297)
Friday, May 03, 2013, 14:17: BIAS and EE to 30kV and -800V
Friday, May 03, 2013, 14:24: Started heating TBHT to 280A at 1A/min
Monday, May 06, 2013, 08:46: TBHT @ 276A, Voltage limiting at 2.5V. Increased limit to 2.7V. TGHT to 280A and 2.52V. COIL temp ~100C
Monday, May 06, 2013, 09:48: COIL:RDCUR at 2.93A
Monday, May 06, 2013, 10:34: Coil temp ~240C. Increasing COIL:RDCUR to 3.52A COIL:RDVOL at 4.1V
Monday, May 06, 2013, 11:48: Coil temp 330C COIL:RDCUR at 3.52A RDVOL at 4.9V
Monday, May 06, 2013, 11:54: COIL:RDCUR at 3.9A
Monday, May 06, 2013, 12:56: RDVOL at 5.9V. Coil temp ~380C
Monday, May 06, 2013, 13:47: Cooling down target to correct anode connection.
Tuesday, May 07, 2013, 08:47: De-biased
Tuesday, May 07, 2013, 10:06: Corrected el. connections to cathode floating. Started tube heating to 280A
Wednesday, May 08, 2013, 12:12: De-biased
Wednesday, May 08, 2013, 12:12: Cooling down cathode 1A/min
Thursday, May 09, 2013, 15:22: TPS:IV4 closed |
Attachment 1: 2014-04-30_FEBIAD_COIL_AWG18.PNG
|
|
Attachment 2: 2014-05-01_FEBIAD_COIL_AWG18.PNG
|
|
Attachment 3: Target_Assembly.pdf
|
|
323
|
Friday, July 19, 2013, 14:14 |
Anders Mjos | | | | | Tube only | 38307-9 | In progress | FEBIAD Coil Test | Friday, July 19, 2013, 14:14 : Stopping Turbos. Vacuum at 1.3E-7 T
Friday, July 19, 2013, 15:14: Venting
Friday, July 19, 2013, 16:22: Target installed. Roughing.
Friday, July 19, 2013, 16:41: Starting turbos
Friday, July 19, 2013, 16:49: Turbos at speed
Friday, July 19, 2013, 16:51 : Vacuum at 1.4E-5 T
Monday, July 22, 2013, 08:19: Opened up water flow. Vacuum stable at 1.3E-7 T after some minor bumps to 1.6E-7 T
Monday, July 22, 2013, 13:34: T/C logger installed on 9-pins 4 & 5. Ray is working in the HV cage to install a different PS for the magnet coil.
Monday, July 22, 2013, 14: Increasing Coil current manually. Vacuum starts to creep up at 3A (T/C around 85 deg C).
Monday, July 22, 2013, 16:37: Current at 4A. Voltage at 6.5V. T/C around 400 deg C.
Tuesday, July 23, 2013, 08:50: Coil conditioned to ~500 deg C at about 4.7A
Tuesday, July 23, 2013, 08:54: Evacuating gas line through the chamber.
Tuesday, July 23, 2013, 09:01: Gas lines evacuated.
Tuesday, July 23, 2013, 09:10: Coil current to zero.
Tuesday, July 23, 2013, 09:22: Target. biased
Tuesday, July 23, 2013, 09:22: Opened IV4
Tuesday, July 23, 2013, 09:32: ANODE to 200V. Helium leak to 6.0
Tuesday, July 23, 2013, 09:35: Coil temp at 220 deg C.
Tuesday, July 23, 2013, 10:58: Heating aborted at 200A. Will resume later.
Tuesday, July 23, 2013, 12:01: Restarted heating to 250A.
Tuesday, July 23, 2013, 13:11: Spark too out some optics. Restarted.
Tuesday, July 23, 2013, 14:39: COIL 130 deg C. TBHT at 280A read back.
Tuesday, July 23, 2013, 14:44: Sparking occurs across the spark gap on top of the test stand.
Tuesday, July 23, 2013, 16:14: Lowered TBHT to 270 read back. Will leave it like this over night.
Friday, July 26, 2013, 10:09: Cooling down TBHT.
Friday, July 26, 2013, 11:13: ANODE and COIL OFF. Closed IV4. Closed gas supply.
Friday, July 26, 2013, 12:41: BIAS, EE and EL to zero.
Data on Docushare:
https://documents.triumf.ca/docushare/dsweb/View/Collection-11041 |
325
|
Tuesday, August 20, 2013, 08:24 |
Anders Mjos | | | | | Tube only | 38307-9 | In progress | FEBIAD Coil Test | Tuesday, August 20, 2013, 08:13: Roughing gas lines
Tuesday, August 20, 2013, 08:22: Gas lines roughed. Valve closed |
349
|
Wednesday, December 04, 2013, 09:22 |
Anders Mjos | | | | | | | In progress | Testing impedance with the new TBHT P/S | Wednesday, December 04, 2013, 09:21 : Turbos stopped. Vacuum at 1.2E-7 Torr
Wednesday, December 04, 2013, 12:35: Venting
Copper bars installed w/ 130 in lbs torque
Wednesday, December 04, 2013, 13:06: Roughing
Wednesday, December 04, 2013, 15:16: Turbos started. Vacuum at 0.03 Torr
Wednesday, December 04, 2013, 15:23: Turbos at speed.
Wednesday, December 04, 2013, 15:26: Vacuum at 5E-6 Torr
Thursday, December 05, 2013
Impedance measured on TGHT and TBHT (~2.5 mOhm and ~2.0 mOhm). Readback on TBHT gives an impedance of ~2.5 mOhm. This is higher than the previous test. Local current on TBHT shows 60A more than the readback at 300A. The vacuum did not come down as low as usual, which likely means there is a leak.
Thursday, December 05, 2013, 13:15: Turbos stopped.
Friday, December 06, 2013, 13:11: Venting
Gaskets on doors cleaned.
Friday, December 06, 2013, 13:40: Roughing
Friday, December 06, 2013, 13:59: Starting turbos
Friday, December 06, 2013, 14:07: Turbos at speed.
Friday, December 06, 2013, 14:09: Vacuum at 1.4 E-5 Torr
Monday, December 09, 2013, 08:46: Vacuum at 2.0 E-5 Torr |
360
|
Wednesday, February 12, 2014, 09:01 |
Anders Mjos | | | | | | | In progress | Testing Cleaning sample | Wednesday, February 12, 2014, 08:55: Stopped turbos
Wednesday, February 12, 2014, 11:28: Venting
Installed one sample. No cleaning. Connection tabs wiped with alcohol to prevent making the source tray dirty.
Wednesday, February 12, 2014, 13:17: Started roughing
Wednesday, February 12, 2014, 13:38: Started turbos
Wednesday, February 12, 2014, 13:42: TP1B at speed. Vacuum at 5.4E-5 T
Wednesday, February 12, 2014, 13:46: TP1A at speed. Vacuum at 1.9E-5 T
Wednesday, February 12, 2014, 13:48: Vacuum at 1.7E-5 T
EPICS white-out due to ER0 activity. Graham assisted in getting the system back up.
Wednesday, February 12, 2014, 15:16 : Vacuum at 4.8E-6 T
Friday, February 27, 2014
Leak checked doors. No leak found.
Friday, February 28, 2014, 08:42: Opened up water supply. Major vacuum response.
Friday, February 28, 2014, 08:42: Stopped turbos
Friday, February 28, 2014, 10:19: Venting
Removed cleaning sample.
Friday, February 28, 2014, 11:38: Pumping down empty chamber
Friday, February 28, 2014, 11:56 : Starting Turbos
Friday, February 28, 2014, 12:05 : Turbos at speed
Friday, February 28, 2014, 12:06: Vacuum at 1.7E-5 T
Monday, March 03, 2014, 09:28 : Vacuum leak on waterline (HS) still present. Stopping turbos for investigation.
Tuesday, March 04, 2014, 09:58: Venting
Replaced Cu-gaskets with Parker SST gaskets.
Tuesday, March 04, 2014, 11:03: Roughing
Tuesday, March 04, 2014, 11:26: Starting Turbos
Tuesday, March 04, 2014, 11:35: Turbos at speed. (TP1A timed out once)
Tuesday, March 04, 2014, 11:36: Vacuum at 1.6E-5 T
Thursday, March 06, 2014, 08:21: Vacuum leak no waterline (HS) still present. Stopping turbos. |
364
|
Monday, March 17, 2014, 19:10 |
Anders Mjos | Ta#42 | LP-SIS | ITW | TM4 | 40282-1 | 39956-1 / 39956-9 (base / lid) | In progress | Conditioning | NOTE:
TBHT Power Supply is 600A. EPICS thinks it is 500. Multiply current setting with 1.2 for actual current to the tube.
Time stamp on OM-DAQPRO-5300 is on hour behind (daylight savings).
All bolts torqued to 130 in lbs. TGHT and TBHT bolts tightened and loosened 3x.
Monday, March 17, 2014, 19:10: Roughing
Monday, March 17, 2014, 19:30: Turbos started
Monday, March 17, 2014, 19:38: Turbos at speed.
Monday, March 17, 2014, 19:40: Vacuum at 1.3E-5 T
BY R.M.
Tuesday, March 18, 2014, 10:10: Vacuum 2.87e-07 T
Tuesday, March 18, 2014, 10:12: Heatshield Water Circuit turned on
Tuesday, March 18, 2014, 10:25: Vacuum 2.85e-07 T
By AM
Tuesday, March 18, 2014, 16:06:
Conditioned high voltage BIAS to 30kV. BIAS:RDCUR 37 uA.
Started heater auto-ramping. TBHT to 50A at 1A/min. TGHT to 100A at 2 A/min.
Vacuum at 2.7E-7 T
Tuesday, March 18, 2014, 17:06: TBHT and TGHT reached 50A and 100A respectively. Local readback on TBHT is 58A (as expected - see note above). Vacuum is gradually coming down.
Operation stable over night. TSG:CBC needed to be restarted. Switched off over night.
Wednesday, March 19, 2014, 08:21: Continue heating to 85A / 250 A TBHT/TGHT.
Wednesday, March 19, 2014, 09:12
Water temperatures 27 - 28 deg C, and flow Rates
4.0 l/m HS+MSP
6.4 l/m TBHT
5.1 l/m COIL+EE
5.6 l/m TGHT
Wednesday, March 19, 2014, 09:57: Continue heating to 170 A / 500 A, TBHT/TGHT
Wednesday, March 19, 2014, 09:58: Opened IV4
Wednesday, March 19, 2014, 09:58: Restarted Q1.
Wednesday, March 19, 2014, 10:11: Switched FC0 bias to negative
Wednesday, March 19, 2014, 10:30: Q1 restarted. Possible spark. Small vacuum response on IG1
Wednesday, March 19, 2014, 10:49: Some sparking
Wednesday, March 19, 2014, 12:43: Continue heating to 190A / 580 A TBHT/TGHT.
Wednesday, March 19, 2014, 13:00: TBHT voltage limited. Increased limit to 2.3V
Water temperatures and flow rates
35 C 4.0 l/m HS+MSP
28 C 6.4 l/m TBHT
28 C 5.1 l/m COIL+EE
30 C 5.6 l/m TGHT
Wednesday, March 19, 2014, 13:32: Local read back on PS: 223A / 580A TBHT/TGHT
Water temperatures and flow rates
37 C 4.0 l/m HS+MSP
28 C 6.4 l/m TBHT
29 C 5.1 l/m COIL+EE
31 C 5.6 l/m TGHT
Wednesday, March 19, 2014, 14:30: Measured ~2E-7 A 23Na on FC6 and 2E-7 A on FC0. Vacuum on IG1 4.2E-8 T
Wednesday, March 19, 2014, 14:58: TBHT was voltage limiting. Increased voltage limit to 2.4 V
Target will condition over night.
Thursday, March 20, 2014, 10:07: Measured ~1.4E-8 A 23Na on FC6 and 2E-7 A on FC0. Vacuum on IG1 8.3E-7 T
Water temperatures and flow rates
35 C 4.0 l/m HS+MSP
27 C 6.4 l/m TBHT
27 C 5.1 l/m COIL+EE
29C 5.6 l/m TGHT
Thursday, March 20, 2014, 10:13: Starting mass scan 200 - 0
Local current on PS (TBHT/TGHT): 227 A / 580 A
At about 10:15 to 10:20 the TGHT:RDVOL dropped from 7.2 - 7.1 V.
Thursday, March 20, 2014, 11:05: Mass scan finished.
Water temperatures and flow rates
36 C 4.0 l/m HS+MSP
28 C 6.4 l/m TBHT
29 C 5.1 l/m COIL+EE
30 C 5.6 l/m TGHT
Thursday, March 20, 2014, 13:20
Water temperatures and flow rates
34.8 C 4.0 l/m HS+MSP
26.1 C 6.4 l/m TBHT
26.8 C 5.1 l/m COIL+EE
28.4 C 5.6 l/m TGHT
Thursday, March 20, 2014, 13:24: Conditioning EE to -2kV
Thursday, March 20, 2014, 13:26: EE at -2kV and 694 uA
Thursday, March 20, 2014, 13:36: Lowering EE back to -1.4kV
Thursday, March 20, 2014, 13:38: Starting the cool down of the target at 2 A/min
Thursday, March 20, 2014, 15:08: Closed IV4
Friday, March 21, 2014, 08:32: Lowered BIAS, EE and EZL to 0. TGHT and TBHT off.
Friday, March 21, 2014, 08:33: Stopped turbos. Vacuum at 1.3E-7 T
Friday, March 21, 2014, 13:10: Venting |
Attachment 1: Ta#42_Test_Stand.docx
|
Attachment 2: OMEGA_OM-DAQPRO-5300_21-Mar-14_13.56.35.dlp
|
365
|
Friday, March 21, 2014, 13:55 |
Anders Mjos | | | | | | | In progress | Pumping down empty chamber | Roughing
Friday, March 21, 2014, 13:59: Starting turbos
Friday, March 21, 2014, 14:08: Turbos at speed
Friday, March 21, 2014, 14:09: Vacuum at 7.5 E-6T |
367
|
Friday, March 28, 2014, 10:39 |
Anders Mjos | TiC#4 | HP-SIS | ITE | TM3 | | | In progress | Conditioning TiC#4 | NOTE:
TBHT Power Supply is 600A. EPICS thinks it is 500. Multiply current setting with 1.2 for actual current to the tube.
Friday, March 28, 2014, 10:38: Stopped turbos. Vacuum at 1.3E-7 T
Friday, March 28, 2014, 15:05: Venting
By RM
Friday, March 28, 2014, 15:22: Target assembly installed
Friday, March 28, 2014, 15:43: Chamber Roughing started
Friday, March 28, 2014, 15:58: Turbos started
Friday, March 28, 2014, 16:03: TP1B at speed
Friday, March 28, 2014, 16:06: TP1A at speed
Friday, March 28, 2014, 16:07: IG1 Turned on - reading 1.29e-05T
By R.M.
Monday, March 31, 2014, 09:55: Water to heatshield line turned on, no change in vacuum: 1.31e-07 T
|
368
|
Tuesday, April 01, 2014, 11:09 |
Aurelia Laxdal | TiC#4 | HP-SIS | ITE | TM3 | | | In progress | HV and Heaters Conditioning | Started March 31, 2014:
- did the HV conditioning up to 30kV.
April 1, 2014:
- started the Heaters Conditioning.
Heaters Conditioning finished.
The Power Supplies front panel:
TGHT: 5.56V and 580A
TBHT: 2.23V and 227A
April 2, 2014:
- did a mass scan. NOTE: data is shifted by 10-15%.
plotdump-local-clean.txt_Apr2_14_16-33-19.txt
After the scan finished I found the Test Stand EPICS screens whited-out. Decided with Friedhelm to leave it as it was for the night and to contact Controls next day to reboot it without tripping the heaters and the HV.
April 3, 2014:
Found everything recovered. Except: “SOURCES ARCH IS RUNNING” was red. So, I restarted it. Jane Richards and Friedhelm didn’t do any IOC reboot. Also found that the data from yesterday’s scan was saved (see the previous scan).
Did another mass scan: plotdump-local-clean.txt_Apr3_14_10-18-13.txt
NOTE: data is shifted by 10-15%.
Cooling down .
|
Attachment 1: ITE-TM3-TiC#4-HP-SIS_Test_Stand_Conditioning.docx
|
370
|
Friday, April 04, 2014, 08:24 |
Anders Mjos | TiC#4 | HP-SIS | ITE | TM3 | | | In progress | Venting |
Aurelia Laxdal wrote: |
HV and Heaters Conditioning had finished. The target was cooled down and it's ready for the on-line installation.
|
Friday, April 04, 2014, 08:23: Target bias, EE and EZL to zero. Turbos off.
Friday, April 04, 2014, 10:14: Venting
Friday, April 04, 2014, 10:48: Target removed - By R.M. |
374
|
Monday, April 28, 2014, 10:23 |
Anders Mjos | | | | | | | In progress | Cu-strip cleaning test - sample #2, cleaned | Monday, April 28, 2014, 10:23: Started roughing
Monday, April 28, 2014, 10:48: Started turbos. CG1 at ~0.3 T
Monday, April 28, 2014, 10:56 : Turbos at speed
Monday, April 28, 2014, 10:58 : Vacuum at 7.2E-6 T
Tuesday, April 29, 2014, 09:15: Vacuum over night was somewhat erratic with a couple of excursions. Venting to redo door seal and inspect chamber.
Tuesday, April 29, 2014, 13:18: Venting
Aborted venting.
Wednesday, April 30, 2014, 10:15: Vented. Cleaned front door o-ring and groove. Inspected VCR joint on HS water loop. No visible issues.
Wednesday, April 30, 2014, 10:15: Roughing
Wednesday, April 30, 2014, 10:35 : Starting turbos
Wednesday, April 30, 2014, 10:44 : Turbos at speed
Wednesday, April 30, 2014, 10:45 : Vacuum at 6.5E-6 T
Thursday, May 01, 2014, 08:44: Vacuum erratic over night. Small burst of pressure increase in vacuum with ~2 hours intervals. Leak found on HS cooling circuit by purging the water line.
Thursday, May 01, 2014, 08:46: Stopping turbos. Vacuum at 2.7E-7 T
HS water line should be purged again before breaking VCR seal.
Thursday, May 01, 2014, 09:59: Venting
Thursday, May 01, 2014, 10:45: Removed HS loop.
Thursday, May 01, 2014, 10:45: Roughing
Thursday, May 01, 2014, 11:11: Starting turbos. CG1 ~ 0.1 T
Thursday, May 01, 2014, 11:19: Turbos at speed
Thursday, May 01, 2014, 11:21 : Vacuum at 5.2E-6 T
Monday, May 12, 2014, 10:03 : Turbos stopped. Vacuum at 1.22 E-7 T
Monday, May 12, 2014, 13:34: Venting
|
377
|
Monday, May 12, 2014, 14:20 |
Anders Mjos | SiC#30 | HP-FEBIAD | ITE | TM3 | 38481-8 | 39956-5 | In progress | Conditioning SiC#30 | Monday, May 12, 2014, 14:14 : Roughing
Monday, May 12, 2014, 14:34: Starting turbos
Monday, May 12, 2014, 14:42 : Turbos at speed
Monday, May 12, 2014, 14:44 : Vacuum at 1.7E-5 T
Tuesday, May 13, 2014, 10:51: Opened water for HS circuit. Vacuum stable at 2.2E-7 T. Minor spike to 2.5E-7 T for 10 s.
Tuesday, May 13, 2014, 10:54: Roughing out gas lines.
Tuesday, May 13, 2014, 11:30: Opening SV5 and SV2 to evacuate gas lines completely.
Tuesday, May 13, 2014, 11:58: BIAS to 30kV, EZL to 13 kV. EE to 1.5 kV.
Tuesday, May 13, 2014, 11:59: Opening isolation valve
Tuesday, May 13, 2014, 12:12: Started heating to 450A / 200A TGHT / TBHT.
Target heating stopped at 167 A - likely caused by network problems. Multiple gaps in strip tool. Indicating lost network connection.
Wednesday, May 14, 2014, 10:07: Resuming heating to 450A / 200A TGHT / TBHT (EPICS 170A)
Wednesday, May 14, 2014, 10:12: De-biasing to investigate ANODE/CATHODE BIAS
Switched ON ANODE/CATHODE BIAS PS.
Wednesday, May 14, 2014, 10:22: BIAS to 30kV, EZL to 13 kV. EE to 1.5 kV.
Wednesday, May 14, 2014, 16:07: Continue heating TGHT to 500A
Wednesday, May 14, 2014, 16:33: TGHT at 500A. TBHT at 203 A.
Thursday, May 15, 2014, 14:57: Switched OFF/ON IOC to recover from white-out.
Thursday, May 15, 2014, 15:51: Started heating to 550A / 240A
COIL to 50A
ANODE to 200V
TGHT to 580A
TBHT to 280A
Friday, May 16, 2014, 11:28 : Opening Ne
Friday, May 16, 2014, 11:56: TBHT to 290 A
Friday, May 16, 2014, 14:12: Started cool down. ANODE/CATHODE Bias requires reconfiguration.
Tuesday, May 20, 2014, 11:10: Ray and co is checking the configuration and troubleshooting the burnt off GND connection. The Test Stand will be configured to CATHODE negative BIAS.
Tuesday, May 20, 2014, 12:35: BIAS, EZL, EE, COIL, ANODE ON.
Tuesday, May 20, 2014, 12:35: Gas lines pumped.
Tuesday, May 20, 2014, 12:35: Auto heating to 240A/500A at 1A/2A /min.
Tuesday, May 20, 2014, 12:44: IV4 opened |
Attachment 1: SiC#30_Conditioning.docx
|
381
|
Wednesday, May 21, 2014, 17:05 |
Aurelia Laxdal | SiC#30 | HP-FEBIAD | ITE | TM3 | | | In progress | SiC#30 HV and Heaters conditiong | As per Friedhelm the conditioning settings are:
TGHT 580A
TBHT 290A
COIL 80A
ANODE 200V
Ramped up completed:
TGHT 580A/5.683V
TBHT 242A/2.295V (EPICS settings) and 289A/2.29V at the PS
COIL 80A
Current on the Anode = 13.431mA
|
385
|
Monday, June 16, 2014, 09:12 |
Anders Mjos | | | | | | | In progress | Empty chamber | Monday, June 16, 2014, 09:12: Roughing
Tuesday, June 17, 2014, 14:38: Venting |
386
|
Tuesday, June 17, 2014, 15:22 |
Anders Mjos | SiC#30 | HP-FEBIAD | ITE | TM3 | 38481-8 | 39956-5 | In progress | SiC#30 HV and Heaters Conditioning |
Anders Mjos wrote: |
Aurelia Laxdal wrote: |
HV and Heaters Conditioning for SiC#30 was completed Friday, May 23, 2014. The target was cooled down and it's ready for the on-line installation.
|
Friday, June 13, 2014, 08:43: Turbos stopped. Vacuum at 1.2E-7 T
Monday, June 16, 2014, 08:26: Venting. Water purged.
Monday, June 16, 2014, 09:00: Target removed
|
The target assembly did not pass the megger test between anode and heat shield after the previous conditioning. The AlN insulators were found to have failed during the conditioning. The coil insulation was burnt. AlN insulators and anode ware replaced.
Tuesday, June 17, 2014, 15:22: Roughing
By R.M.
Tuesday, June 17, 2014, 15:52: Turbos Started
Tuesday, June 17, 2014, 15:54: TP1B at speed
Tuesday, June 17, 2014, 15:57: IG1 Turned on 1.92e-05T
Tuesday, June 17, 2014, 15:59: TP1A at speed
Tuesday, June 17, 2014, 15:59: IG1 1.31e-05T
By AM
Wednesday, June 18, 2014, 08:24: Opened HS water circuit. Vacuum stable at 2.2E-7 T.
Wednesday, June 18, 2014, 08:40: Pumping on gas lines.
Wednesday, June 18, 2014, 08:49: Closed pump valve on gas lines.
Wednesday, June 18, 2014, 08:51: Opening TSH:SV5
Wednesday, June 18, 2014, 08:53: Opening TSH:SV2
Wednesday, June 18, 2014, 09:00: BIAS/ EZL / EE 30 / 13 / -1.5 kV
Wednesday, June 18, 2014, 09:04: Starting target heating to 500 / 240 A
Wednesday, June 18, 2014, 09:07: COIL to 50 A. ANODE to 200 V
Wednesday, June 18, 2014, 09:33: OPEN TPS:IV4
Wednesday, June 18, 2014, 14:05: TBHT at 240 A 2.6 V. TGHT still ramping (403 A)
Wednesday, June 18, 2014, 15:03: TGHT at 500 A 4.5 V
Thursday, June 19, 2014, 08:51: Ramping to 580 A / 265 A
Thursday, June 19, 2014, 09:37: Continue ramping TBHT to 290A
Thursday, June 19, 2014, 09:44: 8E-8 A on FC0
Thursday, June 19, 2014, 10:52: TBHT at 305A. Running mass scan.
Thursday, June 19, 2014, 11:36: Opening for He.
Thursday, June 19, 2014, 11:46: Opening for Ne.
Thursday, June 19, 2014, 11:54: Lowering TBHT to 300 A
Thursday, June 19, 2014, 13:01: Mass scan. ~1E-10 A Ne current on FC6 with Ne open.
Thursday, June 19, 2014, 15:06: Mass scan up.
Thursday, June 19, 2014, 16:00: Mass scan down.
Thursday, June 19, 2014, 16:49: Started cooling down target.
Friday, June 20, 2014, 08:53: Target de-biased. Turbos off.
Friday, June 20, 2014, 10:23: Venting. Purging water from HS circuit. |
Attachment 1: SiC#30_Conditioning_3rd_time.docx
|
389
|
Friday, June 20, 2014, 11:44 |
Anders Mjos | | | | | | | In progress | Pumping down empty chamber | Friday, June 20, 2014, 11:44: Roughing
Friday, June 20, 2014, 13:00: Strarting turbos
Friday, June 20, 2014, 13:09: Turbos at speed.
Friday, June 20, 2014, 13:10 : Vacuum at 1.3E-5
Thursday, June 26, 2014, 08:52 : Turbos stopped. Vacuum at 1.3E-7 T
Thursday, June 26, 2014, 15:34: Venting |
390
|
Thursday, June 26, 2014, 16:32 |
Anders Mjos | Ta#43 | LP-SIS | ITW | TM1 | 40282-2 | 39230-6 | In progress | Conditioning Ta#43 | Thursday, June 26, 2014, 16:31: Roughing.
Thursday, June 26, 2014, 16:51: Starting turbos.
Thursday, June 26, 2014, 16:59: Turbos at speed.
Thursday, June 26, 2014, 17:01: Vacuum at 1.2E-5 T
Friday, June 27, 2014, 08:39: Opened HS cooling line. Vacuum stable at 1.9E-7 T
Wednesday, July 02, 2014, 10:24: Vacuum at 1.3E-7 T
Wednesday, July 02, 2014, 10:31: BIAS / EE / EZL to 30 / 1.5 / 14 kV
Wednesday, July 02, 2014, 10:32: Opened TPS:IV4
Wednesday, July 02, 2014, 10:36: Started heating TGHT / TBHT to 400 A / 155 A
Wednesday, July 02, 2014, 14:00: Heating finished for today.
Thursday, July 03, 2014, 08:09 : Resuming heating TGHT / TBHT to 580 A / 200 A. Vacuum at 2.1E-7 T
Thursday, July 03, 2014, 09:17: TGHT voltage limiting. Stopped and restarted heating.
Thursday, July 03, 2014, 12:51 : Heating TBHT to 230 A
Thursday, July 03, 2014, 13:18: TBHT at 227 A (local readback). Started mass scan.
Thursday, July 03, 2014, 15:39: Lowering TBHT to 218 A (local).
Friday, July 04, 2014, 11:00: Heated to 230 A.
Friday, July 04, 2014, 15:40: Q1/Q6 found off.
Friday, July 04, 2014, 15:42 : Starting cool down.
Monday, July 07, 2014, 09:24 : Closed TPS:IV4
Monday, July 07, 2014, 09:24: EE conditioning to -2kV
Monday, July 07, 2014, 10:02: BIAS off. Turbos off.
Tuesday, July 08, 2014, 08:13: Venting |
Attachment 1: Ta#43_Conditioning.docx
|
391
|
Tuesday, July 08, 2014, 09:05 |
Anders Mjos | | | | | | | In progress | Empty chamber | Tuesday, July 08, 2014, 09:05: Roughing
Tuesday, July 08, 2014, 13:23: Starting turbos
Tuesday, July 08, 2014, 13:30 : Turbos at speed
Tuesday, July 08, 2014, 13:33 : Vacuum at 2.8E-6 T |
395
|
Wednesday, July 23, 2014, 14:34 |
Anders Mjos | | | | | | | In progress | Empty chamber | Wednesday, July 23, 2014, 14:34: Roughing
Wednesday, July 23, 2014, 15:03: Starting turbos.
Wednesday, July 23, 2014, 15:11: Turbos at speed
Wednesday, July 23, 2014, 15:13: Vacuum at 7.4E-6 T |
|