Wednesday, September 14, 2011, 15:33, John Wong, Test#1, HP-SIS, ITW, TM1, test, test, In progress, testing elog for test stand
|
Wednesday, September 14, 2011, 15:33
blah blah blah... |
Tuesday, March 06, 2012, 15:15, Pierre Bricault, , HP-SIS, , , , , , ISAC test stand two turbos replaced
|
Vac group has replaced the two turbo pumps. |
Tuesday, May 15, 2012, 07:39, Rick Maharaj, Sic #27, HP-SIS, ITE, TM4, , , In progress, Water on at test stand
|
The vacuum on TSGIG1 reads 2.85e-07. Turing on water on teststand and observing any changes in vacuum pressure. |
Tuesday, May 15, 2012, 10:14, Anders Mjos, SiC#27, HP-SIS, ITE, TM4, , , In progress, target ready to be heated and biased
|
Tuesday, May 15, 2012, 10:13: Turbo pumps at speed. Vacuum at 1.4E-5.
Tuesday, May 15, 2012, 12:03: Cooling lines opened. Vacuum stable at 1.6E-6
Tuesday, May 15, 2012, 12:17: Target ready to be heated and biased. |
Tuesday, May 15, 2012, 16:18, Aurelia Laxdal, SiC#27, HP-SIS, ITE, TM4, , , In progress, Target/Ion source conditioning
|
Did the HV conditioning up to 30kV and started to ramp up the heaters to 580A and 230A. |
Thursday, May 17, 2012, 08:36, Anders Mjos, SiC#27, HP-SIS, ITE, TM4, , , Done, Target removed
|
Thursday, May 17, 2012, 08:36: Turbo pumps switched off in preparation of target removal.
Thursday, May 17, 2012, 08:51: Purging cooling lines.
Thursday, May 17, 2012, 08:55: Venting. |
Thursday, May 17, 2012, 12:19, Anders Mjos, SiC#27, HP-SIS, ITE, TM4, , , Problems/Solutions, Loose chip of insulator material detected
|
Anders Mjos wrote:
A chip of insulator material was detected below the lower target insulator stand-off (attachment |
Thursday, May 17, 2012, 13:24, John Wong, SiC#27, HP-SIS, ITE, TM4, 38817-3, , Problems/Solutions, Solid residues found on EE
|
Thursday, May 17, 2012, 13:15
After the test-stand, the EE was removed for inspection. It was discovered that there were some solid residues coated on the extraction electrode
and the common plate, but the ionizer tube was clean (see attachment#1). Some samples were collected and will try to do some analysis. This |
Tuesday, September 11, 2012, 19:48, Friedhelm Ames, NB#7, HP-SIS, , , , , Done, cool down finished, all source power supplies off.
|
|
Wednesday, April 10, 2013, 12:14, Anders Mjos, Ta#40, HP-SIS, ITE, TM4, 38295-4, , Done, Conditioning Ta#40
|
Wednesday, April 10, 2013, 12:13: Stopped turbos in preparation for venting the chamber.
Wednesday, April 10, 2013, 13:05: Venting
Wednesday, April 10, 2013, 13:37: Ta#40 installed with 130 in lbs torque on all bolts. |
Thursday, April 18, 2013, 13:50, Anders Mjos, Ta#40, HP-SIS, ITE, TM4, 38295-4, , Done, Ta#40 stored under vacuum
|
Target installed at the Test Stand after an inspection in the lab. EE was cleand. All bolts torqued to 130 in lbs
Thursday, April 18, 2013, 13:48: Rouging
Thursday, April 18, 2013, 14:11: Starting turbos |
Friday, September 27, 2013, 11:41, Anders Mjos, Ta#41, HP-SIS, ITW, TM4, 39069-5, 38817-10, Done, Ta#41 Conditioning
|
Friday, September 27, 2013, 11:41: Roughing
Friday, September 27, 2013, 12:08: Turbos started
Friday, September 27, 2013, 12:16: Turbos at speed. |
Friday, March 28, 2014, 10:39, Anders Mjos, TiC#4, HP-SIS, ITE, TM3, , , In progress, Conditioning TiC#4
|
NOTE:
TBHT Power Supply is 600A. EPICS thinks it is 500. Multiply current setting with 1.2 for actual current to the tube. |
Tuesday, April 01, 2014, 11:09, Aurelia Laxdal, TiC#4, HP-SIS, ITE, TM3, , , In progress, HV and Heaters Conditioning
|
Started March 31, 2014:
- did the HV conditioning up to 30kV.
April 1, 2014: |
Thursday, April 03, 2014, 16:46, Aurelia Laxdal, TiC#4, HP-SIS, ITE, TM3, , , Done, HV and Heaters Conditioning
|
HV and Heaters Conditioning had finished. The target was cooled down and it's ready for the on-line installation. |
Friday, April 04, 2014, 08:24, Anders Mjos, TiC#4, HP-SIS, ITE, TM3, , , In progress, Venting
|
Aurelia Laxdal wrote:
|
Friday, August 29, 2014, 14:52, Anders Mjos, Ta#44, HP-SIS, ITE, TM4, 38817-9, 40316-11, Done, Conditioning Ta#44
|
Friday, August 29, 2014, 14:51: Roughing
Friday, August 29, 2014, 15:11: Starting turbos.
Friday, August 29, 2014, 15:19: Turbos at speed |
Monday, March 16, 2015, 18:53, Anders Mjos, Ta#45, HP-SIS, ITE, TM4, 38817-5, , In progress, Conditioning Ta#45
|
Monday, March 16, 2015, 18:53: Started turbos
Monday, March 16, 2015, 19:00: Turbos at speed. Vacuum at 1.3E-5 T
Tuesday, March 17, 2015, 09:03: Opened cooling water. Vacuum stable at 1.9E-7 T |
Monday, May 25, 2015, 14:40, Anders Mjos, SiC#31, HP-SIS, ITW, TM4, 38817-7, , In progress, SiC#31 Conditioning
|
Monday, May 25, 2015, 14:35: Rouging
Monday, May 25, 2015, 15:05: Turbos started.
Monday, May 25, 2015, 15:15: Turbos at speed. Vacuum at 2.4E-5 T |
Friday, September 11, 2015, 11:43, Anders Mjos, Ta#46, HP-SIS, ITE, TM4, , , Done, Ta#46 conditioning
|
EE is ST-200 material (AlN)
Friday, September 11, 2015, 11:0: Roughing
Friday, September 11, 2015, 12:12: Turbos started. |
|