905
|
Thursday, November 04, 2021, 11:55 |
Fernando Maldonado | | | | | | | Done | Opening vacuum chamber for thesis pictures :p | Thursday, November 04, 2021, 11:54: Venting
water loop removed
Thursday, November 04, 2021, 13:39: |
|
929
|
Friday, May 27, 2022, 07:19 |
Fernando Maldonado | | | | | | | Done | FEBIAD parameter scan web-app and brief description (with links) | A web-app for systematic FEBIAD parametrizations
has been develop and now includes the
ISAC Test Stand (ITS) : |
|
988
|
Tuesday, December 12, 2023, 16:11 |
Dave Neilson | Shunt #0 | | | | - | - | | P2N Thermal Test | Tuesday, December 12, 2023, 16:07
- Pumping down test stand overnight for testing
tomorrow. vacuum good, turbos starting now. |
|
999
|
Thursday, March 14, 2024, 17:43 |
Dave Neilson | | LP-FEBIAD | | | 44692-4 | 42972 | | Calibrated Leak Development | Thursday, March 14, 2024, 15:39:
Roughing
Thursday, March 14, 2024, 16:20:TP1B |
|
1000
|
Thursday, April 04, 2024, 10:38 |
Dave Neilson | | LP-SIS | | | 44691-8 | 45235-26 | Done | Mass marker testing | Thursday, April 04, 2024, 09:49:
Target inserted yesterday, April 3. mass
marker tube connections carefully confirmed. |
|
1005
|
Friday, April 19, 2024, 11:33 |
Dave Neilson | - | LP-FEBIAD | | | 44692-4 | 42972-10 | In progress | Development target test - Calibrated leak - Anode mode | Friday, April 19, 2024, 11:32:
assembly installed in test stand.
VV1 closed, pumping down |
|
1006
|
Wednesday, April 24, 2024, 16:21 |
Dave Neilson | | LP-SIS | | | 44691-8 | 45235-26 | | | Wednesday, April 24, 2024, 16:20:
Target assembly installed.
Wednesday, April 24, 2024, 16:20: |
|
1008
|
Thursday, May 02, 2024, 13:45 |
Dave Neilson | - | LP-SIS | | | 44691-8 | 45235-26 | In progress | Mass marker testing | Wednesday, May 01, 2024, 12:44:
pumped down to rough vacuum, TP1B now on.
Wednesday, May 01, 2024, 12:49: |
|
1012
|
Tuesday, July 23, 2024, 09:43 |
Dave Neilson | | LP-SIS | | | 44691-8 | 45235-26 | Done | mass marker - reservoir testing | Wednesday, July 22, 2024, 11:41 -
target installed
Wednesday, July 22, 2024, 13:31 - |
|
1013
|
Wednesday, July 24, 2024, 14:08 |
Dave Neilson | | | | | | | | Beam line window change - DUV installation | Wednesday, July 24, 2024, 14:07
Changed beamline window to DUV window (window
at magnet for target source viewing) |
|
1014
|
Thursday, July 25, 2024, 14:26 |
Dave Neilson | Ta#67 Thin foil | LP-SIS | ITE | TM3 | 45447-14 | 45235-10 | | Conditioning Ta#67 Thin foil | Thursday, July 25, 2024, 14:25 -
competing electrical checks prior to test
stand installation |
|
1019
|
Tuesday, August 13, 2024, 09:31 |
Dave Neilson | | | | | | | Problems/Solutions | Troubleshooting HV sparks and FC0 signal | Monday, August 12, 2024, 17:00 EOD.
target installed, roughed, turbos on. No
effect on vacuum from turning on water cooling |
|
1020
|
Friday, September 06, 2024, 12:08 |
Dave Neilson | | | | | | | Done | Test Stand repair/update | Friday, September 06, 2024: New TSH:TGHT
power supply has been installed and is now
functional. Magna-Power TSD-900/208. The |
|
1021
|
Tuesday, September 10, 2024, 16:24 |
Dave Neilson | TiC #24D | HP-SIS | ITW | TM3 | 45447-27 | 45235-25 | | Back up target testing and conditioning | Tuesday, September 10, 2024, 16:21:
Target installed in test stand by Brady
Tuesday, September 10, 2024, 16:21: |
|
1025
|
Wednesday, October 09, 2024, 13:29 |
Dave Neilson | | | | | 44691-8 | 45235-26 | | Retainer tests - with mass marker target | Wednesday, October 09, 2024, 11:28
Target loaded, remote power supply
added for mass marker, negative channel on |
|
1033
|
Tuesday, December 03, 2024, 14:55 |
Dave Neilson | | | | | | | Done | Power supply changed to CATHODE mode (-) | Tuesday, December 03, 2024, 14:55 ANODE/CATHODE
power supply switched to cathode mode, NEGATIVE |
|
1038
|
Thursday, December 05, 2024, 15:38 |
Dave Neilson | | LP-FEBIAD | | | 44692-4 | 42972-10 | | FEBIAD development | Tuesday, December 02, 2024, 15:35
- Target loaded into the test stand
Thursday, December 03, 2024, 14:33 |
|
1041
|
Tuesday, December 17, 2024, 09:46 |
Dave Neilson | | | | | | 45235-26 | In progress | SIS P2N source cup testing | Monday, December 16, 2024, 3:34 Target
loaded in test stand. Confirmed correct connection
to mass marker power supply through multipin. |
|
1042
|
Tuesday, December 17, 2024, 16:09 |
Dave Neilson | | | | | | | Done | Anode,TGHT, TBHT power supply investigation. Resolved | Note, ground and HVC (high voltage
common) are used interchangeably here.
|
|
1043
|
Friday, December 20, 2024, 09:37 |
Dave Neilson | | | | | | | | Winter holiday shutdown | Friday, December 20, 2024, 09:37
turned off all 4 turbopumps. winding
down prior to evacuating. |
|
|