182
|
Tuesday, October 13, 2015, 10:52 |
Isaac Earle | Standard Operation | Target 1 | Target | T1 & T2 Target Ladder Moves | The T1 and T2 targets were both moved
from Position 0 to Position 4 at approximately
2:30am on Saturday October 10th using the |
|
|
183
|
Thursday, November 05, 2015, 17:07 |
Isaac Earle | Repair | Target 2 | Target | T2-MK1 Profile Monitor Repair and Pos'n 3 Target Removal | The following work was performed on the
T2-MK1 target. The profile monitor
and monitor cage on this target were damaged |
8x |
|
184
|
Thursday, December 17, 2015, 13:31 |
Grant Minor | Development | Other | Target | T1/T2 Target Cassette - window / end cap manufacturing change (WO 41527) | Isaac Earle has recently been managing
the fabrication of some new Be target cassettes
for the T1 / T2 Meson Hall target ladders |
|
|
192
|
Thursday, March 24, 2016, 15:38 |
Isaac Earle | Development | Target 1 | Target | T1/T2 Beryllium Target Test Jig Fabrication Complete | Fabrication of the T1/T2 beryllium target
testing jig (TBP1721) was completed today
by Dan MacDonald. With a target installed |
|
|
193
|
Thursday, March 31, 2016, 11:48 |
Isaac Earle | Standard Operation | Target 1 | Target | T1 & T2 Beryllium Target Manufacturing Complete | Manufacturing of a new batch of T1 and
T2 beryllium targets has been completed.
The job was completed under Machine |
|
|
196
|
Monday, April 11, 2016, 13:54 |
Isaac Earle | Standard Operation | Target 2 | Target | T2-MK2 Target Transported from BL to HC | The T2-MK2 target was transported from
the beam line to the hot cell using the transfer
flask. The target was measured to be |
|
|
197
|
Friday, April 15, 2016, 14:54 |
Isaac Earle | Standard Operation | Target 2 | Target | T2-MK2 Target Changes & Return to Beamline | On April 11th the T2-MK2 target was flushed
with water, then overnight with air at 5psi
supply pressure. The target ladder |
|
|
198
|
Wednesday, April 20, 2016, 10:01 |
Isaac Earle | Standard Operation | Target 1 | Target | T1/T2 Monitor Electrical Check Complete | Mike Russell from Diagnostics Group has
completed an electrical check on the T1 and
T2 profile and protect monitors. He |
|
|
200
|
Friday, May 13, 2016, 15:04 |
Isaac Earle | Standard Operation | Target 2 | Target | T2-MK2 Position 4 Adjusted to +1.5mm Offset | The T2-MK2 target at Position 4 has been
adjust to approximately +1.5mm offset. This
causes the ladder to be moved downwards, |
|
|
201
|
Wednesday, June 15, 2016, 11:00 |
Isaac Earle | Standard Operation | Target 2 | Target | T2-MK2 Target Moved to Position #1 | Position #4 on the T2-MK2 target
has now reached the maximum beam time. The
target was moved to Position #1 at the nominal |
|
|
208
|
Friday, September 30, 2016, 16:54 |
Isaac Earle | Repair | Target 1 | Target | T1-MK2 - New Beryllium Targets Installed | The following work was performed
on the T1-MK2 target assembly during the
September 2016 Mini-shutdown: |
|
|
212
|
Monday, January 09, 2017, 15:07 |
Isaac Earle | Standard Operation | Target 2 | Target | T2-MK2 Target Moved from BL to HC | The T2-MK2 target assembly was moved
from the beam line to the hot cell today.
A maximum field of 203mSv/hr was measured |
|
|
213
|
Thursday, January 12, 2017, 09:21 |
Isaac Earle | Standard Operation | Target 2 | Target | T2-MK2 Position 1 Beam Spot | The beam spot on the 10cm beryllium
target in Position 1 on T2-MK2 (Target ID:
"OCT.06#3") was measured and photographed |
|
|
218
|
Wednesday, April 05, 2017, 17:55 |
Isaac Earle | Development | Other | Target | T2 area devices alignment strategy | A strategy for alignment of the T2 protect
monitor, T2 target, and T2 Collimator A was
discussed today and decided upon by Yuri |
|
|
220
|
Tuesday, April 11, 2017, 17:31 |
Isaac Earle | Development | Target 2 | Target | T2-MK2 target MRO and alignment of T2 devices | The following work was performed on
the T2-MK2 target assembly and the T2 Protect
assembly for maintenance purposes and to |
|
|
221
|
Friday, May 05, 2017, 15:09 |
Isaac Earle | Development | Target 2 | Target | T2-MK2 beam spot check in hot cell | On May 5th the T2-MK2 target was
moved to the hot cell for the purpose of
checking the beam spot on the Position 2 |
|
|
223
|
Monday, May 15, 2017, 16:55 |
Isaac Earle | Other | Target 2 | Target | T2 profile monitor actuation issue | On Thursday May 11th operators attempted
to move the T2 profile monitor (T2-MK2) to
the IN position but were unsuccessful. The |
|
|
224
|
Monday, July 10, 2017, 16:20 |
Keith C Ng | Repair | Target 2 | Target | T2 Heat Exchanger Secondary Side Solenoid Valve Failure | The T2 heat exchanger secondary side solenoid
failed on July 9 at approximately 19:30 (EPICS
ID: B1A:T2CS:SVSEC). The valve was |
|
|
228
|
Tuesday, August 29, 2017, 12:17 |
Isaac Earle | Maintenance | Target 1 | Target | T1-MK1 and T2-MK1 Hansen water fittings replaced | The #6 male Hansen fittings for the
T1-MK1 and T2-MK1 targets (both currently
stored in the target storage pit) were replaced |
|
|
229
|
Tuesday, October 10, 2017, 12:09 |
Isaac Earle | Standard Operation | Target 2 | Target | T2-MK2 position 4 target changed | The following work was performed on
the T2-MK2 target assembly during the 2017
fall shutdown: |
|