38
|
Thursday, June 07, 2012, 18:08 |
Isaac Earle | Repair | Target 1 | Target | Hot Cell Manipulator Broken Tape | A tape snapped on the west side manipulator
today while working on the T1-MK2 target
repair. The tape travels through to |
|
39
|
Friday, June 08, 2012, 16:52 |
Isaac Earle | Repair | Target 1 | Target | Broken Manipulator Tape Update | The broken tape on the west side
hot cell manipulator was found to be one
of two "Z motion slave tapes". |
|
40
|
Friday, June 08, 2012, 17:01 |
Isaac Earle | Repair | Target 1 | Target | T1-MK2 Leak Repair Update | A leak check was performed on the
T1-MK2 target in the hot cell today and confirmed
successful leak-free installation of the |
|
41
|
Monday, June 18, 2012, 16:27 |
Isaac Earle | Repair | Target 1 | Target | T1-MK2 Profile and Protect Monitor Electronics Check | Bill Rawnsley and Mike Russell performed
a 'blip' test on the T1-MK2 profile monitor
and protect monitors today. A possible |
|
46
|
Friday, June 29, 2012, 14:18 |
Isaac Earle | Repair | Target 1 | Target | Manipulator Repair Complete | Repair of the west side hot cell
manipulator was completed and the manipulator
was re-installed into the cell. The |
|
48
|
Friday, July 06, 2012, 16:03 |
Isaac Earle | Repair | Target 1 | Target | T1-MK2 Target Repair Complete | Target elevation measurements and
beam spot plots were completed on the T1-MK2
target and the target is now fully repaired |
|
50
|
Wednesday, July 11, 2012, 17:51 |
Isaac Earle | Repair | Target 1 | Target | T1 Target Swap | BL1A was started yesterday and brought
up to 10 |
|
53
|
Friday, July 27, 2012, 14:48 |
Isaac Earle | Repair | Target 1 | Target | T1-MK1 Target Repair Update | - T1MK1 target transferred from storage
pit to hot cell (max field: 4700 |
|
54
|
Wednesday, August 08, 2012, 14:40 |
Isaac Earle | Repair | Target 1 | Target | T1-MK1 Target Repair Complete | - Re-wired profile monitor was received
from Probes Group and installed on the target |
|
55
|
Friday, September 07, 2012, 16:35 |
Isaac Earle | Repair | Target 2 | Target | T2-MK1 Target Repair Completed | - Profile monitor wiring harness
checked by Bill Rawnsley using resistor pack
--> OK |
|
56
|
Friday, September 07, 2012, 16:39 |
Isaac Earle | Repair | Target 1 | Target | RH Lab Crane Repaired | The "west" button on the
crane pendant was broken, and the crane would
occasionally continue moving west when the |
|
58
|
Tuesday, September 25, 2012, 16:31 |
Isaac Earle | Repair | Target 1 | Target | T1/T2 Controls | - The target control software was
modified to reference the correct pot. look-up
table for the target at T1 (T1-MK1) |
|
59
|
Friday, September 28, 2012, 15:19 |
Isaac Earle | Repair | Target 1 | Target | T1-MK2 Delta Seal Leak | After removal of the leaky
target cassette at position 3, plugs were
installed on the target ladder and a leak |
|
60
|
Wednesday, October 24, 2012, 17:34 |
Isaac Earle | Repair | Target 1 | Target | T1-MK2 Target Repair Complete | The target ladder was detached, old delta
seals removed, sealing surfaces cleaned using
scotchbrite pad and a dremel tool, and delta |
|
61
|
Wednesday, October 24, 2012, 17:38 |
Isaac Earle | Repair | Target 2 | Target | T1 & T2 Target Ladder Control System Status | During the recent shutdown for the
T2/M9 joint repair Graham Waters replaced
the corrupted application code on the controller |
|
62
|
Tuesday, November 13, 2012, 16:26 |
Isaac Earle | Repair | Target 1 | Target | Manipulator Repair Complete | Repair of the west side manipulator
in the west hot cell was completed today.
Part of the repair was done by entering |
|
69
|
Monday, January 21, 2013, 11:57 |
Isaac Earle | Repair | Target 2 | Target | Flask Repair | On January 15th, when attempting
to move the T2 target from the beam line
to the hot cell, the latch mechanism on the |
|
76
|
Tuesday, April 09, 2013, 17:06 |
Isaac Earle | Repair | Target 1 | Target | T1 Target Electronics Check | The T1-MK1 target protect and profile monitor
electronics were 'blip' tested by Bill Rawnsley
on April 5, 2013. The response from |
|
83
|
Friday, May 31, 2013, 16:07 |
Isaac Earle | Repair | Target 1 | Target | Power Supply Fan Failure | Today (May 31, 2013) I was contacted
regarding a burning smell and high temperatures
around the T1/T2 controls racks. Erwin |
|
84
|
Tuesday, June 04, 2013, 13:42 |
Isaac Earle | Repair | Target 1 | Target | T1 and T2 Power Supply Fans Replaced | Replacement of the power supply fans
for the T1 Power Supply, T2 Power Supply,
as well as an additional power supply in |
|