  RH-Meson Hall, Page 6 of 18  Not logged in ELOG logo
New entries since:Wed Dec 31 16:00:00 1969
ID Date Author Category Type Specificdown Subject Text Attachments
  143   Friday, February 27, 2015, 18:06 Isaac EarleDevelopmentTarget 1TargetT1 Rotary Collimator Water and Air Line Investigation Ron Kuramoto, Keith Ng, John McKinnon,
and myself spent some time today investigating
water and air lines related to the T1 Rotary
  
  145   Thursday, March 12, 2015, 10:51 Isaac EarleStandard OperationTarget 2TargetT2-MK2 Pos'n 4 Elevation MeasurementsElevation measurements of the T2-MK2 target
were taken in the hot cell to confirm previous
records in preparation for the T2 Protect
  
  147   Thursday, April 09, 2015, 13:56 Isaac EarleDevelopmentTarget 2TargetT2-MK2 target wired for version identification, cable ties replaced, ready for useThe "POT/CAM" MS connector on
the T2-MK2 has been wired to allow automatic
target version number identification by the
  
  148   Monday, April 20, 2015, 11:42 Isaac EarleStandard OperationTarget 2TargetT2-MK2 Target & T2 Protect Moved The T2-MK2 target was moved from
the hot cell to the beam line. The T2 Protect
Monitor was moved from the beam line to the
  
  149   Tuesday, April 21, 2015, 12:59 Isaac EarleStandard OperationTarget 1TargetT1-MK2 target moved from storage pit to beam line The T1-MK2 target was transported
from the storage pit to the beamline.  The
target measured approximately 10mSv/hr at
  
  150   Tuesday, April 21, 2015, 13:38 Isaac EarleStandard OperationTarget 1TargetAir Amplifier Started. T1 & T2 Profile Monitor Actuation Checked The lower air amplifier has been
started, and air supplied to the T1 and T2
areas by opening the appropriate ball valves
  
  151   Wednesday, April 22, 2015, 09:46 Isaac EarleDevelopmentTarget 1TargetWater Sensors Installed on T1 Monolith Four water sensors have been installed
on top of the T1 monolith.  These water
sensors were wired and brought to the area
 T1_Water_Sensors.jpgIMG_4859.JPGIMG_4860.JPG 
  153   Wednesday, April 22, 2015, 15:17 Isaac EarleDevelopmentTarget 1TargetT1-MK2 wired for version identification The T1-MK2 target was wired for automatic
target version detection by the new PLC control
system (A to C jumper  in POT/CAM MS
  
  155   Thursday, April 23, 2015, 16:29 Isaac EarleStandard OperationTarget 1TargetT1 & T2 Profile and Protect Monitors Electrical Check CompletedAn electrical check has been completed
for the T1 & T2 Profile and Protect Monitors
by Dave Cameron and Mike Russell.  They
  
  156   Friday, April 24, 2015, 11:53 Isaac EarleStandard OperationTarget 2TargetT2-MK2 Target Info Sheet & ElevationsT2-MK2 target information sheet, beam spot
measurements, and elevations were updated
and delivered to Operations. PDF copy attached.
 T2-MK2_-_2015_Elevations.pdf 
  157   Tuesday, April 28, 2015, 15:55 Isaac EarleDevelopmentTarget 1TargetTarget Version Jumper Wires Installed for T1-MK1 and T2-MK1 The T1-MK1 and T2-MK1 targets have
been re-wired to allow version identification.
 Work was performed in the target storage
  
  160   Tuesday, May 12, 2015, 21:20 Grant MinorStandard OperationTarget 1TargetT1 & T2 Targets moved from pos. 0 to pos. 4Grant moved the T1 and T2 targets from
position 0 to position 4 this evening at
around 9pm.
  
  165   Wednesday, July 08, 2015, 16:21 Isaac EarleDevelopmentTarget 1Target0.003" 347 SS Sheet for T1/T2 Targets Received A 5lb roll of 347SS sheet was received
today.  This alloy is to be used for
the target windows of the new T1 and T2 beryllium
 347SS_Mill_Spec_Test_Report_-_July_8_2015.pdf 
  166   Thursday, July 09, 2015, 13:51 Isaac EarleDevelopmentOtherTargetNew T1 and T2 Beryllium Targets OrderedAn order for new T1 and T2  beryllium
targets was submitted to the TRIUMF machine
shop today.  A total of seven T2 targets
  
  168   Friday, July 17, 2015, 10:14 Isaac EarleDevelopmentTarget 1TargetT1/T2 Be Target Failure History & Replacement PlanT1 and T2 beryllium target failure history
was investigated back to 2000 (as far as
XSTRIP records were readily available).  For
 T1_and_T2_Be_Target_History_-_July_17_2015.pdf 
  174   Wednesday, September 30, 2015, 17:07 Isaac EarleStandard OperationTarget 2TargetTarget Moves for Profile Check - Possible Motor or Control Box FailureThe T1 and T2 targets were moved to position
zero, then back to the target position today
so that beam profile could be checked using
  
  175   Thursday, October 01, 2015, 11:43 Isaac EarleRepairTarget 2TargetT2-MK2 Target Ladder Drive Motor Failure The stepper motor that drives the
target ladder on T2-MK2 has failed.  This
is the cause of the difficulty moving the
  
  176   Friday, October 02, 2015, 17:25 Ron KuramotoStandard OperationTarget 1TargetRaise Target to lower Rad levels for 1AM7 repairToday the T1MK2 target was moved from Position
4 to Position 0 to lower the Rad fields for
the 1AM7 repair in the 1A Tunnel. The Rad
  
  180   Friday, October 09, 2015, 15:18 Isaac EarleRepairTarget 2TargetT2-MK2 Check at Hot Cell and Motor Drive Cable ReplacementWhile the T2 monolith was uncovered for
T2 Protect repair (see previous e-log), it
was decided that the T2 target should be
 7x 
  181   Friday, October 09, 2015, 15:52 Isaac EarleRepairTarget 1TargetT1-MK2 Protect Monitor Replacement and InspectionWhen the damage to the T2 Protect Monitor
was found to be caused by flying debris from
a vacuum spike (see e-log #179), it was decided
 12x 