143
|
Friday, February 27, 2015, 18:06 |
Isaac Earle | Development | Target 1 | Target | T1 Rotary Collimator Water and Air Line Investigation | Ron Kuramoto, Keith Ng, John McKinnon,
and myself spent some time today investigating
water and air lines related to the T1 Rotary |
|
145
|
Thursday, March 12, 2015, 10:51 |
Isaac Earle | Standard Operation | Target 2 | Target | T2-MK2 Pos'n 4 Elevation Measurements | Elevation measurements of the T2-MK2 target
were taken in the hot cell to confirm previous
records in preparation for the T2 Protect |
|
147
|
Thursday, April 09, 2015, 13:56 |
Isaac Earle | Development | Target 2 | Target | T2-MK2 target wired for version identification, cable ties replaced, ready for use | The "POT/CAM" MS connector on
the T2-MK2 has been wired to allow automatic
target version number identification by the |
|
148
|
Monday, April 20, 2015, 11:42 |
Isaac Earle | Standard Operation | Target 2 | Target | T2-MK2 Target & T2 Protect Moved | The T2-MK2 target was moved from
the hot cell to the beam line. The T2 Protect
Monitor was moved from the beam line to the |
|
149
|
Tuesday, April 21, 2015, 12:59 |
Isaac Earle | Standard Operation | Target 1 | Target | T1-MK2 target moved from storage pit to beam line | The T1-MK2 target was transported
from the storage pit to the beamline. The
target measured approximately 10mSv/hr at |
|
150
|
Tuesday, April 21, 2015, 13:38 |
Isaac Earle | Standard Operation | Target 1 | Target | Air Amplifier Started. T1 & T2 Profile Monitor Actuation Checked | The lower air amplifier has been
started, and air supplied to the T1 and T2
areas by opening the appropriate ball valves |
|
151
|
Wednesday, April 22, 2015, 09:46 |
Isaac Earle | Development | Target 1 | Target | Water Sensors Installed on T1 Monolith | Four water sensors have been installed
on top of the T1 monolith. These water
sensors were wired and brought to the area |
|
153
|
Wednesday, April 22, 2015, 15:17 |
Isaac Earle | Development | Target 1 | Target | T1-MK2 wired for version identification | The T1-MK2 target was wired for automatic
target version detection by the new PLC control
system (A to C jumper in POT/CAM MS |
|
155
|
Thursday, April 23, 2015, 16:29 |
Isaac Earle | Standard Operation | Target 1 | Target | T1 & T2 Profile and Protect Monitors Electrical Check Completed | An electrical check has been completed
for the T1 & T2 Profile and Protect Monitors
by Dave Cameron and Mike Russell. They |
|
156
|
Friday, April 24, 2015, 11:53 |
Isaac Earle | Standard Operation | Target 2 | Target | T2-MK2 Target Info Sheet & Elevations | T2-MK2 target information sheet, beam spot
measurements, and elevations were updated
and delivered to Operations. PDF copy attached. |
|
157
|
Tuesday, April 28, 2015, 15:55 |
Isaac Earle | Development | Target 1 | Target | Target Version Jumper Wires Installed for T1-MK1 and T2-MK1 | The T1-MK1 and T2-MK1 targets have
been re-wired to allow version identification.
Work was performed in the target storage |
|
160
|
Tuesday, May 12, 2015, 21:20 |
Grant Minor | Standard Operation | Target 1 | Target | T1 & T2 Targets moved from pos. 0 to pos. 4 | Grant moved the T1 and T2 targets from
position 0 to position 4 this evening at
around 9pm. |
|
165
|
Wednesday, July 08, 2015, 16:21 |
Isaac Earle | Development | Target 1 | Target | 0.003" 347 SS Sheet for T1/T2 Targets Received | A 5lb roll of 347SS sheet was received
today. This alloy is to be used for
the target windows of the new T1 and T2 beryllium |
|
166
|
Thursday, July 09, 2015, 13:51 |
Isaac Earle | Development | Other | Target | New T1 and T2 Beryllium Targets Ordered | An order for new T1 and T2 beryllium
targets was submitted to the TRIUMF machine
shop today. A total of seven T2 targets |
|
168
|
Friday, July 17, 2015, 10:14 |
Isaac Earle | Development | Target 1 | Target | T1/T2 Be Target Failure History & Replacement Plan | T1 and T2 beryllium target failure history
was investigated back to 2000 (as far as
XSTRIP records were readily available). For |
|
174
|
Wednesday, September 30, 2015, 17:07 |
Isaac Earle | Standard Operation | Target 2 | Target | Target Moves for Profile Check - Possible Motor or Control Box Failure | The T1 and T2 targets were moved to position
zero, then back to the target position today
so that beam profile could be checked using |
|
175
|
Thursday, October 01, 2015, 11:43 |
Isaac Earle | Repair | Target 2 | Target | T2-MK2 Target Ladder Drive Motor Failure | The stepper motor that drives the
target ladder on T2-MK2 has failed. This
is the cause of the difficulty moving the |
|
176
|
Friday, October 02, 2015, 17:25 |
Ron Kuramoto | Standard Operation | Target 1 | Target | Raise Target to lower Rad levels for 1AM7 repair | Today the T1MK2 target was moved from Position
4 to Position 0 to lower the Rad fields for
the 1AM7 repair in the 1A Tunnel. The Rad |
|
180
|
Friday, October 09, 2015, 15:18 |
Isaac Earle | Repair | Target 2 | Target | T2-MK2 Check at Hot Cell and Motor Drive Cable Replacement | While the T2 monolith was uncovered for
T2 Protect repair (see previous e-log), it
was decided that the T2 target should be |
7x |
181
|
Friday, October 09, 2015, 15:52 |
Isaac Earle | Repair | Target 1 | Target | T1-MK2 Protect Monitor Replacement and Inspection | When the damage to the T2 Protect Monitor
was found to be caused by flying debris from
a vacuum spike (see e-log #179), it was decided |
12x |