Wednesday, June 06, 2012, 08:48, Isaac Earle, Repair, Target 1, Target, Manipulator Repair Complete
Wednesday, June 06, 2012, 08:58, Isaac Earle, Maintenance, Target 2, Target, T2 Monolith Leak Check
Thursday, June 07, 2012, 18:08, Isaac Earle, Repair, Target 1, Target, Hot Cell Manipulator Broken Tape
Friday, June 08, 2012, 16:52, Isaac Earle, Repair, Target 1, Target, Broken Manipulator Tape Update
Friday, June 08, 2012, 17:01, Isaac Earle, Repair, Target 1, Target, T1-MK2 Leak Repair Update
Monday, June 18, 2012, 16:27, Isaac Earle, Repair, Target 1, Target, T1-MK2 Profile and Protect Monitor Electronics Check
Friday, June 22, 2012, 13:54, Isaac Earle, Maintenance, Target 2, Target, Air Amplifier Rebuild Complete
Friday, June 29, 2012, 14:18, Isaac Earle, Repair, Target 1, Target, Manipulator Repair Complete
Tuesday, July 03, 2012, 13:23, Isaac Earle, Standard Operation, Target 2, Target, T2 Plug Block Replaced & Beam Blockers Tested
Friday, July 06, 2012, 16:03, Isaac Earle, Repair, Target 1, Target, T1-MK2 Target Repair Complete
Monday, July 09, 2012, 17:17, Isaac Earle, Standard Operation, Target 1, Target, BL1A Start-Up Prep
Wednesday, July 11, 2012, 17:51, Isaac Earle, Repair, Target 1, Target, T1 Target Swap
Monday, July 23, 2012, 16:01, Isaac Earle, Development, Target 1, Target, Target Flask Seismic Restraint Clamps Installed
Friday, July 27, 2012, 14:48, Isaac Earle, Repair, Target 1, Target, T1-MK1 Target Repair Update
Wednesday, August 08, 2012, 14:40, Isaac Earle, Repair, Target 1, Target, T1-MK1 Target Repair Complete
Friday, September 07, 2012, 16:35, Isaac Earle, Repair, Target 2, Target, T2-MK1 Target Repair Completed
Friday, September 07, 2012, 16:39, Isaac Earle, Repair, Target 1, Target, RH Lab Crane Repaired
Tuesday, September 25, 2012, 16:31, Isaac Earle, Repair, Target 1, Target, T1/T2 Controls
Friday, September 28, 2012, 15:19, Isaac Earle, Repair, Target 1, Target, T1-MK2 Delta Seal Leak
Wednesday, October 24, 2012, 17:34, Isaac Earle, Repair, Target 1, Target, T1-MK2 Target Repair Complete