58
|
Tuesday, September 25, 2012, 16:31 |
Isaac Earle | Repair | Target 1 | Target | T1/T2 Controls | - The target control software was
modified to reference the correct pot. look-up
table for the target at T1 (T1-MK1) |
|
57
|
Thursday, September 13, 2012, 18:09 |
Isaac Earle | Maintenance | Target 1 | Cooling | September Shutdown T1 & T2 MRO | The following tasks were performed
during the 2012 September Shutdown:
- Both targets moved to position |
|
56
|
Friday, September 07, 2012, 16:39 |
Isaac Earle | Repair | Target 1 | Target | RH Lab Crane Repaired | The "west" button on the
crane pendant was broken, and the crane would
occasionally continue moving west when the |
|
55
|
Friday, September 07, 2012, 16:35 |
Isaac Earle | Repair | Target 2 | Target | T2-MK1 Target Repair Completed | - Profile monitor wiring harness
checked by Bill Rawnsley using resistor pack
--> OK |
|
54
|
Wednesday, August 08, 2012, 14:40 |
Isaac Earle | Repair | Target 1 | Target | T1-MK1 Target Repair Complete | - Re-wired profile monitor was received
from Probes Group and installed on the target |
|
53
|
Friday, July 27, 2012, 14:48 |
Isaac Earle | Repair | Target 1 | Target | T1-MK1 Target Repair Update | - T1MK1 target transferred from storage
pit to hot cell (max field: 4700 |
|
52
|
Monday, July 23, 2012, 16:01 |
Isaac Earle | Development | Target 1 | Target | Target Flask Seismic Restraint Clamps Installed | Installation of the seismic restraint
clamps has been completed for the MK1 and
MK2 target flasks in the Remote Handling |
|
51
|
Tuesday, July 17, 2012, 15:30 |
Isaac Earle | Development | Target 1 | Cooling | T1 & T2 Expansion Tank Level Warnings Added | Mike Mouat and Juan Pon have modified
the control system so that the control room
will receive a message when the warning or |
|
50
|
Wednesday, July 11, 2012, 17:51 |
Isaac Earle | Repair | Target 1 | Target | T1 Target Swap | BL1A was started yesterday and brought
up to 10 |
|
49
|
Monday, July 09, 2012, 17:17 |
Isaac Earle | Standard Operation | Target 1 | Target | BL1A Start-Up Prep | - T1 & T2 targets switched to
"remote" control
- Both target ladders were moved |
|
48
|
Friday, July 06, 2012, 16:03 |
Isaac Earle | Repair | Target 1 | Target | T1-MK2 Target Repair Complete | Target elevation measurements and
beam spot plots were completed on the T1-MK2
target and the target is now fully repaired |
|
47
|
Tuesday, July 03, 2012, 13:23 |
Isaac Earle | Standard Operation | Target 2 | Target | T2 Plug Block Replaced & Beam Blockers Tested | The T2 plug block was replaced and the
M9 and M20 beam blockers were tested. The
plug block did not interfere with the travel |
|
46
|
Friday, June 29, 2012, 14:18 |
Isaac Earle | Repair | Target 1 | Target | Manipulator Repair Complete | Repair of the west side hot cell
manipulator was completed and the manipulator
was re-installed into the cell. The |
|
45
|
Tuesday, June 26, 2012, 09:05 |
Isaac Earle | Maintenance | Target 1 | Cooling | T1 & T2 Target Water Flow Transducers Serviced | The target water outlet flow transducers
on the T1 and T2 cooling packages were serviced
(new shaft, paddle wheel, & o-ring) to |
|
44
|
Friday, June 22, 2012, 13:54 |
Isaac Earle | Maintenance | Target 2 | Target | Air Amplifier Rebuild Complete | A full rebuild of the upper air amplifier
was completed. New anodized aluminum
barrels were installed (replacing the old |
|
43
|
Friday, June 22, 2012, 13:48 |
Isaac Earle | Development | Target 1 | Cooling | T1 & T2 Expansion Tank Level Sensor Recording Enabled | Mike Mouat enabled recording for T1 and
T2 expansion tank warning and trip level
sensors on XTPAGE/XSTRIP. |
|
42
|
Thursday, June 21, 2012, 13:38 |
Isaac Earle | Standard Operation | Target 2 | Cooling | T2 Water Package Started | The T2 water package was reconnected
to the target and started after being shut-off
since April 12, 2012. The M9 and M20 |
|
41
|
Monday, June 18, 2012, 16:27 |
Isaac Earle | Repair | Target 1 | Target | T1-MK2 Profile and Protect Monitor Electronics Check | Bill Rawnsley and Mike Russell performed
a 'blip' test on the T1-MK2 profile monitor
and protect monitors today. A possible |
|
40
|
Friday, June 08, 2012, 17:01 |
Isaac Earle | Repair | Target 1 | Target | T1-MK2 Leak Repair Update | A leak check was performed on the
T1-MK2 target in the hot cell today and confirmed
successful leak-free installation of the |
|
39
|
Friday, June 08, 2012, 16:52 |
Isaac Earle | Repair | Target 1 | Target | Broken Manipulator Tape Update | The broken tape on the west side
hot cell manipulator was found to be one
of two "Z motion slave tapes". |
|