250
|
Tuesday, April 16, 2019, 15:35 |
Keith C Ng | Repair | Other | M9 | M9 project post shutdown summary | Completed work at m9 beam line:
- Removed existing service stand
and associated cable and water services. |
|
|
262
|
Monday, April 06, 2020, 15:02 |
Isaac Earle | Standard Operation | Target 2 | M9 | M9 beam blocker returned to beamline | The M9 beam blocker was returned to the
beamline today using the RH shielded transport
flask. The top flange o-ring was replaced |
|
|
261
|
Monday, March 23, 2020, 16:13 |
Isaac Earle | Maintenance | Other | Other | M9 beam blocker MRO completed | M9 beam blocker MRO work was completed
in the hot cell today. This included
replacement of the main shaft seals and replacement |
|
|
289
|
Wednesday, May 04, 2022, 11:27 |
Adam Newsome | Standard Operation | Target 2 | M9 | M9 and M20 Beam Blocker Actuation Test | The beam blockers for M9 and M20 were actuated,
and vacuum was monitored to ensure no disruptions.
Both actuation tests were successful. Motion |
|
|
265
|
Friday, June 12, 2020, 13:54 |
Isaac Earle | Development | Other | M9 | M9 Q1Q2 water header installed | The Q1Q2 water header (TB23481) was mounted
this morning as per installation drawing
TB23400. |
 |
|
260
|
Wednesday, March 11, 2020, 10:29 |
Isaac Earle | Development | Other | M9 | M9 Q1Q2 service stand foot plate installed | The M9 Q1Q2 "foot" plate
(TB23363) has been installed over the floor
plate. A nominal gap between the plates |
|
|
258
|
Friday, February 28, 2020, 09:06 |
Isaac Earle | Development | Other | M9 | M9 Q1Q2 service stand floor plate installed | The M9 service stand floor plate
(TB23351) was installed in the M9 pit yesterday.
Prior to installation all 5 threaded inserts |
|
|
267
|
Tuesday, July 07, 2020, 15:13 |
Isaac Earle | Development | Other | M9 | M9 Q1Q2 service stand Lemo connector wiring | The diagram below shows the wiring for
the two connectors on the service stand (the
wires running from the stand to the power |
|
|
266
|
Tuesday, July 07, 2020, 13:22 |
Isaac Earle | Development | Other | M9 | M9 Q1Q2 | The M9 Q1Q2 magnet assembly lift
beam has been installed according to drawing
TB23401. The side-to-side as well as |
   |
|
13
|
Monday, January 23, 2012, 15:27 |
Isaac Earle | Repair | Target 2 | Target | M20BB returned to beam line. M9BB moved to hot cell. | M20 beam blocker was transferred from the
hot cell to the beam line.
M9 beam blocker was transferred from |
|
|
237
|
Friday, April 13, 2018, 14:21 |
Isaac Earle | Maintenance | Other | Other | M20 beam blocker MRO and T1/T2 final checks | The M20 beam blocker main shaft seals were
replaced as per the T1/T2 target device maintenance
schedule. Both air cylinders were found |
|
|
323
|
Friday, March 03, 2023, 16:00 |
Albert Kong | Maintenance | Target 2 | Other | M20 Return to T2 Monolith + Vaccum Leak / T1-T2 Valve Re-inspection | We moved M20 back to the T2 monolith
and re did the connections for air + limit
switches + T2 profile monitor air. |
   |
|
324
|
Monday, March 06, 2023, 16:58 |
Albert Kong | Repair | Target 2 | Cooling | M20 O-Ring Replacement and Valve Replacement Leak Check | We replaced tha O-ring on M20 at
T2 and brought the target station down to
vacuum, which allowed the target water pump |
 |
|
319
|
Tuesday, February 21, 2023, 16:56 |
Albert Kong | Maintenance | Target 2 | Other | M20 BB moved to meson hall hot cell roof | The M20 beam blocker was moved from the
T2 monolith to the meson hall hot cell with
the remote handling flask (completed ~4pm). |
|
|
12
|
Friday, January 20, 2012, 10:23 |
Isaac Earle | Repair | Target 2 | Target | M20 BB Shaft Bearing Replaced | The replacement shaft bearing was machined
by Maico Dalla Valle and installed in the
beam blocker. Smooth operation of the |
 |
|
162
|
Thursday, June 11, 2015, 16:59 |
Isaac Earle | Development | Other | Controls | Lab Test of New T1/T2 Level Sensors | The new T1/T2 level sensors (Omega LVCN414)
were tested in the RH HC lab today using
the Omega software on a laptop and positioning |
|
|
3
|
Friday, November 04, 2011, 13:36 |
Isaac Earle | Maintenance | Target 2 | Target | Kaon Target (Training) | Moved Kaon Target from storage
pit to remote handling hot cell using flask
as training exercise. Safety surveyor |
|
|
288
|
Thursday, April 14, 2022, 14:38 |
Adam Newsome | Other | Target 2 | Diagnostics | Issue with Protect Monitor SHV Cable | Diagnostics group (Shengli Liu) noted a
lack of connectivity between control panel
and T2 Protect Monitor via the high voltage |
  |
|
178
|
Tuesday, October 06, 2015, 14:04 |
Isaac Earle | Other | Other | Controls | Instructions for loading display screen for T1/T2 | The following instructions were provided
by Graham Waters:
|
|
|
349
|
Friday, June 28, 2024, 15:44 |
Albert Kong | Other | Other | Transfer Flask | Inspection of Primary Target Transfer Flask |
Normal