Entry  Monday, January 20, 2020, 16:07, Isaac Earle, Other, Other, Other, Second 55-gal drum moved to cyclotron east vault tunnel RWC-55-02-2019_(after_move_to_cyc_vault_tunnel).pdf
Entry  Wednesday, July 17, 2024, 15:05, Adam Newsome, Standard Operation, Other, Other, Safety Walkaround Complete - Meson Hall HC/WC Area 
Entry  Thursday, October 10, 2024, 12:24, Adam Newsome, Other, Other, Hot Cell, Safety Walkaround Complete - Meson Hall HC/WC Area 
Entry  Tuesday, December 20, 2011, 09:54, Isaac Earle, Maintenance, Target 1, Target, Replaced T1-MK1 Target Ladder 
Entry  Thursday, January 12, 2012, 11:34, Isaac Earle, Maintenance, Target 2, Target, Replaced M20 Beam Blocker Vacuum Seal O-Rings 
Entry  Thursday, March 02, 2023, 06:59, maicodallavalle, Maintenance, Target 1, Cooling, Refilled Expasion Tank 
Entry  Thursday, March 02, 2023, 07:04, maicodallavalle, Maintenance, Target 2, Cooling, Refilled Expasion Tank 
Entry  Friday, October 02, 2015, 17:25, Ron Kuramoto, Standard Operation, Target 1, Target, Raise Target to lower Rad levels for 1AM7 repair 
Entry  Friday, May 01, 2015, 16:01, Isaac Earle, Repair, Target 1, Other, RH Warm Cell Used by Beamlines Group for TNF Heat Exchanger Leak Check IMG_1510.JPGIMG_1511.JPGIMG_1512.JPG
Entry  Friday, April 22, 2016, 14:45, Isaac Earle, Other, Other, Active Sump, RH MH Hot Cell Lab Active Sump Water Released 
Entry  Tuesday, June 28, 2016, 08:32, Isaac Earle, Other, Other, Active Sump, RH MH Hot Cell Lab Active Sump Overflow 
Entry  Tuesday, June 28, 2016, 16:28, Isaac Earle, Other, Other, Active Sump, RH MH Hot Cell Lab Active Sump High Level Sensor Test 
Entry  Thursday, March 22, 2018, 17:24, Isaac Earle, Standard Operation, Other, Active Sump, RH Lab active sump released 
Entry  Friday, September 07, 2012, 16:39, Isaac Earle, Repair, Target 1, Target, RH Lab Crane Repaired 
Entry  Wednesday, April 14, 2021, 14:30, Isaac Earle, Standard Operation, Other, Active Sump, RH Lab Active Sump pumped out 
Entry  Thursday, November 22, 2012, 17:22, Isaac Earle, Standard Operation, Target 1, Active Sump, RH Lab Active Sump Released 
Entry  Wednesday, September 25, 2013, 14:05, Isaac Earle, Standard Operation, Target 1, Active Sump, RH Lab Active Sump Level Sensor Inspected 
Entry  Tuesday, November 18, 2014, 10:52, Isaac Earle, Standard Operation, Target 1, Active Sump, RH Hot Cell Lab Active Sump Released 
Entry  Monday, September 28, 2015, 10:29, Isaac Earle, Standard Operation, Other, Active Sump, RH Hot Cell Lab Active Sump High Level Sensor Tested 
Entry  Monday, January 16, 2023, 15:06, Adam Newsome, Repair, Other, Active Sump, RH Active Sump - draining flow rate sensor repair 