186
|
Monday, January 25, 2016, 16:54 |
Isaac Earle | Maintenance | Target 1 | Cooling | T1 MRO Work | The following work was performed at the
T1 cooling package and target between January
18-21, 2016: |
|
276
|
Thursday, February 17, 2022, 13:03 |
Matthew Gareau | Maintenance | Target 1 | Target | T1 MK2 wire scanner and protect monitor test removal and reattachment with pin straightening | this Work was done on 09 Dec 2021.
Since Isaac Earle was leaving Triumf
he was giving us (maico, chad, adam, and |
    |
26
|
Tuesday, April 03, 2012, 15:55 |
Isaac Earle | Maintenance | Target 1 | Target | T1 Ladder Position Look-up Tables Updated | Graham Waters has activated the appropriate
target ladder position look-up tables for
the T1-MK1 target which was installed in |
|
330
|
Tuesday, June 06, 2023, 15:42 |
Albert Kong | Standard Operation | Target 1 | Cooling | T1 Heat Exchanger Low Flow Diagnostics | On May 31, the low active water in BL1A
was turned off briefly and upon re-starting,
the flow to the T1 heat exchanger was very |
 |
216
|
Monday, March 27, 2017, 16:15 |
Isaac Earle | Repair | Target 1 | Cooling | T1 Cooling System Target Water Return Hose Damaged | The 18' shielding block which lies west
of the T1 cooling package was removed on
Friday Mar 24 so that vacuum equipment could |
 |
209
|
Friday, September 30, 2016, 16:59 |
Isaac Earle | Repair | Target 1 | Cooling | T1 Cooling System Inlet Pressure Transducer Replaced | The T1 cooling system inlet pressure
transducer (EPICS ID: B1A:T1CS:PGIN, Omega
part # PX315-100GI) began failing in August |
|
331
|
Tuesday, July 18, 2023, 09:14 |
Adam Newsome | Other | Target 1 | Cooling | T1 Cooling Package: target flow (FGTGT) sensor noise issues | Between 1:00 pm and 6:00 pm on July 17,
2023, the T1 target cooling water flow rate
sensor exhibited some noise which resulted |
 |
315
|
Wednesday, February 01, 2023, 14:23 |
Albert Kong | Maintenance | Target 1 | Cooling | T1 Cooling Package: flow test after resin exchange / valve leak check / faulty(?) dial pressure gauge | Maico/Eric/Albert:
The expansion tank in T1 was filled
to ~36cm in the morning. |
|
317
|
Thursday, February 02, 2023, 15:14 |
Albert Kong | Maintenance | Target 1 | Cooling | T1 Cooling Package: Leaked Valve Inspection | A 0.75" SwageLok ball valve that was
taken out from the T1 cooling package was
inspected (SS-45S12). |
|
112
|
Thursday, April 03, 2014, 16:35 |
Isaac Earle | Standard Operation | Target 1 | Cooling | T1 Cooling Package Started | The T1 cooling package was started
around 2pm today. There was no change
to the T1 volume vacuum during startup. |
|
310
|
Monday, January 16, 2023, 15:01 |
Adam Newsome | Maintenance | Target 1 | Cooling | T1 Cooling Package MRO - 2023 Shutdown | T1 Cooling Package MRO began Jan. 16, 2023.
The following maintenance tasks have |
|
85
|
Friday, August 23, 2013, 10:39 |
Isaac Earle | Repair | Target 1 | Cooling | T1 Cooling Package Inlet Pressure (P1) Sensor | The T1 cooling package inlet pressure
(P1) has been dropping since approximately
May 5, 2013 from the regular operating pressure |
 |
316
|
Thursday, February 02, 2023, 10:35 |
Albert Kong | Maintenance | Target 1 | Cooling | T1 Cooling Package Draining (Prep for Valve Replacement) | Water reservoir in T1 started draining
at ~7.30 am, will leave till tomorrow or
overnight to fully drain. |
|
138
|
Tuesday, January 27, 2015, 17:38 |
Isaac Earle | Repair | Target 1 | Cooling | T1 Cooling Package 3/4" Valves Rebuilt - T1 MRO Complete | - Both 3/4" ball valves on the T1
cooling package target water circuit were
rebuilt, leak tested with house air pressure, |
|
20
|
Tuesday, March 20, 2012, 10:31 |
Isaac Earle | Repair | Target 1 | Cooling | T1 Cooling Package - Potential Water Leak | The T1 expansion tank warning level sensor
had tripped and the level was approximately
1cm from the base of the tank. No trip |
|
78
|
Friday, April 12, 2013, 17:33 |
Isaac Earle | Development | Target 1 | Cooling | T1 & T2 high-temp limit switch installation, wiring, and commissioning complete | Installation, wiring, and commissioning
of the high temperature limit switches for
the T1 and T2 cooling packages was completed |
|
256
|
Wednesday, February 05, 2020, 14:53 |
Isaac Earle | Maintenance | Target 1 | Cooling | T1 & T2 cooling package MRO work completed | Annual MRO work on the T1 and T2
cooling packages is now complete. The
following tasks were performed: |
|
160
|
Tuesday, May 12, 2015, 21:20 |
Grant Minor | Standard Operation | Target 1 | Target | T1 & T2 Targets moved from pos. 0 to pos. 4 | Grant moved the T1 and T2 targets from
position 0 to position 4 this evening at
around 9pm. |
|
45
|
Tuesday, June 26, 2012, 09:05 |
Isaac Earle | Maintenance | Target 1 | Cooling | T1 & T2 Target Water Flow Transducers Serviced | The target water outlet flow transducers
on the T1 and T2 cooling packages were serviced
(new shaft, paddle wheel, & o-ring) to |
|
142
|
Friday, February 20, 2015, 13:55 |
Isaac Earle | Standard Operation | Target 2 | Target | T1 & T2 Target Moves | - The T1-MK1 target was moved from the
hot cell to storage pit hole #3 (ready as
T1 spare) |
|