  231   Thursday, December 07, 2017, 13:54 Isaac EarleDevelopmentOtherOtherWaste pails transferred from warm cell storage bunker to rad waste pitSix 5 gallon pails were transferred this
morning from a temporary storage bunker in
the Warm Cell to the Rad Waste Pit for long
 IMG_0102.JPGIMG_6285.JPGIMG_0102.JPGIMG_6285.JPG 
  234   Wednesday, March 28, 2018, 10:12 Isaac EarleStandard OperationOtherOtherFive waste pails moved to East Vault Tunnel for storage Five 5 gallon metal pails with active
waste were moved from the Warm Cell to the
Cyclotron East Vault Tunnel today for long
  
  237   Friday, April 13, 2018, 14:21 Isaac EarleMaintenanceOtherOtherM20 beam blocker MRO and T1/T2 final checksThe M20 beam blocker main shaft seals were
replaced as per the T1/T2 target device maintenance
schedule.  Both air cylinders were found
  
  243   Tuesday, August 28, 2018, 11:16 Isaac EarleStandard OperationOtherOtherSouth TNF Holding Tank water released The water in the South TNF Holding
Tank was released today under work permit
#C2018-08-28-3.  The tank contained
  
  245   Thursday, October 25, 2018, 08:58 Keith C NgRepairOtherOtherT1 collimator valve solenoid coil replaced againOn
23rd October we restarted the T1 and T2 water
packages after the mini shutdown and after
  
  246   Thursday, November 01, 2018, 13:57 Keith C NgOtherOtherOthernuclear venillation in hot cells not workingRandomly checked on the nuclear ventilation
for the Meson Hall Hotcells and discovered
they were not running again (both magnahelic
  
  253   Tuesday, December 17, 2019, 12:39 Isaac EarleStandard OperationOtherOther55 gallon drum and old M9 service stand moved to Rad Waste PitThe following items were moved today from
the Warm Cell to the Rad Waste Pit for long
term storage:
 RWC-55-01-2019.pdfpit_-_before_move.jpgdrum_being_lifted.jpgpit_-_after_move_-_showing_drum.jpgpit_-_after_move_-_showing_service_stand_(bottom_right_with_green_sling).jpg 
  254   Monday, January 20, 2020, 16:07 Isaac EarleOtherOtherOtherSecond 55-gal drum moved to cyclotron east vault tunnel The second (and final) 55 gallon
drum containing active items from the Meson
Hall East Hot Cell was transported today
 RWC-55-02-2019_(after_move_to_cyc_vault_tunnel).pdf 
  257   Monday, February 10, 2020, 14:51 Isaac EarleMaintenanceOtherOtherT1-MK2 target and M9BB moved The T1-MK2 target was moved from
the hot cell to Hole #5 in the storage pit. 
The M9 beam blocker was then moved from the
  
  259   Wednesday, March 04, 2020, 13:42 Ron KuramotoRepairOtherOtherB/L 1A vacuum air leak repair A 4” Marmon aluminum blank-off
flange and o-ring were replaced on the south
port of the T1 target monolith vacuum vessel. This
 1AT1_Vacuum_Leak_Repair-Feb2020.pdf 
  261   Monday, March 23, 2020, 16:13 Isaac EarleMaintenanceOtherOtherM9 beam blocker MRO completedM9 beam blocker MRO work was completed
in the hot cell today.  This included
replacement of the main shaft seals and replacement
  
  295   Wednesday, July 06, 2022, 12:49 Matthew GareauRepairOtherOtherHelium line damage, and hotcell window oil leakingToday myself and Adam Newsome started the
leak detection steps for a target exchange
and notice that the Helium line was not connected/broken
  
  300   Tuesday, August 23, 2022, 14:36 Adam NewsomeStandard OperationOtherOtherBL1A Holding Tank - Level CheckThe water level inside the BL1A active
water holding tank was checked today (Aug.
23, 2022). The tank is essentially empty
  
  319   Tuesday, February 21, 2023, 16:56 Albert KongMaintenanceTarget 2OtherM20 BB moved to meson hall hot cell roofThe M20 beam blocker was moved from the
T2 monolith to the meson hall hot cell with
the remote handling flask (completed ~4pm).
 IMG_1255.JPEG 
  323   Friday, March 03, 2023, 16:00 Albert KongMaintenanceTarget 2OtherM20 Return to T2 Monolith + Vaccum Leak / T1-T2 Valve Re-inspection We moved M20 back to the T2 monolith
and re did the connections for air + limit
switches + T2 profile monitor air.
 IMG_1755.JPEGIMG_1657.JPEGIMG_1763.jpegScreenshot_2023-03-30_124716.png 
  334   Tuesday, October 17, 2023, 14:25 Albert KongMaintenanceOtherOtherT1/T2 Air Amplifier Spool O-Ring ServicingToday we re-lubricated the o-rings on the
top air amplifier for T1/T2, and replaced
the o-rings on the bottom air amplifier with
 IMG_2576.JPEGIMG_2575.JPEG 
  350   Wednesday, July 17, 2024, 15:05 Adam NewsomeStandard OperationOtherOtherSafety Walkaround Complete - Meson Hall HC/WC AreaA safety walkaround for July 2024 was completed
by A. Kong.
Results can be found in the master
  
  250   Tuesday, April 16, 2019, 15:35 Keith C NgRepairOtherM9M9 project post shutdown summary Completed work at m9 beam line:
- Removed existing service stand
and associated cable and water services.
  
  258   Friday, February 28, 2020, 09:06 Isaac EarleDevelopmentOtherM9M9 Q1Q2 service stand floor plate installed The M9 service stand floor plate
(TB23351) was installed in the M9 pit yesterday. 
Prior to installation all 5 threaded inserts
 M9_service_stand_floor_plate_TB23351.png 
  260   Wednesday, March 11, 2020, 10:29 Isaac EarleDevelopmentOtherM9M9 Q1Q2 service stand foot plate installed The M9 Q1Q2 "foot" plate
(TB23363) has been installed over the floor
plate.  A nominal gap between the plates
  