198
|
Wednesday, April 20, 2016, 10:01 |
Isaac Earle | Standard Operation | Target 1 | Target | T1/T2 Monitor Electrical Check Complete | Mike Russell from Diagnostics Group has
completed an electrical check on the T1 and
T2 profile and protect monitors. He |
|
197
|
Friday, April 15, 2016, 14:54 |
Isaac Earle | Standard Operation | Target 2 | Target | T2-MK2 Target Changes & Return to Beamline | On April 11th the T2-MK2 target was flushed
with water, then overnight with air at 5psi
supply pressure. The target ladder |
|
196
|
Monday, April 11, 2016, 13:54 |
Isaac Earle | Standard Operation | Target 2 | Target | T2-MK2 Target Transported from BL to HC | The T2-MK2 target was transported from
the beam line to the hot cell using the transfer
flask. The target was measured to be |
|
195
|
Monday, April 11, 2016, 13:51 |
Isaac Earle | Development | Other | Other | Target Transfer Flask Hoist Hook Lower Limit Adjusted | The lower limit of the flask hoist
hook has been adjusted. The travelling
nut for the lower limit was rotated 3 notches |
|
194
|
Thursday, April 07, 2016, 16:44 |
Isaac Earle | Development | Other | Controls | T1/T2 Controls "Assembly Tests" Completed | The T1/T2 Control System "Assembly
Tests" (Document 118467 Release
#1, Section 5) have been completed. The |
|
193
|
Thursday, March 31, 2016, 11:48 |
Isaac Earle | Standard Operation | Target 1 | Target | T1 & T2 Beryllium Target Manufacturing Complete | Manufacturing of a new batch of T1 and
T2 beryllium targets has been completed.
The job was completed under Machine |
|
192
|
Thursday, March 24, 2016, 15:38 |
Isaac Earle | Development | Target 1 | Target | T1/T2 Beryllium Target Test Jig Fabrication Complete | Fabrication of the T1/T2 beryllium target
testing jig (TBP1721) was completed today
by Dan MacDonald. With a target installed |
|
191
|
Thursday, March 24, 2016, 14:46 |
Isaac Earle | Other | Other | Other | TNF / 500MeV Resin Cans Removed from Storage Pit #1 | Three used TNF / 500MeV system cooling
system resin cans were removed from the Meson
Hall target storage pit (two from Hole #1, |
|
190
|
Wednesday, March 16, 2016, 16:50 |
Isaac Earle | Development | Target 2 | Controls | Preliminary Testing of T2 Control System Complete | Preliminary testing of the new
PLC control system and EPICS interface was |
|
189
|
Monday, March 07, 2016, 18:22 |
Isaac Earle | Development | Target 1 | Controls | Preliminary Testing of T1 Control System Complete | Preliminary testing of the new PLC
control system and EPICS interface was completed
today for the T1 target, T1 cooling package, |
|
188
|
Wednesday, February 24, 2016, 13:03 |
Isaac Earle | Repair | Other | Other | Target Flask 2-Ton Hoist Chain Twist Corrected | A 1/2 turn twist in the target flask
hoist chain has been corrected to address
a deficiency observed by inspectors by Gordon |
|
187
|
Wednesday, February 03, 2016, 17:35 |
Isaac Earle | Standard Operation | Target 2 | Cooling | T2 MRO Work | The following work was performed at the
T2 cooling package and target between Jan
25 - Feb 3, 2016: |
|
186
|
Monday, January 25, 2016, 16:54 |
Isaac Earle | Maintenance | Target 1 | Cooling | T1 MRO Work | The following work was performed at the
T1 cooling package and target between January
18-21, 2016: |
|
185
|
Monday, January 18, 2016, 17:19 |
Isaac Earle | Standard Operation | Target 1 | Cooling | T1 & T2 Packages Drained; BL1A Holding Tank Released | The T1 and T2 cooling packages were
drained to the BL1A holding tank on Jan 8
2016. The volumes were 100L and 80L |
|
184
|
Thursday, December 17, 2015, 13:31 |
Grant Minor | Development | Other | Target | T1/T2 Target Cassette - window / end cap manufacturing change (WO 41527) | Isaac Earle has recently been managing
the fabrication of some new Be target cassettes
for the T1 / T2 Meson Hall target ladders |
|
183
|
Thursday, November 05, 2015, 17:07 |
Isaac Earle | Repair | Target 2 | Target | T2-MK1 Profile Monitor Repair and Pos'n 3 Target Removal | The following work was performed on the
T2-MK1 target. The profile monitor
and monitor cage on this target were damaged |
8x |
182
|
Tuesday, October 13, 2015, 10:52 |
Isaac Earle | Standard Operation | Target 1 | Target | T1 & T2 Target Ladder Moves | The T1 and T2 targets were both moved
from Position 0 to Position 4 at approximately
2:30am on Saturday October 10th using the |
|
181
|
Friday, October 09, 2015, 15:52 |
Isaac Earle | Repair | Target 1 | Target | T1-MK2 Protect Monitor Replacement and Inspection | When the damage to the T2 Protect Monitor
was found to be caused by flying debris from
a vacuum spike (see e-log #179), it was decided |
12x |
180
|
Friday, October 09, 2015, 15:18 |
Isaac Earle | Repair | Target 2 | Target | T2-MK2 Check at Hot Cell and Motor Drive Cable Replacement | While the T2 monolith was uncovered for
T2 Protect repair (see previous e-log), it
was decided that the T2 target should be |
7x |
179
|
Friday, October 09, 2015, 14:56 |
Isaac Earle | Repair | Target 2 | Other | T2 Protect Monitor Replacement | On Monday Oct 5th a decision was
made to uncover and remove the T2 Protect
Monitor due to faulty readings. The |
9x |