ID Date Author Category Type Specific Subject Text Attachments
  198   Wednesday, April 20, 2016, 10:01 Isaac EarleStandard OperationTarget 1TargetT1/T2 Monitor Electrical Check CompleteMike Russell from Diagnostics Group has
completed an electrical check on the T1 and
T2 profile and protect monitors.  He
  
  197   Friday, April 15, 2016, 14:54 Isaac EarleStandard OperationTarget 2TargetT2-MK2 Target Changes & Return to BeamlineOn April 11th the T2-MK2 target was flushed
with water, then overnight with air at 5psi
supply pressure.  The target ladder
 T2-MK2_Position_4_Entrance_Side_-_April_14_2016.JPGT2-MK2_Position_4_Exit_Side_-_April_14_2016.JPGIMG_7024.JPGIMG_7026.JPG 
  196   Monday, April 11, 2016, 13:54 Isaac EarleStandard OperationTarget 2TargetT2-MK2 Target Transported from BL to HCThe T2-MK2 target was transported from
the beam line to the hot cell using the transfer
flask.  The target was measured to be
  
  195   Monday, April 11, 2016, 13:51 Isaac EarleDevelopmentOtherOtherTarget Transfer Flask Hoist Hook Lower Limit Adjusted The lower limit of the flask hoist
hook has been adjusted.  The travelling
nut for the lower limit was rotated 3 notches
  
  194   Thursday, April 07, 2016, 16:44 Isaac EarleDevelopmentOtherControlsT1/T2 Controls "Assembly Tests" CompletedThe T1/T2 Control System "Assembly
Tests"  (Document 118467 Release
#1, Section 5) have been completed.  The
  
  193   Thursday, March 31, 2016, 11:48 Isaac EarleStandard OperationTarget 1TargetT1 & T2 Beryllium Target Manufacturing CompleteManufacturing of a new batch of T1 and
T2 beryllium targets has been completed.
The job was completed under Machine
 T1_T2_Be_Target_Documentation_(2016_Batch).xlsx 
  192   Thursday, March 24, 2016, 15:38 Isaac EarleDevelopmentTarget 1TargetT1/T2 Beryllium Target Test Jig Fabrication CompleteFabrication of the T1/T2 beryllium target
testing jig (TBP1721) was completed today
by Dan MacDonald.  With a target installed
 IMG_6904.JPG 
  191   Thursday, March 24, 2016, 14:46 Isaac EarleOtherOtherOtherTNF / 500MeV Resin Cans Removed from Storage Pit #1Three used TNF / 500MeV system cooling
system resin cans were removed from the Meson
Hall target storage pit (two from Hole #1,
  
  190   Wednesday, March 16, 2016, 16:50 Isaac EarleDevelopmentTarget 2ControlsPreliminary Testing of T2 Control System CompletePreliminary testing of the new
PLC control system and EPICS interface was
 T2_Testing_Checklist_-_Complete_-_March_16_2016.pdf 
  189   Monday, March 07, 2016, 18:22 Isaac EarleDevelopmentTarget 1ControlsPreliminary Testing of T1 Control System Complete Preliminary testing of the new PLC
control system and EPICS interface was completed
today for the T1 target, T1 cooling package,
 T1_Testing_Checklist_-_Complete_-_March_7_2016.pdf 
  188   Wednesday, February 24, 2016, 13:03 Isaac EarleRepairOtherOtherTarget Flask 2-Ton Hoist Chain Twist Corrected A 1/2 turn twist in the target flask
hoist chain has been corrected to address
a deficiency observed by inspectors by Gordon
  
  187   Wednesday, February 03, 2016, 17:35 Isaac EarleStandard OperationTarget 2CoolingT2 MRO WorkThe following work was performed at the
T2 cooling package and target between Jan
25 - Feb 3, 2016:
  
  186   Monday, January 25, 2016, 16:54 Isaac EarleMaintenanceTarget 1CoolingT1 MRO WorkThe following work was performed at the
T1 cooling package and target between January
18-21, 2016:
  
  185   Monday, January 18, 2016, 17:19 Isaac EarleStandard OperationTarget 1CoolingT1 & T2 Packages Drained; BL1A Holding Tank Released The T1 and T2 cooling packages were
drained to the BL1A holding tank on Jan 8
2016.  The volumes were 100L and 80L
  
  184   Thursday, December 17, 2015, 13:31 Grant MinorDevelopmentOtherTargetT1/T2 Target Cassette - window / end cap manufacturing change (WO 41527)Isaac Earle has recently been managing
the fabrication of some new Be  target cassettes
for the T1 / T2 Meson Hall target ladders
 Left_new_right_old_ref_TBP1683_16Dec2015.JPGTBP1690_left_new_right_old_16Dec2015.JPGTBP1683_forming_tool_16Dec2015.JPGNew_Frame_Ref_TBP1696_16Dec2015.pdf 
  183   Thursday, November 05, 2015, 17:07 Isaac EarleRepairTarget 2TargetT2-MK1 Profile Monitor Repair and Pos'n 3 Target RemovalThe following work was performed on the
T2-MK1 target.  The profile monitor
and monitor cage on this target were damaged
 8x 
  182   Tuesday, October 13, 2015, 10:52 Isaac EarleStandard OperationTarget 1TargetT1 & T2 Target Ladder Moves The T1 and T2 targets were both moved
from Position 0 to Position 4 at approximately
2:30am on Saturday October 10th using the
  
  181   Friday, October 09, 2015, 15:52 Isaac EarleRepairTarget 1TargetT1-MK2 Protect Monitor Replacement and InspectionWhen the damage to the T2 Protect Monitor
was found to be caused by flying debris from
a vacuum spike (see e-log #179), it was decided
 12x 
  180   Friday, October 09, 2015, 15:18 Isaac EarleRepairTarget 2TargetT2-MK2 Check at Hot Cell and Motor Drive Cable ReplacementWhile the T2 monolith was uncovered for
T2 Protect repair (see previous e-log), it
was decided that the T2 target should be
 7x 
  179   Friday, October 09, 2015, 14:56 Isaac EarleRepairTarget 2OtherT2 Protect Monitor ReplacementOn Monday Oct 5th a decision was
made to uncover and remove the T2 Protect
Monitor due to faulty readings.  The
 9x 