  1795   Wednesday, September 26, 2018, 07:14 David WangConditioning StationRepairTM3 TM3 HV test at TCS.I did a HV test on TM3 at TCS yesterday.
HV Ramp up speed: 1KV per 5 minutes when
below 30KV,1KV per 10 minutes from 30-36KV.
  
  1797   Tuesday, October 02, 2018, 09:49 David WangITEStandard OperationTM4UCx 24#TM4 was disconnected in ITE.TM4 was disconnected in ITE yesterday.
See attachment for checklist.
 TM2_UCx_24#_disconnection_in_ITE..pdf 
  1799   Wednesday, October 03, 2018, 14:16 David WangSouth Hot-CellStandard OperationTM4Ta #57Leak check TM4 Lp Ta# 57 at SHC.Tried to leak check TM4 Ta57# at TCS. LD
failed to pump down properly at fine range.
It always tripped at 4 torr. I cheeked all
  
  1801   Tuesday, October 09, 2018, 12:32 David WangConditioning StationRepairTM4 TM4 steers 4 pin feedthrough CF flangeTM4 Steers 4 pin feedthrough CF flange
is replaced due an inside feed through insulator
broken. CF 25 cooper seal is replaced with
  
  1803   Wednesday, October 10, 2018, 07:52 David WangITEStandard OperationTM4Ta#57TM4 has been connected in ITE.TM4 has been connected in ITE. see attachment.  TM4_with_TA#56_connection_in_ITE.pdf 
  1806   Tuesday, October 23, 2018, 10:45 David WangITWStandard OperationTM2SiC nanoTM2 was disconnected in ITW.TM2(SiC nano) has been disconnected in
ITW. See attachment
 TM2_SiC_nano_disconnection_in_ITW.pdf 
  1808   Tuesday, October 23, 2018, 11:32 David WangSouth Hot-CellMaintenance  ITW RV4S leak check.ITW RV4S (A and B) are leak checked. They
are good.  
  
  1811   Monday, October 29, 2018, 10:43 David WangConditioning StationRepair  ITW exit 2 leak check at TCS.I did a leak check this morning on exit
2 module at TCS. LD base  leak rate
is 4.00XE-9atm.cc/sec, Base pressure is 0.00
  
  1815   Thursday, November 01, 2018, 11:42 David WangConditioning StationStandard OperationTM2UCx 25.TM2 HS line helium pressure test at TCS and helium spray at SHC..Chad and I did  leak check on TM2
HS line at SHC yesterday. Base LR 0.0XE-9
atm.cc/sec.   No response on LD.
  
  1829   Wednesday, November 28, 2018, 06:39 David WangConditioning StationStandard Operation  Disconnection checklist LpTa #56TM4 was disconnected in ITE. Checklist
list in attachment.
 LpTa#56_disconnection_checklist.pdf 
  1830   Wednesday, November 28, 2018, 07:04 David WangITEDevelopmentTM4LpTa 56New high current flexible cables inspection after LpTa#56 beam run.Inspected new high current flexible cables
during TM4 disconnection. The new cables
and adapters work fine.
 new_flexibble_cable_in_ITE_after_Ta#56_run_001.JPGnew_flexibble_cable_in_ITE_after_Ta#56_run_004.JPG 
  1833   Thursday, November 29, 2018, 06:38 David WangSouth Hot-CellStandard OperationTM4 Leak check TM4 UCx 26 at SHC.Chad and I did a leak check on TM4 HS line
with UCx 26# installed . Base LR 0.0X E-9
atm.cc/sec. Base pressure 0.0XE-4 torr. 
  
  1836   Tuesday, December 04, 2018, 12:36 David WangITEStandard OperationTM4UCx 26.TM4 has been connected in ITE/ Checklist.TM4 has been connected in ITE. See attachment
for connection checklist
 UCx26_TM4_connection_checklist.pdf 
  1844   Thursday, January 03, 2019, 13:30 David WangITWRepair  ITH:MP1ITH:MP1 inlet pressure showed 10torr after
power outage during holiday. All ITE/W turbo-pumps
were tripped because of it. Removed one shielding
  
  1845   Thursday, January 03, 2019, 13:41 David WangCraneRepair  Target hall crane PLC issue.Target hall crane did not work properly
after power outage during Christmas time.
The only movement could be operated is crane
  
  1846   Friday, January 04, 2019, 08:48 David WangITWStandard OperationTM2 TM2 has been disconnected in ITW.TP1, TP2 are still connected for next week
leak check. All water lines in TM2 are purged
with 80 psi air, each for 5 minutes.
 UCx25_TM2_disconnection_checklist.pdf 
  1848   Tuesday, January 08, 2019, 08:49 David WangITWStandard OperationTM2 TP1 TP1 have been disconnected in ITWStarted argon venting of ITW now.    
  1849   Wednesday, January 09, 2019, 06:26 David WangConditioning StationStandard Operation  TCS vacuum pumps have been stopped.The tCS will be vented soon for TM2 move
later this week.
  
  1852   Wednesday, January 09, 2019, 13:29 David WangITWRepair  ITH:MP1ITH: MP1 has been replaced due to its poor
performance.  Its motor and power cable
are taken out and reused on new pump. Vacuum
  
  1854   Thursday, January 10, 2019, 10:45 David WangConditioning StationStandard OperationTM2 TM2 is under vacum at TCS.TCS: TP1, TP2 and TP1S are started.    