Message ID: 1714     Entry time: Tuesday, May 15, 2018, 10:21
Author: David Wang 
Category: Conditioning Station 
Type: Standard Operation 
Module: TM4 
Target/Number:  
Subject: Tm4 water circles helium pressur test result  

  Helium pressure test on TM4  water lines is done this morning. 70 psi helim , 1 minutes time to each circle. The result:

A(oven+): 0.00xE-9 atm.cc/sec

B(Oven -): 8.1Xe-7 atm.cc/sec

C(tube -): 0.00xE-9 atm.cc/sec

D(tube+): 1.0xE-5 atm.cc/sec

PQ(coil 2): capped on top. water lines were removed because of leak

RU(Coil1): 0.00xE-9 atm.cc/sec

EE: 0.00xE-9 atm.cc/sec

MSP: 0.00xE-9 atm.cc/sec

HS: No target, capped on top. It was fine on last target check in 2017 Oct.

window: Capped on top. Containment box is not installed.

The leak check on D line caused the IG1 small response during test.

B and D circle are double checked. The reasults are same.

D line leak is in E-5 atm.cc/sec range. It is possible to locate it by using helium spray method in SHC. The containment box is not on so it should be easy to do it.

Switch on IGA gauge at TCS and apply helium and water at certain psi to check the IGA response may give us more information on these leaks.

 All lines were test in last year shut down. They were good.

 