Tuesday, June 02, 2015, 10:39, Travis Cave, South Hot-Cell, Standard Operation, TM4, SiC#31, Electrical Check
|
Electrical check on TM#4 with SiC#31. See attached PDF for details. |
Tuesday, June 02, 2015, 09:43, chad fisher, South Hot-Cell, Standard Operation, TM4, SiC#31, SiC#31 installed
|
Ta #45 has been removed from TM4 and SIC#31installed. |
Tuesday, June 02, 2015, 06:51, David Wang, South Hot-Cell, Standard Operation, TM4, , Target Hall Scheduled Activities April 07 - June 26 2015 
|
Target Hall schedule weekly update. All jobs are finished on time so far. |
Monday, June 01, 2015, 14:24, Travis Cave, South Hot-Cell, Standard Operation, TM4, Ta#45, Electrical Check
|
Post beam electrical check on the Ta#45 target installed on TM#4. See attached PDF. |
Monday, June 01, 2015, 11:23, Travis Cave, ITE, Standard Operation, TM4, Ta#45, Module moved
|
TM#4 with Ta#45 has been moved from the east target station to the south hot cell. |
Friday, May 29, 2015, 09:16, Travis Cave, Conditioning Station, Standard Operation, TM2, no target, Module moved
|
TM#2 with no source tray has been moved from the conditioning station to the north east silo. |
Wednesday, May 27, 2015, 08:57, Travis Cave, Conditioning Station, Standard Operation, TM2, , Module moved
|
TM#2 with no source tray has been moved from the south hot cell to the conditioning station. |
Tuesday, May 26, 2015, 14:34, chad fisher, South Hot-Cell, Repair, TM2, , Shutter replacement
|
The shutter in TM2 was successfully replaced today.
New lock washer and nut were installed onto shutter and nut torqued to 120 ft lbs.
Shutter guide alignment tool was used to insure tapped shutter guide holes were concentric with thru holes in shutter side mounting panel, button |
Tuesday, May 26, 2015, 11:49, Grant Minor, Assembly/Bench Test, Repair, TM2, , TM2 New Source Tray - Braze & Solder Report - 22 May 2015 6x
|
Hello,
For reference, I have attached a list of all solder joints in the TM2 Source Tray, and the alloys used for the most recent build (as per ITA6144). |
Friday, May 22, 2015, 15:44, David Wang, ITW, Standard Operation, TM1, UCx12, 5 Shielding blocks have been transferred from ITE to ITW.
|
5 shielding blocks have been transferred from ITE to ITW. I checked all ITW water signals, and they are good. ITW is configured to take proton
beam. |
Wednesday, May 13, 2015, 13:55, chad fisher, South Hot-Cell, Repair, TM2, , Shutter removal 
|
TM2 has been successfully de-shuttered.
All went pretty much according to plan except I had to remove one fastener out of the upper wiring harness (the one that has just been installed)
to allow for enough clearance to rotated the shutter guide out of the way...I shutter to think what would have happened otherwise...anyways... |
Monday, May 11, 2015, 11:20, David Wang, South Hot-Cell, Standard Operation, TM2, , Target Hall Scheduled Activities April 07 - June 26 2015 6x
|
The schedule has some changes due to new TM2 source tray coil cooling line leaking at test stand. Now,It is re-scheduled in such an estimation
that TM2 source tray could be ready at teat stand by this Friday(May-15th). see attachment 1,2.
2015-05-12, Changed and updated the TH activity schedule according to Dons new beam schedule which is re-arranged after the coil line |
Monday, May 11, 2015, 10:45, Anders Mjos, Conditioning Station, Maintenance, , , RGA electronics box installed
|
The communications chip has been replaced. The electronics box has been grounded (see attached pdf). |
Thursday, May 07, 2015, 11:02, Travis Cave, South Hot-Cell, Repair, TM2, No target, Wiring of TM#2
|
Wires in TM#2 have been terminated at the top of the module. |
Wednesday, May 06, 2015, 14:30, Travis Cave, South Hot-Cell, Repair, TM2, No target, Wiring of TM#2 
|
Wires for TM#2 steering elements, and png gauge have been run down to the containment box level. Chad has placed them in the little cable trays. Slack
has been pulled back. and termination of the wire will be done on the 7th of May. A modification was done to the signal line of the png gauge wire ultem
block, as grounded screw was inserted to allow for strain relief so the end would hopefully quit breaking. See attached pictures for the details. |
Tuesday, May 05, 2015, 10:57, chad fisher, South Hot-Cell, Repair, TM2, , TM2 Wiring 
|
Old wiring was removed yesterday, new wiring run thru the vacuum chase. Old IMG gauge removed today, new cable trays installed and wires installed into
cable trays. |
Monday, May 04, 2015, 13:32, Anders Mjos, Conditioning Station, Maintenance, , , TK2 expansion tank topped up
|
Caled cyclotron ops to open P23 and confirmed penthouse valve open.
Filled up TK2 to 21 in water leve. |
Friday, May 01, 2015, 13:48, David Wang, South Hot-Cell, Standard Operation, TM2, , Target Hall Scheduled Activities April 07 - June 26 2015 update 
|
Target Hall Scheduled Activities April 07 - June 26 2015 update. 2015-05-01. All TH scheduled jobs are finished on time
this week. |
Friday, May 01, 2015, 08:27, chad fisher, South Hot-Cell, Repair, TM2, , Containment Box Removal
|
Containment box has been removed in preparation for wire replacement. |
Thursday, April 30, 2015, 08:50, Travis Cave, South Hot-Cell, Standard Operation, TM2, No target, Module move
|
TM#2 with no source tray has been moved from the north east silo to the south hot cell. |
|