865
|
Friday, March 20, 2015, 13:37 |
chad fisher | South Hot-Cell | Development | | | TM2 Optics Tray | Final assembly and alignment of TM2 optics
tray continued today. Front section is "aligned". |
|
|
866
|
Monday, March 23, 2015, 07:56 |
David Wang | ITE | Standard Operation | | | TH Shut Down Activities Schedule Feb 23th- Apr 15th update | This schedule is following Dons schedule
on module moves. See attachments for updating.
2015-03-27: Weekly update the schedule. |
|
|
871
|
Wednesday, March 25, 2015, 10:37 |
chad fisher | South Hot-Cell | Development | | | TM2 optics tray build | TM2 optics tray build is continuing. Going
well. Hope to have assembly and alignment
finished by Friday. |
|
|
877
|
Monday, March 30, 2015, 07:38 |
David Wang | ITE | Standard Operation | TM4 | | TH Shut Down Activities Schedule Feb 23th- Apr 15th update | Updated schedule this morning after last
Fridays ISAC facility support group meeting.
Updated schedule on 2015-April -02. |
|
|
879
|
Tuesday, March 31, 2015, 11:36 |
chad fisher | South Hot-Cell | Development | TM2 | | TM2 Optics Tray Complete | TM2 optics tray is complete.
Master alignment tray: 0 up/down,
0 left/right |
|
|
882
|
Wednesday, April 01, 2015, 13:08 |
David Wang | ITE | Standard Operation | TM4 | | Replaced ITE tank to module 42X0.275 o-ring | I replaced ITE tank to module 42 ID X 0.275
o-ring. The o-ring is changed once a year
before the first beam time. The flanges was |
|
|
884
|
Friday, April 10, 2015, 15:40 |
David Wang | ITE | Standard Operation | TM4 | | 5 Shielding blocks have been transferred from ITW to ITE. | 5 shielding blocks have been transferred
to ITE. The ITE is configured to take proton
beam. |
|
|
885
|
Monday, April 13, 2015, 08:59 |
David Wang | ITE | Standard Operation | | | Target Hall Scheduled Activities April 07 - June 26 2015 | See attachments 1, 2 for target hall schedule
from 07 April to 26 June 2015. The first
TM1 move which is scheduled on 16 April 2015 |
|
|
886
|
Wednesday, April 15, 2015, 09:01 |
Anders Mjos | Conditioning Station | Development | | | Archiver variables added by Controls |
|
|
|
890
|
Monday, April 20, 2015, 07:27 |
David Wang | ITE | Standard Operation | TM4 | | Target Hall Scheduled Activities April 07 - June 26 2015 | Weekly target hall schedule update.2015-04-20
weekly target hall schedule update
2015-04-27 attachments 3,4. |
|
|
893
|
Tuesday, April 21, 2015, 13:01 |
Grant Minor | ITW | Development | TM2 | | TM2 MK4 Optics Tray - banana plug bore modification (on bench) | The MK4 optics tray prepared for TM2 (as
per ITA6082) had an undersized bore for the
banana plug, making insertion of the plug |
|
|
895
|
Wednesday, April 22, 2015, 11:05 |
David Wang | Conditioning Station | Standard Operation | TM1 | | electrical check on TM1 at CS under vacuum | I did an electrical check on TM1 at CS.
The resistance check:A-B 3.918m ohm, A-C
5.905m ohm,A-D 4.070m ohm,B-C5.462m ohm,B-D3.633m |
|
|
897
|
Thursday, April 23, 2015, 12:56 |
Anders Mjos | Conditioning Station | Maintenance | TM1 | | IG1 Good Vacuum limit changed | Changed by Dave Morris.
New value is 1E-5 T (old value was
7.09E-5 T) |
|
|
899
|
Monday, April 27, 2015, 16:12 |
Keith C Ng | South Hot-Cell | Development | TM2 | | Ceramic Standoffs in TM2 source tray steerer assembly | On drawing ITA6008 for the Encole 0.5"
ceramic standoffs there is a note to match
pairs of ceramics to within +/-0.001". |
|
|
900
|
Monday, April 27, 2015, 17:09 |
Grant Minor | ITE | Development | TM2 | | TM2 - New Source Tray - Water Block Seal Groove Inspection Report | The water blocks soldered to the TM2 cooling
lines (see Ref. Assy. ITA6144) were inspected.
See attached inspection reports and |
|
|
903
|
Tuesday, April 28, 2015, 11:09 |
Anders Mjos | ITW | Maintenance | | | Resistance measured of TGHT and TBHT lines to ITW | The new TBHT and TGHT power supplies were
brough up to high current; 350 A and 420
A respectively. The TGHT power supply was |
|
|
907
|
Friday, May 01, 2015, 08:27 |
chad fisher | South Hot-Cell | Repair | TM2 | | Containment Box Removal | Containment box has been removed in preparation
for wire replacement. |
|
|
908
|
Friday, May 01, 2015, 13:48 |
David Wang | South Hot-Cell | Standard Operation | TM2 | | Target Hall Scheduled Activities April 07 - June 26 2015 update | Target Hall Scheduled Activities
April 07 - June 26 2015 update.
2015-05-01. All TH scheduled |
|
|
909
|
Monday, May 04, 2015, 13:32 |
Anders Mjos | Conditioning Station | Maintenance | | | TK2 expansion tank topped up | Caled cyclotron ops to open P23 and confirmed
penthouse valve open.
Filled up TK2 to 21 in water leve. |
|
|
910
|
Tuesday, May 05, 2015, 10:57 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 Wiring | Old wiring was removed yesterday, new wiring
run thru the vacuum chase. Old IMG gauge
removed today, new cable trays installed |
|