845
|
Tuesday, February 17, 2015, 13:06 |
Anders Mjos | ITE | Development | | | Resistance measured of TGHT and TBHT lines to ITE | The copper bars was installed by David
and Anders. After the measurements were completed,
the copper bars were removed. |
 |
846
|
Tuesday, February 17, 2015, 13:07 |
Anders Mjos | ITW | Development | | | Resistance measured of TGHT and TBHT lines to ITW | See e-log entry
for ITE for details. The copper bars have
not been removed. They can be used for testing |
|
847
|
Monday, February 23, 2015, 12:28 |
David Wang | ITE | Maintenance | | | 2015 shut down coils and pedal wheels replacement on ITE water flow sensors. | Dan and I replaced pedal wheels and coils
on ITE water flow sensors. It is a shut down
job we did every two years. See attachment |
|
848
|
Wednesday, February 25, 2015, 10:44 |
David Wang | ITW | Maintenance | | | 2015 shut dwon ITW water sensor coils and pedal wheels replacement | Dan and I replaced pedal wheels and coils
on ITW water flow sensors. It is a shut
down job we did every two years. See attachment |
|
849
|
Thursday, February 26, 2015, 09:22 |
David Wang | ITW | Standard Operation | | | TH Shut Down Activities Schedule Feb 23th- Mar 25th | TH shut down activities schedule from Feb
23th-March 25th. The schedule will be updated
each week. See attachment 1. |
 |
850
|
Friday, February 27, 2015, 09:34 |
chad fisher | South Hot-Cell | Maintenance | | | Hot cell Entry February 25 2015 | See attached report.
Summary:
Radio problems just before entry |
|
852
|
Thursday, March 05, 2015, 06:44 |
David Wang | ITE | Maintenance | TM4 | | 5 Shielding blocks have been moved to ITE. | 5 Shielding blocks have been moved to ITE
for next week TM1 move and RPG Radon test. |
|
853
|
Thursday, March 05, 2015, 07:17 |
David Wang | ITW | Standard Operation | | | TH Shut Down Activities Schedule Feb 23th- Apr 15th update | TH shut down jobs are processing as scheduled
this week. Discussed with Don, and we think
the jobs scheduled in next week should be |
6x |
854
|
Thursday, March 05, 2015, 14:30 |
chad fisher | South Hot-Cell | Development | | | Dissection Box | Box for dissecting targets almost complete.
Should be done tomorrow. |
|
855
|
Monday, March 09, 2015, 09:42 |
chad fisher | South Hot-Cell | Development | | | Hot Cell Table Swiping | 3 swipes of the south hot cell table were
taken from the target hall through the roof
hatch (2 standard, 1 alpha). |
|
859
|
Thursday, March 12, 2015, 13:04 |
David Wang | ITE | Standard Operation | TM4 | | 5 Shielding blocks have been transferred from ITE to ITW. | 5 shielding blocks have been transferred
from ITE to ITW for next week TM4 move. |
|
865
|
Friday, March 20, 2015, 13:37 |
chad fisher | South Hot-Cell | Development | | | TM2 Optics Tray | Final assembly and alignment of TM2 optics
tray continued today. Front section is "aligned". |
![20150320_113132[2].jpg 20150320_113132[2].jpg](attachment.png) |
866
|
Monday, March 23, 2015, 07:56 |
David Wang | ITE | Standard Operation | | | TH Shut Down Activities Schedule Feb 23th- Apr 15th update | This schedule is following Dons schedule
on module moves. See attachments for updating.
2015-03-27: Weekly update the schedule. |
   |
871
|
Wednesday, March 25, 2015, 10:37 |
chad fisher | South Hot-Cell | Development | | | TM2 optics tray build | TM2 optics tray build is continuing. Going
well. Hope to have assembly and alignment
finished by Friday. |
  |
877
|
Monday, March 30, 2015, 07:38 |
David Wang | ITE | Standard Operation | TM4 | | TH Shut Down Activities Schedule Feb 23th- Apr 15th update | Updated schedule this morning after last
Fridays ISAC facility support group meeting.
Updated schedule on 2015-April -02. |
   |
879
|
Tuesday, March 31, 2015, 11:36 |
chad fisher | South Hot-Cell | Development | TM2 | | TM2 Optics Tray Complete | TM2 optics tray is complete.
Master alignment tray: 0 up/down,
0 left/right |
  |
882
|
Wednesday, April 01, 2015, 13:08 |
David Wang | ITE | Standard Operation | TM4 | | Replaced ITE tank to module 42X0.275 o-ring | I replaced ITE tank to module 42 ID X 0.275
o-ring. The o-ring is changed once a year
before the first beam time. The flanges was |
    |
884
|
Friday, April 10, 2015, 15:40 |
David Wang | ITE | Standard Operation | TM4 | | 5 Shielding blocks have been transferred from ITW to ITE. | 5 shielding blocks have been transferred
to ITE. The ITE is configured to take proton
beam. |
|
885
|
Monday, April 13, 2015, 08:59 |
David Wang | ITE | Standard Operation | | | Target Hall Scheduled Activities April 07 - June 26 2015 | See attachments 1, 2 for target hall schedule
from 07 April to 26 June 2015. The first
TM1 move which is scheduled on 16 April 2015 |
   |
886
|
Wednesday, April 15, 2015, 09:01 |
Anders Mjos | Conditioning Station | Development | | | Archiver variables added by Controls |
|
|