Thursday, February 26, 2015, 09:22, David Wang, ITW, Standard Operation, , , TH Shut Down Activities Schedule Feb 23th- Mar 25th 
|
TH shut down activities schedule from Feb 23th-March 25th. The schedule will be updated each week. See attachment 1.
Feb-27-2015: Updated the schedule, and uploaded as PDF file. See attachment 2. |
Monday, March 02, 2015, 10:52, David Wang, ITE, Maintenance, TM4, UCx, ITE primary and secondary vacuum vessels leak check.
|
Dan and I leak checked ITE primary and secondary vacuum vessels with TM4 in ITE. The leak detector was hooked to ITE TP2 BV2. Leak detector
base leak rate: 0.0xE-09 atm.cc/sec, base pressure: 0.0xE-4 torr. All secondary vacuum vessel seals has been checked(helium spray), and no leak has been
found. On the ITE primary vacuum vessel, we leak checked every thing except the TM4 service cap and water lines inside the TM4. NO leak has been |
Thursday, March 05, 2015, 06:44, David Wang, ITE, Maintenance, TM4, , 5 Shielding blocks have been moved to ITE.
|
5 Shielding blocks have been moved to ITE for next week TM1 move and RPG Radon test. |
Thursday, March 05, 2015, 07:17, David Wang, ITW, Standard Operation, , , TH Shut Down Activities Schedule Feb 23th- Apr 15th update 6x
|
TH shut down jobs are processing as scheduled this week. Discussed with Don, and we think the jobs scheduled in next week should be processed as we planned.
See attachments for updated schedule.
I updated the schedule today. See attachment 3, 4 for updating. 2015-Mar-10. |
Thursday, March 12, 2015, 13:04, David Wang, ITE, Standard Operation, TM4, , 5 Shielding blocks have been transferred from ITE to ITW.
|
5 shielding blocks have been transferred from ITE to ITW for next week TM4 move. |
Monday, March 23, 2015, 07:56, David Wang, ITE, Standard Operation, , , TH Shut Down Activities Schedule Feb 23th- Apr 15th update   
|
This schedule is following Dons schedule on module moves. See attachments for updating.
2015-03-27: Weekly update the schedule. The shut down job is close to the end. See attachment 3, 4. |
Wednesday, March 25, 2015, 14:25, David Wang, South Hot-Cell, Standard Operation, TM4, Ta#45, Leak check on TM4 HS water line with new Ta#45 target. at SHC
|
Chad and I leak checked TM4 HS water line with new Ta#45 target installed at SHC. Leak detector base leak rate 0.0Xe-9 atm.cc/sec, base pressure 0.0Xe-4
torr. Chad sprayed helium twice on each of HS 2 VCR joints.No leak has been found. The joints are leak tight. The helium pressure test will be done
at CS later. |
Wednesday, March 25, 2015, 14:34, David Wang, Conditioning Station, Standard Operation, TM4, Ta#45, TM4 and CS turbo- pumps are started .
|
I connected TM4 and CS vacuum system after TM4 move. CS roughing pump was started first this morning. Later, Anders, Bill and I started 3 turbo pumps
on TM4 and CS. The pumping down is good so far. The CS vacuum system ion gauges are turned on also. |
Friday, March 27, 2015, 10:03, David Wang, Conditioning Station, Standard Operation, TM4, Ta#45, Helium pressure test on TM4 HS line at CS  
|
The helium pressure test on TM4 HS line at conditioning station is done. No leak. I also leak checked all vacuum seals on TM4 service cap. They are all
good. |
Friday, March 27, 2015, 11:29, David Wang, Conditioning Station, Standard Operation, TM4, Ta#45, TM4 is connected at CS  
|
TM4 has been connected at CS which includes high current cables, water lines, EE cable, and Enizel lens cable. The HV cover has been installed
onto the TM4 service cap.The CS water system is started. All water signals are good so far. Anders will start HV and heaters conditioning
on next Monday. |
Monday, March 30, 2015, 07:38, David Wang, ITE, Standard Operation, TM4, , TH Shut Down Activities Schedule Feb 23th- Apr 15th update   
|
Updated schedule this morning after last Fridays ISAC facility support group meeting.
Updated schedule on 2015-April -02. See attachments 3,4. The scheduled all shut down jobs are done on time.The TM2 move to SHC will be delayed
to May.There will be a new beam running time TH activities schedule (start from April 15) replacing this shut down schedule on next time weekly update. |
Wednesday, April 01, 2015, 06:56, David Wang, Conditioning Station, Standard Operation, TM4, Ta#45, TM4 has been disconnected at CS.
|
TM4 has been disconnected at CS. The CS and TM4 is venting for move. Anders stopped vacuum and water system yesterday. |
Wednesday, April 01, 2015, 13:08, David Wang, ITE, Standard Operation, TM4, , Replaced ITE tank to module 42X0.275 o-ring    
|
I replaced ITE tank to module 42 ID X 0.275 o-ring. The o-ring is changed once a year before the first beam time. The flanges was cleaned and the new
o-ring was installed. It works fine. |
Wednesday, April 01, 2015, 13:12, David Wang, ITE, Standard Operation, TM4, Ta#45, TM4 has been connected in ITE
|
TM4 has been connected in ITE. ITE six turbo-pumps have been started. So far so good. |
Friday, April 10, 2015, 15:40, David Wang, ITE, Standard Operation, TM4, , 5 Shielding blocks have been transferred from ITW to ITE.
|
5 shielding blocks have been transferred to ITE. The ITE is configured to take proton beam. |
Monday, April 13, 2015, 08:59, David Wang, ITE, Standard Operation, , , Target Hall Scheduled Activities April 07 - June 26 2015   
|
See attachments 1, 2 for target hall schedule from 07 April to 26 June 2015. The first TM1 move which is scheduled on 16 April 2015 could be delayed
because of SHC operator availability. I will update the schedule once Don confirms the move date with Isaac.
Updated the schedule. The TM1 move has been re-scheduled to Friday, 17 April 2015. See attachments 3,4. |
Monday, April 20, 2015, 07:27, David Wang, ITE, Standard Operation, TM4, , Target Hall Scheduled Activities April 07 - June 26 2015   
|
Weekly target hall schedule update.2015-04-20
weekly target hall schedule update 2015-04-27 attachments 3,4. |
Monday, April 20, 2015, 10:22, David Wang, Conditioning Station, Standard Operation, TM1, UCx12, TM1 with UCx12 has been connected to CS and ready for conditioing.
|
The TH will be locked during the TM1 conditioning time due to an interference issue between CS HV cover and a gas analysis valve on top of TM1.
A work permit has been issued for the conditioning job because of it. |
Wednesday, April 22, 2015, 11:05, David Wang, Conditioning Station, Standard Operation, TM1, , electrical check on TM1 at CS under vacuum
|
I did an electrical check on TM1 at CS. The resistance check:A-B 3.918m ohm, A-C 5.905m ohm,A-D 4.070m ohm,B-C5.462m ohm,B-D3.633m ohm. They are very
close to the check we did in SHC. The only unusual thing I found during the check is the ohmmeter reading between A and 60 KV common (6.2K )and the Megga
reading between them at 250 V which is 0. I repeated 4 times and always got the same readings. However, after so many times check, the Megga reading |
Thursday, April 23, 2015, 09:08, David Wang, Conditioning Station, Maintenance, TM1, UCx12, Huge Leak on TM1 contaiment box window.    
|
There is a huge leak on TM1 containment box window. I did a 70 psi helium pressure test on all TM1 water circuits this morning. The LD base leak rate
was 0.0XE-9 atm.cc/sec. When applying the 70 psi helium to containment box window circuit, the leak rate on LD jumped to 1XE-4 atm.cc/sec in 5 seconds.I
released the helium source right away,t but the conditioning station is full of helium molecules already, and the leak rate on LD stays at 1xE-5 |
|