  ID Date Authordown Category Type Module Target/Number Subject Text Attachments
  732   Monday, August 11, 2014, 14:30 David WangITEStandard OperationTM4UCx #10TM4 is connected in ITE.TM4 is connected in ITE. All ITE 
turbo pumps are started. I will check the
pumping down process tomorrow morning. Everything
  
  733   Wednesday, August 13, 2014, 12:21 David WangITERepairTM4UCx10ITE TP4S is replacedITE TP4S was broken down last night . I
stopped the ITE pumps and vented station
with Argon this morning. Edi and I replaced
  
  734   Wednesday, August 20, 2014, 10:25 David WangITEStandard OperationTM4 5 Shielding blocks have been transferred from ITW to ITE.5 Shielding blocks have been transferred
from ITW to ITE. ITE  is configured
to take proton beam.
  
  735   Wednesday, September 03, 2014, 10:50 David WangITWStandard OperationTM1  TM1 has been disconnected in ITW.  TM1 has been disconnected in ITW.   
  739   Thursday, September 04, 2014, 09:47 David WangSouth Hot-CellStandard OperationTM1 Leak check on TM1 HS water line with new target installedChad and I  leak checked the TM1 HS
line with new target installed. Base leak
rate 0.0xe-9 atm.cc/sec. No any response
  
  740   Thursday, September 04, 2014, 11:19 David WangConditioning StationStandard OperationTM1 TM1 is connected in CS.TM1 is connected in CS. All turbo pumps
are started.
  
  741   Friday, September 05, 2014, 07:15 David WangConditioning StationStandard OperationTM1 helium pressure test on TM1 HS water line at CS.Helium pressure test on TM1 HS water line
at CS is done. 80psi helium with LD 0.0xE-9
atm.cc/sec. 3 minutes test and no response
  
  743   Monday, September 08, 2014, 13:44 David WangConditioning StationStandard OperationTM1ZrC#6TM1 is disconnected at CS.Stopped TM1 and CS turbo pumps. Disconnected
TM1 at CS. The CS and TM1 are under vacuum
and naturally leak up. I will vent it on
  
  744   Wednesday, September 10, 2014, 07:12 David WangITWRepairTM1 Removed ITW HS and COIL flow rate monitors.Removed ITW HS and COIL flow rate monitors
installed at the beginning of this year.
They were installed on these two circuits
  
  746   Wednesday, September 10, 2014, 11:47 David WangITWStandard OperationTM1 TM1 has been connected in ITW.TM1 has been connected in ITW.  ITW
and TM1 turbo pumps have been started. Water
is supplied to TM1 only. Everything is good
  
  749   Tuesday, September 16, 2014, 10:41 David WangITWStandard OperationTM1ZrC #45 Shielding blocks have been transferred from ITE to ITW.5 Shielding blocks have been transferred
from ITE to ITW. The ITW is configured to
take proton beam
  
  751   Tuesday, September 23, 2014, 11:49 David WangITEStandard OperationTM4UCx #10TM4 has been disconnected in ITE.TM4 has been disconnected and moved to
SHC from ITE. ITE was vented with argon before
move.
  
  755   Wednesday, September 24, 2014, 15:03 David WangSouth Hot-CellStandard OperationTM4Ta#44Leak check on TM4 HS water line with new Ta#44 target. at SHCThis morning Chad and I leak checked TM4
HS line with new Ta#44 target installed.
I calibrated LD before the check. Before
  
  756   Wednesday, September 24, 2014, 15:16 David WangITEStandard OperationTM4Ta#44Reconnected TM4 in ITE.TM4 has been reconnected back to ITE. I
started all turbo pumps on ITE and TM4. The
ITE TP4s was extremely difficult to start.
  
  759   Friday, October 10, 2014, 10:47 David WangConditioning StationDevelopmentTM3 TM3 has been connected in CSTM3 has been connected in CS. All water
supplies are bypassed theTM3 on the top of
the service cap. TM3 TP2 was difficult to
  
  762   Tuesday, October 14, 2014, 12:19 David WangITWStandard OperationTM1 TM1 was disconnected in ITW.TM1 was disconnected in ITW this morning.
Heat shield circuit is purged.
  
  768   Monday, October 20, 2014, 08:59 David WangConditioning StationDevelopmentTM3 Started TCS water system.I started TCS water system this morning
to check if the chillers work properly.
  
  769   Monday, October 20, 2014, 09:13 David WangConditioning StationDevelopmentTM3 TM3 TP2 failedTM3 TP2 stopped working this morning at
4:00 AM. I tried to start it but failed.
On normal start mode , It could not pass
  
  773   Wednesday, October 22, 2014, 09:41 David WangConditioning StationDevelopmentTM3 TM3 has been disconnected at CS.TM3 has been disconnected at CS. It is
vented and ready to move.
  
  778   Tuesday, November 04, 2014, 11:05 David WangSouth Hot-CellStandard OperationTM1ThO#1Leak check on TM1 HS water line withThO#1 installed.Chad and I leak checked HS line on TM1
with ThO#1 target installed. The LD pumped
down to base leak rate 0.0xE-9 atm.cc/sec,
  