1662
|
Tuesday, November 14, 2017, 14:34 |
David Wang | ITW | Standard Operation | TM2 | Ta#55 | TM2 has been connected in ITW. |
TM2 has been connected in ITW. All turbo-pumps are started. Everything works fine. |
1666
|
Wednesday, December 13, 2017, 15:32 |
Anders Mjos | Assembly/Bench Test | Maintenance | TM2 | | Source Tray inspection |
The Source tray was inspected in the RH shop today by Anders, Friedhelm and Jens. The routing of the lines are satisfactory, however a design proposal to remove the ground electrode line will be made. This design will have to ensure a proper connection from the electrode to ground (using the window cooling lines). All other lines are OK at this point. Some fine adjustments are expected after brazing and soldering to maintain high voltage separation. Photos are available on DocuShare Collection-21401 |
1670
|
Friday, December 22, 2017, 11:09 |
Anders Mjos | ITW | Standard Operation | TM2 | | Shut down High Active Cooling water |
Stopped MP1 today in preparation for the power outage over the holidays. both P-25 and P-26 breakers have been switched off to prevent inadvertent start of system |
1677
|
Tuesday, January 16, 2018, 10:36 |
Anders Mjos | Spent Target Vault | Standard Operation | TM2 | | Old TM2 Source Tray moved to Cyclotron basement |
The old TM2 Source Tray from 2009 has been moved to Cyclotron basement this morning. Source tray was stored in location 9. The box was moved from the vault to the ante-room yesterday. No contamination was found on the box. |
1686
|
Tuesday, February 13, 2018, 13:56 |
Anders Mjos | ITW | Standard Operation | TM2 | Ta#55 | Target module disconnected |
TM disconnected by David and Yasmine Feb 8th. One of the water couplings were leaking for a short while when disconnected. NCR 10836 submitted by Max |
1687
|
Wednesday, February 14, 2018, 10:06 |
Anders Mjos | ITW | Maintenance | TM2 | | Replaced parker couplings on Window cooling line |
By Anders & David. Couplings will be taken apart for inspection. |
1688
|
Friday, February 16, 2018, 13:46 |
Anders Mjos | ITW | Maintenance | TM2 | | Parker coupling inspection |
Findings and photos from the inspections attached. The inspection was conducted by Anders, David and Maico. |
Attachment 1: Used_Parker_FS251_Inspection.pdf
|
|
1691
|
Tuesday, March 06, 2018, 09:53 |
David Wang | ITW | Standard Operation | TM2 | | Tm2 and Tm4 vacuum disconnection |
The job is done. See attachment. |
Attachment 1: TM2_TM4_disconnection_Vacuum.pdf
|
|
1698
|
Monday, April 09, 2018, 09:57 |
Travis Cave | South Hot-Cell | Standard Operation | TM2 | Ta#55 | Module move |
TM#2 with Ta#55 has been moved from the west target station to the south hot cell. |
1723
|
Thursday, May 24, 2018, 15:19 |
Keith C Ng | Assembly/Bench Test | Repair | TM2 | | tm 2 source tray build |
Attached alignment check notes after brazing and fabrication.
First page lower half shows establishment of baseline using master jig
Second page top half shows the alignment of the target mounting plate jig and the steerer cone aperture.
Second page bottom half shows alignment of the master target jig. Master target jig needed the 9 pin and heat shield locating features removed to seat the target correctly.
Overall, source tray assembly sits .006" high on average (min .003", max .010"), .003" to the left with respect to ion beam axis. |
Attachment 1: 20180524_alignmentcheckresults.pdf
|
|
1724
|
Friday, May 25, 2018, 11:41 |
Travis Cave | South Hot-Cell | Standard Operation | TM2 | no target | Module move |
TM#2 has been moved from the south hot cell to the conditioning station. |
1726
|
Wednesday, May 30, 2018, 09:51 |
David Wang | Conditioning Station | Repair | TM2 | | TM2 water lines helium pressure test at TCS. |
I did a helium pressure test on TM2 water lines at TCS. We will remove the TM2 source tray soon so this test is a reference check for future new source. The result:
Helium 70 psi, 2 minutes to each circiut. Leak detector base LR.0.0x e-9atm.cc/sec, base pressure 0.0x e-4torr
Ta+(A) 0.0x e-9atm.cc/sec
Ta-(B) 0.0x e-9atm.cc/sec
Tu-(C) 7.8x e-7 atm.cc/sec
Tu+(D) 3.5x e-7 atm.cc/sec
Coil 2(PU) 0.0x e-9atm.cc/sec
Coil 1(RU) 0.0x e-9atm.cc/sec
EE 8.2 x e-9atm.cc/sec
MSP 0.0x e-9atm.cc/sec
Containment box window 0.0 xe-9atm.cc/sec
HS no target and opened. No test.
All water lines on module side in TM2 should be in good condition according to this test . The leak response we found on B and C lines are from water block seals mostly. |
1727
|
Wednesday, May 30, 2018, 09:55 |
David Wang | Conditioning Station | Repair | TM2 | | TM2 and TCS vacuum pumps are switched off. |
I switched off TM2 and TCS vacuum pumps. The TCS and TM2 will be under vacuum without pumping. |
1733
|
Friday, June 08, 2018, 11:36 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 Source Tray Removal Progress |
The containment box has been removed from TM2, the Enzel lens and steerers disconnected and optics tray removal has commenced. |
Attachment 1: TM2_06082018.jpg
|
|
1734
|
Friday, June 08, 2018, 14:24 |
Travis Cave | South Hot-Cell | Standard Operation | TM2 | no target | Module move |
TM#2 has been moved from the conditioning station to the south hot cell. |
1735
|
Monday, June 11, 2018, 11:30 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 containment box on |
Tm2 containment box has been re-installed onto TM2. |
1736
|
Tuesday, June 12, 2018, 11:26 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM4 Optics Tray |
I have "slung" the TM4 optics tray in preparation for its removal. |
Attachment 1: fh.jpg
|
|
1743
|
Wednesday, June 27, 2018, 14:56 |
Travis Cave | South Hot-Cell | Standard Operation | TM2 | no target | Module move |
TM2 has been moved from the silo to the south hot cell. |
1745
|
Friday, June 29, 2018, 10:15 |
chad fisher | South Hot-Cell | Standard Operation | TM2 | | TM2 work and target install |
On Thursday, June 29th the containment box of TM2 was removed and the optics tray re-installed and reconnected. The box was then re-installed.
Friday the window waterlines were leak checked, Nb target installed (with new fasteners, high current torqued to 130 in*lbs) target leak and electrical checked and containment box cover installed with new fasteners. |
1747
|
Friday, June 29, 2018, 13:36 |
Travis Cave | South Hot-Cell | Standard Operation | TM2 | Nb#8 | Electrical Check |
The results of the various electrical checks performed on the TM#2 with and without the Nb#8 target attached. |
Attachment 1: TM2_elec_chk_steerers_and_lens_062818.pdf
|
|
Attachment 2: TM2_Nb8_elec_chk_shc.pdf
|
|
Attachment 3: TM2_notgt_elec_chk_shc_062918.pdf
|
|