Wednesday, August 09, 2023, 09:41, David Wang, North Hot-Cell, Standard Operation, TM2, Nb#10, TM2 Nb# 10 electrical and leak check at NHC
|
Nb#10 has been installed on TM2 . electrical and leak check on HS line are good. See attachment. |
Wednesday, August 09, 2023, 13:13, David Wang, Conditioning Station, Standard Operation, TM2, Nb#10, Tm2 Nb#10 has been connect at TCS.
|
TM2 Nb#10 has been connect at TCS. TCS water system and vacuum system have been started. Everything looks ok so far. TCS Faraday cage is secured for
TM2 conditioning at TCS. |
Tuesday, August 15, 2023, 13:58, Frank Song, ITW, Standard Operation, TM2, Nb#10, Module Connection
|
TM2 with new target Nb#10 was moved to ITW from TCS and re-connected in pit. TPs are running at their full speed. |
Friday, August 25, 2023, 07:22, Frank Song, ITW, Repair, TM2, Nb#10, module disconnection
|
TM2 with target Nb#10 was disconnected in ITW yesterday for beam production issue investigation. |
Thursday, June 27, 2024, 09:49, David Wang, North Hot-Cell, Standard Operation, , Nb#10, Nb#10target has been remotely transferred from NHC to SHC.
|
Nb#10target has been remotely transferred from NHC to SHC. |
Tuesday, August 20, 2024, 11:53, Carla Babcock, South Hot-Cell, Standard Operation, , Nb#10, Nb#10 PIE
|
Nb#10 never worked online - repeller had no effect on the beam and one of the RF wires was touching HVC. Max 60pA was seen on the source cup. See notes
here ITW-TM2-Nb#10/#11-LP-IGLIS
(Web |
Monday, August 26, 2024, 09:57, Travis Cave, Spent Target Vault, Standard Operation, , Nb#10, Spent Target Move
|
Nb#10 was placed in pail#295 and moved from the south hot cell to the spent target vault, spot 4A, it was 230uSv/hr when removed from the SHC.
See attached PDF for vault details. |
Friday, November 18, 2011, 16:29, Bevan Moss, Conditioning Station, Standard Operation, TM1, N/A, High Voltage (HV) testing
|
TM1 was high voltage tested without a target on November 16, 2011 with Don Jackson, Pierre Bricault, and Bevan Moss. The module was able to hold
up to 25 kV but between that and 32 kV there was lots of discharge which could be measured in the vacuum. See the attached plot for the voltage current
and sparks. |
Wednesday, June 20, 2012, 11:39, Grant Minor, South Hot-Cell, Development, TM3, N/A, TM3 Planned Activites at South Hot Cell Jun 20 to 29 2012
|
Normal
0
false
false
false
EN-CA
X-NONE
X-NONE
|
Thursday, June 21, 2012, 14:30, chad fisher, South Hot-Cell, Repair, TM3, N/A, TM3 Refurbishment Start
|
Started refurb of TM3.
Planned activities:
Inspection |
Thursday, June 21, 2012, 14:33, chad fisher, South Hot-Cell, Repair, TM3, N/A, Pictures TM3 June 21st 8x
|
Here are the pictures from today...there is video too but it is not uploaded yet. |
Monday, June 25, 2012, 07:53, chad fisher, South Hot-Cell, Repair, TM3, N/A, TM3 Refurb. Work
|
On Friday, June 22 the following work was carried out.
Further inspection of the source tray.
Testing of existing tray removal and installation tool...it works fine, there was
just a specific method for proper coupling to the target module. There was no documentation for this tool, so it took a little bit of insight with |
Wednesday, December 05, 2012, 13:26, Grant Minor, South Hot-Cell, Standard Operation, TM4, N/A, TM4 moved from SHC to South West Silo
|
TM4 was successfully moved from the South Hot Cell to the South-West Silo remotely by Grant Minor, with help from David Wang and Don Jackson. The
move was without problems. See ISAC Work Permit 2012-12-04-1. |
Wednesday, April 17, 2013, 15:17, Bevan Moss, Conditioning Station, Standard Operation, TM3, N/A, Turbo Pumps Failed
|
Both Turbo pumps on TM3 have failed. They were both attempted to start in soft mode. TP2 could only achieve ~19kpm and TP1 ~10kpm. I have
turned off the scroll pump and vented through the turbo pumps. |
Friday, April 19, 2013, 10:48, Bevan Moss, Conditioning Station, Maintenance, TM3, N/A, Turbo Pump 2 replaced
|
Turbo Pump 2 has been replaced on TM3. I got a count of 350 on the sleeve of my tank suit. |
Friday, April 19, 2013, 10:48, Bevan Moss, Conditioning Station, Maintenance, TM3, N/A, Turbo Pump 2 replaced
|
Turbo Pump 2 has been replaced on TM3. I got a count of 350 on the sleeve of my tank suit. |
Friday, April 19, 2013, 10:51, Bevan Moss, Conditioning Station, Standard Operation, TM3, N/A, Roughing Started 10:48
|
With the Turbo pump replaced I have started roughing at 10:48 |
Friday, April 19, 2013, 13:32, Bevan Moss, Conditioning Station, Standard Operation, TM3, N/A, Turbo Pumps Started
|
Both Turbo Pumps are now operational. |
Friday, April 19, 2013, 15:25, Bevan Moss, Conditioning Station, Standard Operation, TM3, N/A, Turbo Pumps Started
|
Bevan Moss wrote:
Both Turbo Pumps are now operational. |
Monday, April 22, 2013, 11:31, Bevan Moss, Conditioning Station, Standard Operation, TM3, N/A, Cooling Package Started
|
Cooling Package was started at 9:25 this morning inlet conductivity is 0.08 Mohm at 22.9C. Resistance reached 5.33 Mohm by 11:30 |
|