ID |
Date |
Author |
Category |
Type |
Module |
Target/Number |
Subject |
Text |
 |
|
443
|
Wednesday, September 04, 2013, 19:01 |
Grant Minor | South Hot-Cell | Repair | TM3 | | Inspection / Ante Room Leak Check Results on TM3 Heat Shield lines (3 Sept 2013) | Yesterday, Grant entered the Ante Room
with David Wang to visually inspect the two
sets of failed c-seals from the Heat Shield |
|
|
445
|
Friday, September 06, 2013, 17:50 |
Grant Minor | South Hot-Cell | Development | TM3 | | C-Seal crush investigation |
|
|
|
489
|
Friday, October 04, 2013, 19:05 |
Grant Minor | Conditioning Station | Standard Operation | TM3 | NiO#2 | HP Conditioning - e-mail notes from Oct 2nd to Oct 4th | I have compiled the e-mail comments from
people involved in High-Power Conditioning
of TM3 w/ the new Rev 3 source tray and NiO#2 |
|
|
490
|
Friday, October 04, 2013, 19:39 |
Grant Minor | Conditioning Station | Standard Operation | TM3 | NiO#2 | TCS vacuum improvement w/ heaters off - 2:20 pm to 7:17pm | Here is the change in the TCS vacuum after
heaters were turned off earlier today:
2:20 pm readings |
|
|
500
|
Tuesday, October 08, 2013, 18:12 |
Grant Minor | Crane | Repair | TM4 | | Target Hall Crane Stuck in East-West Direction - Update | Grant Minor wrote this e-mail today:
***
Hello all, |
 |
|
501
|
Wednesday, October 09, 2013, 19:33 |
Grant Minor | Crane | Repair | TM4 | | Target Hall Crane not operational - likely controls / PLC hardware failure (not stuck wheel) |
|
|
|
503
|
Tuesday, October 15, 2013, 16:44 |
Grant Minor | Crane | Repair | | | Target Hall Crane - operational with temporary thermal sensor bypass | E-mail correspondence on the Target Hall
crane fault diagnosis between October 11th
and 15th: |
|
|
505
|
Wednesday, October 16, 2013, 18:53 |
Grant Minor | ITE | Repair | | | ITE Harp 9 Removed & Blanked-Off - blocks NOT YET replaced | The blocks above the pre-separator section
of the ISAC beam lines were removed today
in the Target Hall by Bevan Moss and Chad |
11x |
|
507
|
Thursday, October 17, 2013, 17:16 |
Grant Minor | ITE | Repair | | | Pre-Separator-area (ITE Harp 9) Blocks Replaced | The pre-separator-area blocks were replaced
today by Bevan and Travis, with Grant present
for photos and observation. |
8x |
|
526
|
Thursday, October 24, 2013, 15:54 |
Grant Minor | South Hot-Cell | Standard Operation | TM4 | Ta#41 | Target conductance |
|
|
|
660
|
Wednesday, May 14, 2014, 19:01 |
Grant Minor | ITE | Maintenance | TM3 | | HV short inspection at ITE | Friedhelm Ames commented to me that there
appears to be a short between High Voltage
and Ground at TM3 at ITE. |
|
|
699
|
Monday, July 07, 2014, 14:45 |
Grant Minor | ITE | Maintenance | TM3 | SiC #30 | FEBIAD gas line check | There were some problems this morning with
provision of FEBIAD gas to the the target
at ITE. It was suspected that the gas |
|
|
714
|
Thursday, July 24, 2014, 18:21 |
Grant Minor | South Hot-Cell | Repair | TM2 | No target / no source tray | Leak check on TM2 ionizer tube cooling lines C and D - module side | Target Ionizer tube cooling lines "C"
and "D" in Target Module 2 were
both leak checked at the Hot Cell. |
  |
|
823
|
Monday, December 15, 2014, 15:55 |
Grant Minor | Conditioning Station | Repair | | | Access to ISAC TCS TK2 Expansion Tank - Fall Arrest | Hello all,
Access was required this morning to |
   |
|
893
|
Tuesday, April 21, 2015, 13:01 |
Grant Minor | ITW | Development | TM2 | | TM2 MK4 Optics Tray - banana plug bore modification (on bench) | The MK4 optics tray prepared for TM2 (as
per ITA6082) had an undersized bore for the
banana plug, making insertion of the plug |
   |
|
900
|
Monday, April 27, 2015, 17:09 |
Grant Minor | ITE | Development | TM2 | | TM2 - New Source Tray - Water Block Seal Groove Inspection Report | The water blocks soldered to the TM2 cooling
lines (see Ref. Assy. ITA6144) were inspected.
See attached inspection reports and |
   |
|
917
|
Tuesday, May 26, 2015, 11:49 |
Grant Minor | Assembly/Bench Test | Repair | TM2 | | TM2 New Source Tray - Braze & Solder Report - 22 May 2015 | Hello,
For reference, I have attached a list |
6x |
|
941
|
Wednesday, June 10, 2015, 16:49 |
Grant Minor | Assembly/Bench Test | Repair | TM2 | | TM2 New Source Tray - *HOLD* on installation into Hot Cell until HV approval | Don Jackson brought to my attention some
potential HV minimum spark gap issues
with the source tray cooling lines. |
  |
|
1003
|
Monday, July 20, 2015, 17:11 |
Grant Minor | South Hot-Cell | Repair | TM2 | | TM2 New Source Tray - additional photos 20 July 2015 | A few additional higher-resolution photos
of the TM2 source tray with new spacer ITA6270,
and bent copper ground line clip. |
  |
|
1005
|
Tuesday, July 21, 2015, 10:40 |
Grant Minor | Assembly/Bench Test | Repair | TM2 | | TM2 - bench inspection photos from 6-June-2015 | |
  |