101
|
Tuesday, May 15, 2012, 12:14 |
chad fisher | South Hot-Cell | Standard Operation | TM4 | SiC#26 | SiC#26 removal TM4 degredation |
SiC#26 was removed from target module #4 this morning. Target shows the now standard arc marks on the 9 pin connector housing...pictures to follow.
Of greater concern is the amount of "plating out" or "arc" marks on both the insulators and connductor of the TM4 source tray. I will again warn that the source trays historically have a life expectancy, and that TM4 continues to show visual signs that the current source tray is rapidly approaching the end of its useful life!
I understand that one of this years goals is to retrofit TM3; however I fear TM4(and possibly TM1) may fail before this can be released. With the current absence of backup source trays and modules I fear we leave the ISAC program in a very vulnerable position.
|
Attachment 1: RHB_2236.JPG
|
|
Attachment 2: RHB_2237.JPG
|
|
Attachment 3: RHB_2238.JPG
|
|
Attachment 4: RHB_2239.JPG
|
|
Attachment 5: RHB_2240.JPG
|
|
Attachment 6: RHB_2241.JPG
|
|
Attachment 7: RHB_2242.JPG
|
|
Attachment 8: RHB_2243.JPG
|
|
Attachment 9: RHB_2244.JPG
|
|
Attachment 10: RHB_2245.JPG
|
|
Attachment 11: RHB_2246.JPG
|
|
Attachment 12: RHB_2247.JPG
|
|
Attachment 13: RHB_2248.JPG
|
|
Attachment 14: RHB_2249.JPG
|
|
Attachment 15: RHB_2250.JPG
|
|
Attachment 16: RHB_2251.JPG
|
|
Attachment 17: RHB_2251.JPG
|
|
Attachment 18: RHB_2252.JPG
|
|
Attachment 19: RHB_2253.JPG
|
|
|
103
|
Wednesday, May 16, 2012, 10:35 |
Travis Cave | Spent Target Vault | Standard Operation | | SiC#26 | Spent target move |
SiC #26 was moved from the south hot cell into storage today. The target was is in pail # 94 and was placed in slot 1B in the storage vault. The fields of the pail at the hot cell were 118mSv/hr upon pail been removed from the hot cell. Attached is the current status of the storage vault. |
Attachment 1: Vault_Storage_May_16_2012.pdf
|
|
|
1789
|
Friday, September 21, 2018, 10:07 |
David Wang | ITW | Standard Operation | TM2 | SiC nano | TM2 with SiC nano target was has been connected in ITW. |
Tm2 with SiC nano has been connected in ITW. See attachment for checklist |
Attachment 1: TM2_with_SiC_nano_connection_in_ITW..pdf
|
|
|
1806
|
Tuesday, October 23, 2018, 10:45 |
David Wang | ITW | Standard Operation | TM2 | SiC nano | TM2 was disconnected in ITW. |
TM2(SiC nano) has been disconnected in ITW. See attachment |
Attachment 1: TM2_SiC_nano_disconnection_in_ITW.pdf
|
|
|
2035
|
Friday, November 29, 2019, 13:10 |
David Wang | ITE | Standard Operation | TM2 | SiC 39# febiad | TM2 SiC#39 connection check list. |
TM2 has been connected in ITE. All turbo-pumps are started. |
Attachment 1: SiC_#_39_febiad_connection_checklist.pdf
|
|
|
2030
|
Tuesday, November 19, 2019, 13:41 |
David Wang | ITE | Standard Operation | TM2 | SiC 38# febiad | TM2 SiC#38 connection check list. |
TM2 was connected in ITE 12th Nov. attach checklist |
Attachment 1: SiC_#_38_febiad_connection_checklist.pdf
|
|
|
2032
|
Wednesday, November 27, 2019, 13:46 |
David Wang | Conditioning Station | Standard Operation | TM2 | SiC 38# febiad | TM2 SiC #38 disconnection checklist. |
TM2 was disconnected in ITE yesterday. |
Attachment 1: SiC_#_38_febiad_disconnection_checklist.pdf
|
|
|
2472
|
Tuesday, August 08, 2023, 12:59 |
David Wang | ITW | Standard Operation | TM2 | SiC #6 | TM2 SiC#6 dhas been disconnected in ITW |
TM2 SiC#6 has been disconnected in ITW. See check list |
Attachment 1: TiC#6_TM2_disconnection_checklist.pdf
|
|
|
2621
|
Wednesday, June 19, 2024, 14:16 |
David Wang | South Hot-Cell | Standard Operation | TM3 | SiC #46 | Tm3 electrical check with SiC#46 target at SHC |
Tm3 electrical check with SiC#46 target and HS line helium spray check at SHC. were done. everything is good. see attachment. |
Attachment 1: TM3_with_SiC_46#_target_electrical_check_at_SHC.pdf
|
|
|
2623
|
Tuesday, June 25, 2024, 11:59 |
David Wang | ITE | Standard Operation | TM3 | SiC #46 | Tm3 has been moved from TCS to ITE. |
Tm3 has been moved from TCS to ITE. the move is smooth. |
|
2624
|
Tuesday, June 25, 2024, 11:59 |
David Wang | ITE | Standard Operation | TM3 | SiC #46 | Tm3 has been moved from TCS to ITE. |
Tm3 has been moved from TCS to ITE. the move is smooth. |
|
2647
|
Thursday, August 08, 2024, 11:41 |
David Wang | South Hot-Cell | Standard Operation | TM3 | SiC #46 | Tm3 was moved from ITE to TCS this Tuesaday, then to SHC this morning. |
Tm3 was moved from ITE to TCS this Tuesday, then to SHC this morning. Both moves are successful. |
|
2648
|
Thursday, August 08, 2024, 13:58 |
David Wang | South Hot-Cell | Standard Operation | TM3 | SiC #46 | TM3 SiC#46 electrical check at SHC with target on (After operation) |
ABCD is short to 60KV bias. Othjer are ok. see attachment.
Found afterwards that this short was due to sparking through the multipin wire insulation where the wires pass behind the TBHT block "C". See fault 17265. |
Attachment 1: TM3_Sic_46_after_run_E_check.pdf
|
|
|
2356
|
Thursday, August 11, 2022, 09:10 |
David Wang | Conditioning Station | Standard Operation | TM4 | SiC #44 | HS line helium pressure test. Gas line fitting on module top and gas line leak check. |
HS line helium pressure test is done at TCS. No leak. I also leak checked gasline adapter and fittings on TM4 top. No leak. 1/4 copper gas line between module and ITE was leak checked yesterday. It is good. |
|
2077
|
Thursday, March 05, 2020, 07:16 |
David Wang | South Hot-Cell | Standard Operation | TM2 | SiC #39 | TM2 SiC #39 post run electrical checklist |
Electrical check result is fine. See attachment. |
Attachment 1: SiC_#39_post_run_cheklist..pdf
|
|
|
2078
|
Friday, March 06, 2020, 09:35 |
David Wang | Spent Target Vault | Standard Operation | | SiC #39 | Spent target SiC#39 removal from SHC to storage vault. |
Spent target SiC#39 is removed from SHC to storage vault at 4C in pail #227.The move is successful. Note:The small aluminum block holding wire on pail lid could be contaminated by SHC manipulator during the lid installation in SHC. |
|
927
|
Tuesday, June 02, 2015, 14:32 |
David Wang | South Hot-Cell | Standard Operation | TM4 | SiC #31 | Leak check on TM4 HS water line with new SiC #31 target. at SHC |
Chad and I leak checked TM4 HS water line with SiC #31 target installed. leak rate:0.0xE-9atm.cc/sec. No leak. The line will be helium pressurized at CS later.
2015-06-03, helium pressure test the line at CS. 70psi 3 minutes. leak rate 0.0xE-9 atm.cc/sec. No leak. See attachments |
Attachment 1: 003.JPG
|
|
Attachment 2: 005.JPG
|
|
Attachment 3: 001.JPG
|
|
|
929
|
Tuesday, June 02, 2015, 14:39 |
David Wang | Conditioning Station | Standard Operation | TM4 | SiC #31 | TM4 and CS turbo- pumps are started . |
TM4 and CS turbo-pumps are started this afternoon. Everything is good so far. |
|
932
|
Wednesday, June 03, 2015, 13:51 |
David Wang | Conditioning Station | Standard Operation | TM4 | SiC #31 | TM4 is connected at CS |
TM4 has been connected at CS. CS HV cover is installed.I made a pair of new cooling lines for TM window cooling at CS. The TM4 containment box window cooling line is connected to the HVC spare circuit now. I checked water flow visually, and it is good. The TM4 is ready for conditioning.See attachment for window cooling modification.
|
Attachment 1: 007.JPG
|
|
Attachment 2: 009.JPG
|
|
Attachment 3: 008.JPG
|
|
Attachment 4: 010.JPG
|
|
|
939
|
Wednesday, June 10, 2015, 11:49 |
David Wang | ITE | Standard Operation | TM4 | SiC #31 | TM4 has been connected in ITE |
Dan and I connected TM4 in ITE. At this stage, water is supplied to TM4 only. We checked the TM4 water signals from electrical room.They are good. The turbo-pumps will be started today once the roughing is done. |