Thursday, August 29, 2013, 12:03, Grant Minor, South Hot-Cell, Repair, TM3, no target, Heat Shield Circuit Leak  
|
Bevan Moss wrote:
|
Wednesday, September 04, 2013, 18:53, Grant Minor, South Hot-Cell, Repair, TM3, , Maico's measurements of new c-seals and bench-tested c-seals 
|
Today Maico measured the thickness of three indium-plated inconel c-seals, presumably Ultra-Seal P/N 50606. These seals had NOT been in the Hot
Cell.
|
Wednesday, September 04, 2013, 19:01, Grant Minor, South Hot-Cell, Repair, TM3, , Inspection / Ante Room Leak Check Results on TM3 Heat Shield lines (3 Sept 2013)
|
Yesterday, Grant entered the Ante Room with David Wang to visually inspect the two sets of failed c-seals from the Heat Shield circuit, to remove the
second set from the Heat Shield water blocks, and to leak check the heat shield circuit with o-rings and a water-block-to-leak-detector fitting.
Some photos of the inspected seals are in the attached design review presentation. Some unusual marks were observed on both sets of failed |
Friday, September 06, 2013, 17:50, Grant Minor, South Hot-Cell, Development, TM3, , C-Seal crush investigation
|
Bevan Moss wrote:
Today Maico completed the new leak testing tool and blank off. He tested them with C-seals without springs and |
Friday, October 04, 2013, 19:05, Grant Minor, Conditioning Station, Standard Operation, TM3, NiO#2, HP Conditioning - e-mail notes from Oct 2nd to Oct 4th
|
I have compiled the e-mail comments from people involved in High-Power Conditioning of TM3 w/ the new Rev 3 source tray and NiO#2 since Bevan Moss' last
log on October 2nd below:
On October 2nd at 6:35pm Friedhelm Ames wrote: |
Friday, October 04, 2013, 19:39, Grant Minor, Conditioning Station, Standard Operation, TM3, NiO#2, TCS vacuum improvement w/ heaters off - 2:20 pm to 7:17pm
|
Here is the change in the TCS vacuum after heaters were turned off earlier today:
2:20 pm readings
TCS:IG1 (service cap) 9.3 x 10^-7 Torr |
Tuesday, October 08, 2013, 18:12, Grant Minor, Crane, Repair, TM4, , Target Hall Crane Stuck in East-West Direction - Update 
|
Grant Minor wrote this e-mail today:
***
Hello all, |
Wednesday, October 09, 2013, 19:33, Grant Minor, Crane, Repair, TM4, , Target Hall Crane not operational - likely controls / PLC hardware failure (not stuck wheel)
|
Grant Minor wrote:
Grant Minor |
Tuesday, October 15, 2013, 16:44, Grant Minor, Crane, Repair, , , Target Hall Crane - operational with temporary thermal sensor bypass
|
E-mail correspondence on the Target Hall crane fault diagnosis between October 11th and 15th:
On 15/10/2013 3:34 PM, Grant Minor wrote:
Hello all, |
Wednesday, October 16, 2013, 18:53, Grant Minor, ITE, Repair, , , ITE Harp 9 Removed & Blanked-Off - blocks NOT YET replaced 11x
|
The blocks above the pre-separator section of the ISAC beam lines were removed today in the Target Hall by Bevan Moss and Chad Fisher with Lynne
LeMessurier present from RPG.
|
Thursday, October 17, 2013, 17:16, Grant Minor, ITE, Repair, , , Pre-Separator-area (ITE Harp 9) Blocks Replaced 8x
|
The pre-separator-area blocks were replaced today by Bevan and Travis, with Grant present for photos and observation.
Photos are attached of each block replacement.
Some difficulty was encountered in replacing the "Layer #3" blocks (photo 9 attached). An interference occurred between the outside |
Thursday, October 24, 2013, 15:54, Grant Minor, South Hot-Cell, Standard Operation, TM4, Ta#41, Target conductance
|
Anders Mjos wrote:
The conductance check on the electrical check was found to be outside of accepted values for the TBHT |
Wednesday, May 14, 2014, 19:01, Grant Minor, ITE, Maintenance, TM3, , HV short inspection at ITE
|
Friedhelm Ames commented to me that there appears to be a short between High Voltage and Ground at TM3 at ITE.
Friedhelm, Anders and I initiated a survey by Andrew from RPG, and entered the Target Hall at approximately 5pm to visually assess the HV cover
at the MAA. There was no clear indication of a problem. We opted to wait for David to return as we weren't sure exactly what we were looking |
Monday, July 07, 2014, 14:45, Grant Minor, ITE, Maintenance, TM3, SiC #30, FEBIAD gas line check
|
There were some problems this morning with provision of FEBIAD gas to the the target at ITE. It was suspected that the gas line was improperly
connected to the module, or that the valves at the module were not opened.
Remote Handling was asked to open the HV cover on TM3 at ITE and check the connection of the FEBIAD gas line. Grant Minor, Maico Dalla Valle, |
Thursday, July 24, 2014, 18:21, Grant Minor, South Hot-Cell, Repair, TM2, No target / no source tray, Leak check on TM2 ionizer tube cooling lines C and D - module side  
|
Target Ionizer tube cooling lines "C" and "D" in Target Module 2 were both leak checked at the Hot Cell. The lines were both
blanked-off.
Bill Paley was present with David Wang in the Target Hall, operating the leak detector. Grant Minor and Anders Mjos were present with Chad |
Monday, December 15, 2014, 15:55, Grant Minor, Conditioning Station, Repair, , , Access to ISAC TCS TK2 Expansion Tank - Fall Arrest   
|
Hello all,
Access was required this morning to the TCS TK2 Expansion Tank to open a valve and re-fill the tank. |
Tuesday, April 21, 2015, 13:01, Grant Minor, ITW, Development, TM2, , TM2 MK4 Optics Tray - banana plug bore modification (on bench)   
|
The MK4 optics tray prepared for TM2 (as per ITA6082) had an undersized bore for the banana plug, making insertion of the plug extremely difficult /
impossible.
Reference stores parts were collected to check the fit: male plug 3-4/01152 and female jack 1-6/1201. The size of the female jack was |
Monday, April 27, 2015, 17:09, Grant Minor, ITE, Development, TM2, , TM2 - New Source Tray - Water Block Seal Groove Inspection Report   
|
The water blocks soldered to the TM2 cooling lines (see Ref. Assy. ITA6144) were inspected.
See attached inspection reports and drawings.
It was found that only 18% of the seal groove diameters and 55% of the depths were in spec. |
Tuesday, May 26, 2015, 11:49, Grant Minor, Assembly/Bench Test, Repair, TM2, , TM2 New Source Tray - Braze & Solder Report - 22 May 2015 6x
|
Hello,
For reference, I have attached a list of all solder joints in the TM2 Source Tray, and the alloys used for the most recent build (as per ITA6144). |
Wednesday, June 10, 2015, 16:49, Grant Minor, Assembly/Bench Test, Repair, TM2, , TM2 New Source Tray - *HOLD* on installation into Hot Cell until HV approval  
|
Don Jackson brought to my attention some potential HV minimum spark gap issues with the source tray cooling lines. It appears:
- The gap between the Ground Electrode cooling lines (ground) and Heat Shield cooling lines (HV) does not meet the spec of 0.668" MIN |
|