ID Date Author Category Type Module Target/Number Subjectdown Text Attachments
  963   Friday, June 26, 2015, 09:44 chad fisherSouth Hot-CellRepairTM2 TM2 Retrofit StatusOn June 25th the following work was completed:
Optics tray was installed into TM2.
The lower fastener on the vertical cable
 20150625_075616_1.jpg20150625_083457.jpg20150625_105735.jpg20150625_110053.jpg 
  807   Tuesday, December 02, 2014, 10:15 chad fisherSouth Hot-CellRepairTM2 TM2 Reburb. Loop InstallFinal polish, clean with methanol and clean
compressed air.
Loop installed and torqued to 90
 TM2_20141202_01.jpg20141203_142215.jpg20141203_143530.jpg 
  805   Monday, December 01, 2014, 14:06 chad fisherSouth Hot-CellRepairTM2 TM2 REFURB. WATER LOOP TESTSome issues with the turntable and having
to wait for a decision on whether to remove
TM2 from the hot cell so that TM4 with dead
 TM2_20141201_01.JPGTM2_20141201_02.JPGTM2_20141201_03.JPGTM2_20141201_04.JPGTM2_20141201_05AC.jpg 
  951   Thursday, June 18, 2015, 08:03 chad fisherSouth Hot-CellRepairTM2 TM2 Optics Tray TransferThe TM2 optics tray has been transferred
from the source tray to the transfer fixture
in preparation for installation of the source
 20150618_075326_1.jpg 
  879   Tuesday, March 31, 2015, 11:36 chad fisherSouth Hot-CellDevelopmentTM2 TM2 Optics Tray CompleteTM2 optics tray is complete.
Master alignment tray: 0 up/down,
0 left/right
 20150331_OPTICS_FRONT.jpg20150331_OPTICS_MIDDLE.jpg20150331_OPTICS_BACK.jpg 
  865   Friday, March 20, 2015, 13:37 chad fisherSouth Hot-CellDevelopment  TM2 Optics TrayFinal assembly and alignment of TM2 optics
tray continued today. Front section is "aligned".
 20150320_113132[2].jpg20150320_113018_1[1].jpg 
  1003   Monday, July 20, 2015, 17:11 Grant MinorSouth Hot-CellRepairTM2 TM2 New Source Tray - additional photos 20 July 2015A few additional higher-resolution photos
of the TM2 source tray with new spacer ITA6270,
and bent copper ground line clip.
 3-8ths_gap_check_15July2015.JPGTM2_New_Source_Tray_20July2015.JPGTM2_Spacer_ITA6270_and_copper_ground_clip_detail_20July2015.JPG 
  917   Tuesday, May 26, 2015, 11:49 Grant MinorAssembly/Bench TestRepairTM2 TM2 New Source Tray - Braze & Solder Report - 22 May 2015Hello,

For reference, I have attached a list
 6x 
  941   Wednesday, June 10, 2015, 16:49 Grant MinorAssembly/Bench TestRepairTM2 TM2 New Source Tray - *HOLD* on installation into Hot Cell until HV approvalDon Jackson brought to my attention some
potential HV minimum spark     gap issues
with the source tray cooling lines. 
 ITA6144_RevC_markup_10Jun2015.pdfTM2_cooling_lines_too_close_GE_HS_10June2015.jpgTM2_cooling_lines_too_close_Window_MSP_10June2015.jpg 
  2474   Wednesday, August 09, 2023, 09:41 David WangNorth Hot-CellStandard OperationTM2Nb#10TM2 Nb# 10 electrical and leak check at NHCNb#10 has been installed on TM2 . electrical
and leak check on HS line are good. See attachment.
 Nb_#10_electrical_and_leak_check_at_NHC.pdf 
  2134   Tuesday, August 18, 2020, 09:57 Adam NewsomeConditioning StationStandard OperationTM2 TM2 Moved to Conditioning StationTM2 was moved from ITW to the Conditioning
Station. 
  
  2517   Tuesday, January 09, 2024, 16:10 Adam NewsomeSouth Hot-CellStandard OperationTM2 TM2 Move - SHC to SiloTM2 was moved with no target attached from
the South Hot Cell to a silo. 
  
  2516   Monday, January 08, 2024, 14:47 Adam NewsomeSouth Hot-CellStandard OperationTM2 TM2 Move - ITW to SHCTM2 was moved from ITW to the South Hot
Cell with Ta#66 target. 
  
  1960   Tuesday, August 13, 2019, 09:49 Adam NewsomeSouth Hot-CellStandard OperationTM2Ta 58TM2 MoveTM2 was moved from ITE to South Hot Cell.
Tantalum 58 target. 
  
  1963   Thursday, August 15, 2019, 09:36 Adam NewsomeITEStandard OperationTM2ZrC #8TM2 MoveTM2 was moved from South Hot Cell to ITE.
ZrC #8 target. 
  
  2002   Monday, October 07, 2019, 09:56 Adam NewsomeITEStandard OperationTM2Ta 59TM2 MoveTM2 has been moved from the Conditioning
Station to ITE with Ta#59 target.
  
  2027   Tuesday, November 12, 2019, 10:02 Adam NewsomeITEStandard OperationTM2SiC#38TM2 MoveTM2 was moved from the Conditioning Station
to ITE, with SiC#38 target. 
  
  893   Tuesday, April 21, 2015, 13:01 Grant MinorITWDevelopmentTM2 TM2 MK4 Optics Tray - banana plug bore modification (on bench)The MK4 optics tray prepared for TM2 (as
per ITA6082) had an undersized bore for the
banana plug, making insertion of the plug
 ita6092_redlines_gminor_21apr2015.pdfTM2_Optics_Tray_Bore_Mod_21Apr2015_1.JPGTM2_Optics_Tray_Bore_Mod_21Apr2015_2.JPGTM2_Optics_Tray_Bore_Mod_21Apr2015_3.JPG 
  1379   Monday, October 24, 2016, 12:22 chad fisherSouth Hot-CellRepair  TM2 Insulator replacementconductor insulators itd0053 and 54 have
been replaced on TM2. All fasteners (1/4-20
x 1 1/4 vented) torqued to 60 in lbs.
  
  1619   Wednesday, September 20, 2017, 13:38 chad fisherSouth Hot-CellRepairTM2 TM2 Insulator replacementBroken insulators ITD0053 and ITD0054 have
been uninstalled from TM2.
 20170920_132813.jpg20170920_132820.jpg20170920_133244.jpg 