Some issues with the turntable and having to wait for a decision on whether to remove TM2 from the hot cell so that TM4 with dead UCx target could be put in this morning.
Progress on TM2:
- Containment box has been removed from TM2.
- Water block jig has been installed.
- Existing blank off has been removed.
- Sealing surfaces have been inspected.
- First stage of sealing surface cleaning has been performed.
Tomorrow:
- Polish of sealing surfaces.
- Installation of loop.
- Vacuum/helium leak check of loop.
TM2_20141201_03 - sealing surfaces before cleaning...kind of dirty
TM2_20141201_05AC - sealing surfaces after cleaning...looks good! |