1307
|
Friday, August 05, 2016, 14:13 |
Isaac Earle | North Hot-Cell | Development | | | Preparations for NHC Ventilation Test | A hole was drilled in the NHC exhaust duct
in the east end of the target hall above
the hatch to the Ante Room. This will |
|
1315
|
Wednesday, August 10, 2016, 14:38 |
Isaac Earle | North Hot-Cell | Development | | | North Hot Cell Ventilation Test Results | Testing was performed on August 9th on
the ISAC nuclear ventilation system to determine
if the existing ventilation system can achieve |
|
1345
|
Wednesday, September 07, 2016, 11:39 |
Isaac Earle | North Hot-Cell | Development | | | NHC North / South Wall Gap Measurements | Measurements were taken today of
the NHC north/south wall gap at the location
where the NHC/TCS partition wall will be |
|
1353
|
Thursday, September 15, 2016, 11:05 |
Isaac Earle | North Hot-Cell | Development | | | NHC / SHC feedthrough panel removed | The sheet metal panel covering the NHC/SHC
feedthrough port was removed today using
a slide-hammer to pull out the concrete anchors |
|
1395
|
Tuesday, November 08, 2016, 14:04 |
Isaac Earle | North Hot-Cell | Development | | | Interference check with TCS turbo pump and proposed NHC duct routing | David Wang and I accessed the NHC today
to check if the proposed duct routing (IRH1618)
will interfere with servicing or replacement |
|
1416
|
Friday, December 09, 2016, 14:58 |
Isaac Earle | North Hot-Cell | Development | | | NHC service area floor and top of roof block painted | The concrete floor in the North Hot
Cell service area and the top of the NHC
roof block in the target hall have been painted |
|
1421
|
Tuesday, January 17, 2017, 13:45 |
Isaac Earle | North Hot-Cell | Development | | | NHC ducting installed | The new ducting section connecting
the existing duct termination in the TCS
space to the NHC partition wall has been |
|
1423
|
Wednesday, January 18, 2017, 11:53 |
Isaac Earle | North Hot-Cell | Development | | | NHC partition wall installation complete | The final panels of the partition
wall were installed today as per drawing
IRH1609. Sealing, finishing, and painting |
|
1435
|
Tuesday, February 07, 2017, 15:57 |
Isaac Earle | North Hot-Cell | Development | | | Ventilation Ducting Gasket Installed | Lead gasket IRH1633 was installed
today according to assembly drawing IRH1618
Rev B. |
|
1437
|
Thursday, February 09, 2017, 14:07 |
Isaac Earle | North Hot-Cell | Development | | | North Hot Cell Shielding Window Gaskets Changed | The North Hot Cell shielding window
gaskets have been changed and the window
has been filled with new oil. Although |
23x |
1440
|
Friday, February 24, 2017, 15:12 |
Isaac Earle | North Hot-Cell | Development | | | NHC interior walls/floor/ceiling re-finished, sealed, and painted | The North Hot Cell interior walls, floor,
and ceiling were re-finished, sealed, and
painted by Omni Coating from Feb 6 - 17 under |
8x |
1442
|
Tuesday, February 28, 2017, 17:51 |
Isaac Earle | North Hot-Cell | Development | | | NHC flanged ducting connection sealed | The North Hot Cell ducting (IRH1617)
has been sealed with a bead of Sikaflex 1a
polyurethane construction sealant where the |
|
1443
|
Thursday, March 02, 2017, 15:02 |
Isaac Earle | North Hot-Cell | Development | | | NHC roughing filter installed | The roughing filter assembly (RFM0001D)
has been installed at the ventilation exhaust
hole on the NHC partition wall. The |
|
1511
|
Thursday, April 27, 2017, 16:58 |
Isaac Earle | North Hot-Cell | Development | | | Right side NHC manipulator installed | Installation of the NHC right side
manipulator was completed yesterday. The
three piece manipulator was assembled in |
|
1518
|
Tuesday, May 02, 2017, 09:48 |
Isaac Earle | North Hot-Cell | Development | | | NHC polycarbonate window cover panel installed | The window cover panel has been installed
on the hot side of the NHC shielding window
according to drawing IRH1638. It was |
|
1533
|
Thursday, May 11, 2017, 16:10 |
Isaac Earle | North Hot-Cell | Development | | | NHC roof block to TH north wall gap sealed | The gap between the north face of
the NHC roof block and the target hall north
wall in the area where the NHC inlet ducting |
|
1560
|
Thursday, June 15, 2017, 11:29 |
Isaac Earle | North Hot-Cell | Development | | | NHC inlet ducting installed | The North Hot Cell inlet ducting assembly
was installed today in the target hall at
the north end of the NHC roof block. A |
|
1564
|
Friday, June 23, 2017, 17:28 |
Isaac Earle | North Hot-Cell | Development | | | NHC module flange and cameras installed | The North Hot Cell module support
flange (IRH1152D) was installed on June 21,
2017 using 1/8" rubber sheet as a sealing |
|
1577
|
Wednesday, July 05, 2017, 15:36 |
Isaac Earle | North Hot-Cell | Development | | | NHC and SHC nuclear ventilation flow sensors installed | Installation of new flow sensors
and transmitters for the NHC and SHC duct
lines was completed in the target hall today. |
|
1578
|
Thursday, July 06, 2017, 14:23 |
Isaac Earle | North Hot-Cell | Repair | | | Slave side Z motion tape snapped on NHC right side manipulator | The NHC right side manipulator was evaluated
today to check if operation was normal through
all ranges of motion. The manipulator |
|