Entry  Thursday, December 12, 2019, 14:39, Isaac Earle, Safe Module Parking, Development, , , SMP assembly shifted 1.0" north 
The SMP assembly was shifted approximately 1.0" north today by pushing it, braced against the south wall, using a 100 Ton capacity air lifting bag
supplied by Beamlines Group.  The move was one of the action items identified at the Gate 4A/4B close-out review.  During commissioning of the
SMP, TM3 was installed into the vacuum vessel, which required the crane to be all the way at its south limit, so the move is to provide some margin for
Entry  Tuesday, December 03, 2019, 12:45, Adam Newsome, Spent Target Vault, Standard Operation, , SiC#38, SiC#38 in Pail 205 moved to Storage Vault: 4B Target_Index_2019-12-03.pdf
SiC#38 in Pail 205 was moved to section 4B of the storage vault. Dose rate when retrieving from Hot Cell was 22.2 mSv/h. 
Entry  Friday, November 29, 2019, 13:10, David Wang, ITE, Standard Operation, TM2, SiC 39# febiad, TM2 SiC#39 connection check list. SiC_#_39_febiad_connection_checklist.pdf
TM2 has been connected  in ITE.  All turbo-pumps are started.
Entry  Friday, November 29, 2019, 11:03, Travis Cave, South Hot-Cell, Standard Operation, TM2, SiC#39, Module move 
 TM#2 with the SiC#39 target has been moved from the south hot cell to the east target station.
Entry  Friday, November 29, 2019, 11:02, Travis Cave, South Hot-Cell, Standard Operation, TM2, SiC#38 SiC#39, Electrical Check Elec_chk_SiC#38_SHC_post_beam_TM2_11-26-2019.pdfElec_chk_SiC#39_SHC_TM2_11-29-2019.pdf
 Results from the electrical check with the old SiC#38 target and the new SiC#39.
Entry  Wednesday, November 27, 2019, 13:46, David Wang, Conditioning Station, Standard Operation, TM2, SiC 38# febiad, TM2 SiC #38 disconnection checklist. SiC_#_38_febiad_disconnection_checklist.pdf
TM2 was disconnected in ITE yesterday.
Entry  Tuesday, November 26, 2019, 10:24, Travis Cave, South Hot-Cell, Standard Operation, TM2, SiC#38, Module move 
 TM#2 with SiC#38 has been moved from ITE to the south hot cell.
Entry  Tuesday, November 19, 2019, 13:41, David Wang, ITE, Standard Operation, TM2, SiC 38# febiad, TM2 SiC#38 connection check list. SiC_#_38_febiad_connection_checklist.pdf
TM2 was connected in ITE 12th Nov. attach checklist
Entry  Thursday, November 14, 2019, 13:52, Travis Cave, Spent Target Vault, Standard Operation, , UC#22,23,24, Targets repackaged Target_Index_2019-11-14_Mini_Vault.pdf
 The targets UC#22,23,24 have been repackaged into the newer stronger pails, and have been placed back in the mini vault with new numbers. See attached
PDF for details.
Entry  Tuesday, November 12, 2019, 10:07, Travis Cave, Spent Target Vault, Standard Operation, , Ta#59, Spent Target Move Target_Index_2019-11-08.pdf
 The spent Ta#59 was moved from the south hot cell to the spent target vault. See the attached for details.
Entry  Tuesday, November 12, 2019, 10:02, Adam Newsome, ITE, Standard Operation, TM2, SiC#38, TM2 Move 
TM2 was moved from the Conditioning Station to ITE, with SiC#38 target. 
Entry  Thursday, November 07, 2019, 08:56, David Wang, Conditioning Station, Standard Operation, TM2, SiC#38, TM2 in TCS. 
Helium pressure leak check on TM2 HS line at TCS is done. No leak. Also, Helium are sprayed to gas line adapter and fittings. No leak. TM2 is connected
at TCS. Anode plug on TCS is connected to module 52pin connector. Water system is started. Vacuum pumping down is good. HV cover will be installed today.
    Reply  Thursday, November 07, 2019, 10:39, Anders Mjos, Conditioning Station, Standard Operation, TM2, SiC#38, Conditioing SiC#38 SiC#38_ANODE_bias_2019-11-07.PNG
Thursday, November 07, 2019, 10:35: Tested source to 30 A on TGHT, TBHT and COIL. ANODE at 100 V.

Tuesday, November 12, 2019 
The FEBIAD source worked well over the weekend. The anode current limit was adjusted twice to stop voltage limiting. About 5E-8 A on the FC with
Entry  Tuesday, November 05, 2019, 14:27, Travis Cave, South Hot-Cell, Standard Operation, TM2, Ta#59, Electrical Check Elec_Chk_TM2_with_Ta59_post_beam_SHC_Nov_05_2019.pdfElec_Chk_TM2_SHC_no_target_Nov_5_2019.pdf
 Results of the electrical check of TM#2 with the old Ta#59 target and target free.
Entry  Tuesday, November 05, 2019, 12:46, chad fisher, South Hot-Cell, Standard Operation, TM2, ta#59, Ta#59 removed 
Ta#59 has been removed from TM2 and it is now ready for electrical check.
Entry  Tuesday, November 05, 2019, 11:57, David Wang, ITE, Standard Operation, TM2, Ta 59, Ta#59 disconnection checklist Ta#59_disconnection_checklist.pdf
See attachment
Entry  Tuesday, November 05, 2019, 10:19, Travis Cave, South Hot-Cell, Standard Operation, TM2, Ta#59, Module move 
 TM#2 with Ta#59 has been moved from the ITE to the south hot cell.
Entry  Thursday, October 31, 2019, 10:17, David Wang, Assembly/Bench Test, Maintenance, TM2, , Febiad target gas line leak check. 
Feibiad gas line for ITE and its adapter fittings for TM2 are tested today by installing them on a dummy water stem. No leak on VCO fitting, adapter
o-rings, and all Swagelock fittings of this assembly. Manual valve on gas line works fine.  The positional check on gas line between TM2 and ITW will
be fulfilled next Tuesday during module disconnection.  
Entry  Thursday, October 31, 2019, 08:49, Anders Mjos, Conditioning Station, Repair, , , Water leak on non-active cooling water circuit 
Yesterday a leak was discovered in the ISAC-I experimental hall. The leak appears to be at the connection between the evaporator and the return water
line. 1 in of water was lost from TCS:TK1. The water is currently valved off to prevent further leakage.
A fault reportt has been submitted to mechanical
Entry  Wednesday, October 30, 2019, 11:18, David Wang, ITW, Standard Operation, TM4, UCx 29, UCx 29 connection checklist UCx_29_connection_checklist.pdf
See attachment
Entry  Tuesday, October 29, 2019, 10:00, Adam Newsome, Safe Module Parking, Development, , , SMP Updates to E-stop circuit and feedback signals 
The SMP main control panel and remote control module were updated in  order to implement the following items which were deemed desirable  during commissioning:
 

        24 VDC line added to E-stop circuit: