2535
|
Friday, January 26, 2024, 11:57 |
David Wang | Safe Module Parking | Standard Operation | TM4 | | TM4 coil1, 2, and HS electrical check at SMP after module moving. | TM4 coil1, 2 and HS are all OL at 250V
at SMP after module move. This week, Chad
and Carl fixed short issue on coil1, 2 and |
|
454
|
Friday, September 13, 2013, 08:05 |
David Wang | South Hot-Cell | Repair | TM4 | | TM4 coil 1 leak check in SHC | Leak checked TM4 coil1 in SHC with Isaac
. The leak detector only can pump down to
1.5xE-7 atm.cc/sec. The leak detector got |
|
731
|
Monday, August 11, 2014, 14:27 |
David Wang | Conditioning Station | Standard Operation | TM4 | | TM4 are vented with argon and disconnected at CS. | TM4 are vented with argon and disconnected
at CS this morning. |
|
1452
|
Thursday, March 16, 2017, 10:32 |
David Wang | Spent Target Vault | Repair | TM4 | | TM4 and its silo rust photos | I watched rust on TM4 and its silo. Most
of rust are on est side of module and silo.
See attachments |
13x |
2633
|
Friday, July 05, 2024, 12:50 |
David Wang | South Hot-Cell | Standard Operation | TM4 | TiC#7 | TM4 and TiC#7 target electrical check and HS leak check at SHC after target installation . | TM4 and TiC#7 target electrical check and
HS leak check at SHC after target installation
have been done. all results are good. |
|
1258
|
Tuesday, June 07, 2016, 18:17 |
David Wang | Conditioning Station | Standard Operation | TM4 | UC#16 | TM4 and TCS turbo pumps are started. | TM4 and TCS vacuum system are connected.
Turbo pumps are started. Everything
is fine so far. |
|
621
|
Thursday, March 13, 2014, 07:35 |
David Wang | ITW | Standard Operation | TM4 | | TM4 and ITW turbo pumps have been started | I connected ITW vacuum system to
TM4. TM4 and ITW turbo pumps have been started
successfully. The pumping down is good so |
|
625
|
Wednesday, March 19, 2014, 15:46 |
David Wang | ITW | Standard Operation | TM4 | | TM4 and ITE air to vacuum leak check and TM4 water lines helium test. | With TM4 located in ITW, All air to vacuum
seals on ITW primary and secondary
vacuum vessels have been leak checked |
7x |
929
|
Tuesday, June 02, 2015, 14:39 |
David Wang | Conditioning Station | Standard Operation | TM4 | SiC #31 | TM4 and CS turbo- pumps are started . | TM4 and CS turbo-pumps are started this
afternoon. Everything is good so far. |
|
143
|
Friday, July 06, 2012, 14:38 |
David Wang | Conditioning Station | Standard Operation | TM4 | UO#3 | TM4 UO#3 target heat shield helium pressure check is done. | Connected leak detector to TM4 and CS vacuum
system. The vacuum readings on TM4 and CS:PNG4
3.6 xE-6 Torr, IG1 2.3xE-6torr, IG4(diagnostic |
|
1256
|
Tuesday, June 07, 2016, 17:11 |
David Wang | Conditioning Station | Standard Operation | TM4 | UC#16 | TM4 UCx16 electrical check and leak check at SHC | Chad and I finished the TM4 UCx6 electrical
check and leak check at SHC. Leak check result
on HS line is good. There is a dead short |
 |
2118
|
Friday, July 03, 2020, 13:23 |
David Wang | South Hot-Cell | Standard Operation | TM4 | UCx#30 | TM4 UCx#30 Electrical check and HS leak check | Electrical and leak check are good. See
attachment. |
|
2057
|
Monday, February 03, 2020, 09:14 |
David Wang | ITW | Standard Operation | TM4 | UCx 29 | TM4 UCx 29 disconnection checklist | TM4 has been disconnected in ITW. See attachment
checklist. |
|
2011
|
Wednesday, October 23, 2019, 06:56 |
David Wang | ITW | Standard Operation | TM4 | UCX 28 | TM4 UCx 28 disconnection checklist | TM4 was disconnected in ITW. See
checklist. |
|
2151
|
Tuesday, September 29, 2020, 14:28 |
David Wang | South Hot-Cell | Standard Operation | TM4 | UC#31 | TM4 UC#31 Electrical check and HS leak check | Tm4 UCx 31# electrical check result. See
attachment. |
 |
1737
|
Thursday, June 14, 2018, 11:37 |
David Wang | ITE | Standard Operation | TM4 | UC#22 | TM4 UC 22# checklist. | See attachments |
|
8
|
Tuesday, July 19, 2011, 12:25 |
maicodallavalle | South Hot-Cell | Standard Operation | TM4 | Ta36 | TM4 Ta36 Target was put into the south hot cell. | Ta36 was check by Maico and Chad.It was
then carried into the anteroom.From the anteroom
it was transferred into the south hot cell. |
|
2233
|
Thursday, July 08, 2021, 11:45 |
David Wang | South Hot-Cell | Standard Operation | TM4 | Ta#62 | TM4 Ta#62 leak check and lectrical check result at SHC and TCS. | At SHC: HS line no leak . electrical check
result is fine. At TCS: helium pressurized
HS line to 70psi, 3 minutes. LD leak |
|
9
|
Tuesday, July 19, 2011, 13:51 |
chad fisher | South Hot-Cell | Standard Operation | TM4 | Ta#36 | TM4 Ta#36 Leak Check Results | Tm4 w/ Ta#36 has been vacuum leak checked
using the standard leak check procedure.
At 1:45pm RH was contacted to notify |
|
1778
|
Friday, September 07, 2018, 10:47 |
David Wang | ITE | Repair | TM4 | UCx24 | TM4 TP2 replacement | TM4 TP2 could not be started after
module was connected back to ITE on Sep 04th.
It was replaced with a new pump on Sep 05th. |
|