  1515   Monday, May 01, 2017, 08:53 chad fisherSouth Hot-CellRepairTM3 Fiberglass removal

Fiberglass, capton tape and tie straps have been removed from TM3.

  1517   Monday, May 01, 2017, 13:11 David WangSouth Hot-CellRepairTM3 Electrical Check on TM3 after fibergalss is moved in SHC.

RU( coil 1), F (anode), and 60kv bias(HS, Gasline, and MSP)  are shorted together. Other lines are good.  They are measured between  individual line each other  @500V. The megga showed OL. All of  them to ground are OL @500V as well. EL is grounded during check.

  1520   Tuesday, May 02, 2017, 18:33 Aurelia LaxdalSouth Hot-CellRepairTM3no targetTM3 HV tests at atmosphere for Each Line(s) after the Fiber Glass removal May 2, 2017

Today a HV test at atmosphere was performed for Each Line(s), while floating the other lines. THIS TEST AT ATMOSPHERE IS THE FIRST ONE AFTER THE FIBER GLASS WAS REMOVED.

Please note:

a). the Einzel Lens line (Y) was grounded.

b). after the fiber glass was removed the "R-U COIL" line and the "(F) Plasma" (which is the Anode line) were shorted to the BIAS voltage.

Tests performed:

1. Applied up to 32kV to "(A) OVEN -"

Sparks occurred at 32kV between the Extraction Electrode holder and the Ground Electrode.

2. Applied up to 33kV to "(B) OVEN +"

Sparks occurred at 33kV but we could not identify the spark location.

3. Applied up to 31kV to "(C) TUBE -"

Sparks occurred at 31kV between the Extraction Electrode holder and the Ground Electrode, at the top and the bottom.

4. Applied up to 30kV to "(D) TUBE +"

Sparks occurred at 30kV between the Extraction Electrode holder and the Ground Electrode, 2 spots at the bottom.

5. Applied up to 30kV to "(P-Q) COIL +"

Sparks occurred at 30kV between the Extraction Electrode holder and the Ground Electrode, all around.

6. Applied up to 30kV to "(R-U) COIL -", to "(F) Plasma" the Anode, to "(E) Cavity" or MSP, "(G) Gas", and  "(J) Heat Shield" - all these are "connected" together at the BIAS voltage.

Sparks occurred around 29-30kV at the Extraction Electrode holder and the Ground Electrode, at the bottom.

8. Applied up to 23kV to "(I) EE" - this is for the Extraction Electrode.

Sparks occurred at 23kV again at the same spot near the bottom, between the Extraction Electrode holder and the Ground Electrode.

 

  1532   Wednesday, May 10, 2017, 14:00 Anders MjosSouth Hot-CellDevelopment ITE-Ta-LP-FEBIADTest target examination

Chad and Anders inspected the test target in the hot cell today. The lid had been previously removed.

  • The EE looked to have performed well. 
  • A piece of Ta foil was found inside the heat shield. It is not clear if this has been there during operation or if it entered the heat shield while in the hot cell. The foil has markings which indicate that it has seen heat.
  • Travis measured 40 MOhm at 500V between heat shield and anode after the target was removed.

Photos are available on DocuShare

  1535   Tuesday, May 16, 2017, 10:28 Travis CaveSouth Hot-CellStandard OperationTM4UC#19module moved

TM#4 with UC#19 has been moved from ITE to the south hot cell.

  1536   Tuesday, May 16, 2017, 13:23 chad fisherSouth Hot-CellStandard OperationTM4UC#20UC#20 Installed

UCx#19 has been removed from TM4 and UCx#20 installed.

UCx#19 still had water in it at pressure and sprayed when the VCR was undone. It was quickly re-tightened but not before significant water pooled beside the main Mykroy standoff and table. Contacted Anders would suggested to soak it up with some wipes and continue, which I did.

New target fasteners including high current. High current fasteners torqued to 130 in lbs.

  1537   Tuesday, May 16, 2017, 14:18 Travis CaveSouth Hot-CellStandard OperationTM4UC#20Electrical Check

TM#4 with UC#20 has had the electrical check done on it  at the south hot cell, see attached for details

Attachment 1: TM4_UC20_Elec_chk_SHC.PDF
TM4_UC20_Elec_chk_SHC.PDF TM4_UC20_Elec_chk_SHC.PDF
  1539   Wednesday, May 17, 2017, 08:31 David WangSouth Hot-CellStandard OperationTM4 Leak check on TM4 HS line at SHC

Chad and I finished leak check on HS line with UCx target installed on it.  Base Leak rate:0.0X 10^-9 atm.cc/sec, Base pressure 0.0X 10 ^-4 torr.  Sprayed helium to VCR joints.   No leak has been found . The line will be pressurized with helium at TCS.

 Helium pressure test on TM4 HS line is done at TCS. BLR 0.0XE-9 atm.cc/sec. 70psi helium , 2 minutes. No response. The line is leak free.

  1550   Tuesday, June 06, 2017, 13:42 chad fisherSouth Hot-CellStandard OperationTM2SiC#36Ta#51 removed SiC#36 installed

This afternoon Ta#51 was removed from TM2 and SiC#36 installed.

All new fasteners used. High current fasteners torqued to 130 in lbs.

 

 

  1562   Thursday, June 22, 2017, 11:10 chad fisherSouth Hot-CellMaintenance  In cell airline

The in cell airline has preemptively been replaced. The hose was, as far as I know the original.

  1565   Monday, June 26, 2017, 11:42 Travis CaveSouth Hot-CellStandard OperationTM4UC#20Module move

 TM#4 with UC#20 has been moved from the east target station to the south hot cell. Also the shield plug was remotely installed as well after David set it up.

  1566   Monday, June 26, 2017, 11:47 chad fisherSouth Hot-CellStandard OperationTM4Ta#52UC#20 Removed Ta#52 installed

UC#20 has been removed from TM4 and put in a bucket back-filled with argon. Ta#52 has been installed onto TM4 with new fasteners. High current torqued to 130 in lbs.

  1568   Tuesday, June 27, 2017, 10:26 David WangSouth Hot-CellStandard OperationTM4Ta#52Leak check on TM4 HS line at SHC

LD base LR:0.0Xe-9 atm.cc/sec. No leak has been found during the check.  The HS line will be helium pressurized at TCS this week.

Helium pressurized the HS line at TCS. 70 psi 2 minutes, 0.0 x E-9 atm.cc/sec. No leak.

  1573   Thursday, June 29, 2017, 11:12 Anders MjosSouth Hot-CellStandard OperationTM4UC#20Post Irradiation Examination (PIE)

The target was inspected by Chad and Anders. Photos are available on DocuShare. It was noticed that the target tube heater terminals had lifted up from the insulator on the target assembly as seen in this Photo. This has later been detemined to be from the assembly, where additional clearance was required and achieved by installing washers.

  1589   Tuesday, August 01, 2017, 14:39 Travis CaveSouth Hot-CellStandard OperationTM2SiC#36Electrical Check

The electrical check of TM#2 with SiC#36 attached. Post beam at the south hot cell. See attached results allow the before beam electrical check results are posted here as well.

Attachment 1: TM2_SiC36_SHC_elec_chk.PDF
TM2_SiC36_SHC_elec_chk.PDF
Attachment 2: TM2_SiC36_Postbeam_SHC_elec_chk.PDF
TM2_SiC36_Postbeam_SHC_elec_chk.PDF
  1591   Wednesday, August 02, 2017, 15:13 David WangSouth Hot-CellStandard OperationTM2 SHC, TM2 leak check on HS line.

HS line is leak checked at SHC this afternoon by helium spay.  Leak detector base LR 0.0 XE-9atm.cc/sec. Base pressure 0.0Xe-4 torr. No leak has been found. This line will be helium pressured  at TCS. It had  a 1.7XE-7 atm.cc/sec leak rate on 70 psi helium at TCS  during last two target  checks.

 2017-08-03. Helium pressure test on TM2 HS line at TCS is done. 70psi helium, 3 minutes. base leak rate 0.0xE-7 atm.cc/sec. Result: 1.8XE-7atm.cc/sec leak which is almost same as before. This line has a very small leak on water block seal under helium pressure test  which we knew already. 

  1597   Tuesday, August 15, 2017, 09:27 Anders MjosSouth Hot-CellStandard OperationTM2SiC#36Electrical Check of target in SHC

Travis Cave wrote:

The electrical check of TM#2 with SiC#36 attached. Post beam at the south hot cell. See attached results allow the before beam electrical check results are posted here as well.

by David and Chad after target removed from module:

Anode to target @500V - 65Kohm
Anode to HS - dead short
Target to HS@500V -62Kohm.

  1603   Monday, August 28, 2017, 12:07 chad fisherSouth Hot-CellStandard OperationTM4UCx#21Ta#52 removed UCx#21 installed

Ta#52 has been removed from TM$ and UCx#21 installed with new mounting and high current hardware. High current fasteners torqued to 130 in lbs.

  1605   Monday, August 28, 2017, 14:40 Travis CaveSouth Hot-CellStandard OperationTM4UC#21Electrical Check

The results of the electrical check of TM#4 with UC#21 attached.

Attachment 1: TM4_UC21_elecchk_SHC.PDF
TM4_UC21_elecchk_SHC.PDF
  1617   Tuesday, September 19, 2017, 10:40 chad fisherSouth Hot-CellMaintenance  South East Manipulator Maintenence

Entered hot cell to preform replacement of slave tong cable. Existing cable shows no signs of wear so it has been re-installed. A spare tong cable has been loaded into a spare tong while in the hot cell in preparation for next time this cable needs to be replaced.