  RH-ISAC, Page 33 of 141  Not logged in ELOG logo
  ID Date Author Category Type Module Target/Numberdown Subject
  2642   Tuesday, July 16, 2024, 13:14 Frank SongITWStandard OperationTM4TiC#7Module Connection

 TM4 with TiC#7 was connected in ITW, all TPs are running at full speed.

Attachment 1: TM4_with_new_target_TiC#7_connection_in_ITW_2024-07-16.pdf
TM4_with_new_target_TiC#7_connection_in_ITW_2024-07-16.pdf TM4_with_new_target_TiC#7_connection_in_ITW_2024-07-16.pdf TM4_with_new_target_TiC#7_connection_in_ITW_2024-07-16.pdf TM4_with_new_target_TiC#7_connection_in_ITW_2024-07-16.pdf
Attachment 2: MicrosoftTeams-image_(65).png
MicrosoftTeams-image_(65).png
  2649   Friday, August 09, 2024, 08:11 Frank SongITWStandard OperationTM4TiC#7module disconnection

 TM4 with spent target TiC#7 (dead) was disconnected in ITW and ready to move to TCS.

Attachment 1: TM4_with_spent_TiC#7_disconnection_in_ITW_20240809.pdf
TM4_with_spent_TiC#7_disconnection_in_ITW_20240809.pdf TM4_with_spent_TiC#7_disconnection_in_ITW_20240809.pdf TM4_with_spent_TiC#7_disconnection_in_ITW_20240809.pdf
  2651   Friday, August 09, 2024, 18:18 David WangITWStandard OperationTM4TiC#7Tm4 has been moved from ITW to SMP.

Tm4 has been moved from ITW to SMP. the move is successful.

  2667   Tuesday, August 20, 2024, 11:36 Carla BabcockSouth Hot-CellStandard Operation TiC#7TiC#7 PIE

TiC#7 failed after two weeks of operations - measurements in the electrical room indicated that the negative side of the CHT was broken (35kOhms to the rest of the target). This was likely due to a large number of proton trips during this target run. At every trip I could see the CHT voltage getting higher and more unstable. This cahnge in voltage was reflected in the unstable anode current and fluctuating RIB beam intensity, as a direct result of the fluctuating power on the CHT. The break was confirmed in PIE, loosening the screws caused the target container to come off without the cathode. Otherwise nothing unusual was seen. The anode wire connections seem very robust, dragging the target around with the multipin disconnected, flipping it up and down, etc and the anode wire stayed attached. Though we saw lots of outgassing on this target, things looked the normal level of dirty. There was no buildup between PE and EE.

  2669   Wednesday, August 21, 2024, 10:53 Travis CaveSpent Target VaultStandard Operation TiC#7Spent Target Move

 TIC#7 was placed in pail #294 and then moved from the south hot cell to the spent target vault spot 4B. It was 82.3mSv/hr when removed from the SHC. See attached PDF for details.

Attachment 1: Target_Index_2024-08-21.pdf
Target_Index_2024-08-21.pdf
  2442   Friday, May 19, 2023, 09:39 Frank SongSouth Hot-CellStandard OperationTM2TiC#6leak/electrical check

 TM2 with TiC#6 was checked on SHC, see pic attached pls.

Attachment 1: TM2_with_TiC#6_leak_and_eletrical_check.png
TM2_with_TiC#6_leak_and_eletrical_check.png
  2444   Wednesday, May 24, 2023, 08:34 David WangConditioning StationStandard OperationTM2TiC#6TM2 HS line helium pressure check and gasline fittins leak check.

TM2 HS line helium leak check is done. leak detector base LR 1.8xE-8atm.cc/sec.  helium pressure 70 psi. 5 minutes test. no change on LD leak rate.    I spray lots helium to gas line adaptor and fittings. No leak.has been found  at this base leak rate level.  Since the TCS MP1 has some  issue ,this time the base leak rate on LD only can get to 1.8Xe-8 atm.cc/sec at this moment instead of 0.0xE-9.  The low E-8  level is not perfect, but  i  have no concern on it.

  2447   Monday, May 29, 2023, 12:52 Frank SongITWStandard OperationTM2TiC#6Module Connection

 TM2 with TiC#6 was connected in ITW (FEBIAD), turbo pumps were started successfully.

Attachment 1: TM2_with_TiC#6_connected_in_ITW_(FEBIAD)_20230529.pdf
TM2_with_TiC#6_connected_in_ITW_(FEBIAD)_20230529.pdf TM2_with_TiC#6_connected_in_ITW_(FEBIAD)_20230529.pdf TM2_with_TiC#6_connected_in_ITW_(FEBIAD)_20230529.pdf TM2_with_TiC#6_connected_in_ITW_(FEBIAD)_20230529.pdf
  2449   Tuesday, May 30, 2023, 12:30 Frank SongITWStandard OperationTM2TiC#6gas lines pump out in ITW Faraday Cage

 Gas lines pumped down at electric room for TM2 at ITW is done, leak rate 0.0e -8 <1.0e -3 T P pressure

Attachment 1: gas_lines_pumped_out_to_ITW.JPG
gas_lines_pumped_out_to_ITW.JPG
  2453   Tuesday, June 06, 2023, 17:36 Carla BabcockITWStandard OperationTM2TiC#6Module conditioning

Conditioned TM2 up to 48kV in ITW. Some sparks and current is not very stable. Drawing about 178uA at 48kV.

  2473   Tuesday, August 08, 2023, 13:01 David WangNorth Hot-CellStandard OperationTM2TiC#6TM2 TiC#6 post run electrical check at NHC.

TM2 TiC#6 post run electrical check has been done at TCS. See attachment

Attachment 1: TiC#6_post_run_electrical_check.pdf
TiC#6_post_run_electrical_check.pdf TiC#6_post_run_electrical_check.pdf
  2476   Wednesday, August 09, 2023, 13:43 Carla BabcockNorth Hot-CellStandard OperationTM2TiC#6TiC#6 PIE

PIE on TiC#6 was done in the NHC. The target assembly looked brand new when we took it out, no heating spots or deposits (pictures on docushare). Online we measured a 400kOhm connection between TGHT-TBHT-COIL to HV common (TGHT and COIL shorted in TM2 service tray) and anode was unstable above ~300V. After the module move and before the target removal David found TGHT-TBHT-COIL was a dead short to HV common and the anode was at 39kOhms to HV common.

1. Wanted to see if the TGHT-TBHT-COIL short was on the COIL. Measured with ohmmeter the COIL lines to HS and got about 700Ohms. But with the target lying down the COIL lines drop and touch the heat shield so to do this measurement Chad had to lift the lines, which could cause them to touch something else. So not sure how reliable this measurement was. It jumped around a lot, saw 0L occasionally.

2. Measured both target legs and tantalum gas line to HS, got about 5kOhms repeatedly using the ohmmeter.

3. Meggered across the gas line insulator to the gas line going into the target and got open circuit at 250V, so the gas line wasn't coated.

4. Target container looked vaguely red in the areas where the target material was, otherwise still no deposits on the inside. The container was not overly crystalized as seen on the legs and end caps.

5. Some sparking marks on the EE and some slightly asymmetric deposits

Continuing Aug. 22 2023:

6. Found what looks like a hole in the insulation on the COIL, maybe the cause of our short? Found a corresponding line mark on the copper plates that hold the coil down but not sure if it is related. Pics on docushare.

7. Grid looks perfectly new. Where was that current going?

8. Copper plates that hold coil were loose and bolts that hold coil in just fell out as well.

9. What can be seen of the anode wire looks good.

  2478   Wednesday, August 23, 2023, 10:45 Travis CaveSpent Target VaultStandard Operation TiC#6Spent Target Move

 TiC #6 moved from north hot cell to spent target vault placed in pail #232 put in spot 6A and the field was 151mSv/hr when removed from the north hot cell. See attached PDF for details about spent target vault.

Attachment 1: Target_Index_2023-08-23.pdf
Target_Index_2023-08-23.pdf
  2439   Monday, May 08, 2023, 10:59 Frank SongNorth Hot-CellStandard OperationTM4TiC#5electrical check/leak check

 TM4 with target TiC#5 installed has been leak checked and electric checked on NHC.

Attachment 1: TM4_with_TiC#5_20230508.png
TM4_with_TiC#5_20230508.png
  2440   Wednesday, May 10, 2023, 08:40 Frank SongITEStandard OperationTM4TiC#5Module Connection

 TM4 was connected in ITE.  pics attached FYI.

Attachment 1: TM4_with_TiC5_connection_in_ITE_20230509.png
TM4_with_TiC5_connection_in_ITE_20230509.png
Attachment 2: TM4_with_TiC5_all_set_in_ITE_20230510_758AM.JPG
TM4_with_TiC5_all_set_in_ITE_20230510_758AM.JPG
  2443   Monday, May 22, 2023, 15:06 Carla BabcockITEStandard OperationTM4TiC#5Module conditioning

Yesterday and today module conditioning was done on Tm4 in ITE. This is the first ramp up after the shutdown and ITE is planned to run at high voltages for the first weeks. The module is behaving well - went up to 40kV yesterday, stayed there for an hour, and up to 46kV today. Current draw is 113uA at 46kV. No serious sparking.

 

Tuesday, May 23, 2023, 09:32 :  Ramping up again, easy to 45kV. Drawing 132uA at 49kV. Still behaving quite well.

  2445   Wednesday, May 24, 2023, 17:25 Carla BabcockITERepairTM4TiC#5Issues with anode short

When I tried to raise the anode voltage in cathode bias mode on May 23 evening, I found the target or tube shorted to HV common. Investigations in the faraday cage today showed the same. I removed all the new electronics (resistors, gemovs, etc) from the power supply to no effect, so I disconnected the TGHT supply and pushed it away from the busbars. There was still a short. David Frank and I then went down to the pit and disconnected everything to measure the module. The module itself showed no short, and the bus bars in the chase for TGHT showed no short, though the ones for TBHT still showed the short.

David and Frank reconnected the module and I disconnected the TBHT supply in the faraday cage, then I found no shorts to TGHT/TBHT. When I reconnected everything there were still no shorts. There must have been a short in the TBHT line in the faraday cage, and another short in the TGHT line in either the faraday cage or on the module top. Both these shorts got resolved by taking everything apart. Still not sure how it happened.

Next I found I could not raise the anode voltage above 230V, it looked like it was current limiting but since the current limit was high, I figured it had something to do with the new electronics installed. I disconnected them all the in cage and that solved the problem, and then reconnecting the gemovs that go from the PSU terminals to HV common caused the problem again, so I left those disconnected.

  2448   Tuesday, May 30, 2023, 12:23 Frank SongITEStandard OperationTM4TiC#5gas lines pump out in ITE Faraday Cage

argon is being supplied at 6 psi to TM4. 

Attachment 1: Argon_supplied_at_6psi_to_TM4_in_ITE.JPG
Argon_supplied_at_6psi_to_TM4_in_ITE.JPG
  2455   Tuesday, June 13, 2023, 09:55 Frank SongITEStandard OperationTM4TiC#5module disconnection

 TM4 with TiC#5 was disconnected in ITE and moved to NHC.

Attachment 1: TM4_with_TiC#5_(FEBIAD)disconnected_in_ITE_20230613.pdf
TM4_with_TiC#5_(FEBIAD)disconnected_in_ITE_20230613.pdf TM4_with_TiC#5_(FEBIAD)disconnected_in_ITE_20230613.pdf TM4_with_TiC#5_(FEBIAD)disconnected_in_ITE_20230613.pdf
  2456   Tuesday, June 13, 2023, 11:45 Frank SongNorth Hot-CellStandard OperationTM4TiC#5electrical check

 TM4 with spent target TiC#5 electric check after moving from ITE to NHC.

Attachment 1: TM4_with_spent_target_electric_check_right_after_moving_to_NHC.png
TM4_with_spent_target_electric_check_right_after_moving_to_NHC.png