Subject: TiC#7 PIE 

TiC#7 failed after two weeks of operations - measurements in the electrical room indicated that the negative side of the CHT was broken (35kOhms to the rest of the target). This was likely due to a large number of proton trips during this target run. At every trip I could see the CHT voltage getting higher and more unstable. This cahnge in voltage was reflected in the unstable anode current and fluctuating RIB beam intensity, as a direct result of the fluctuating power on the CHT. The break was confirmed in PIE, loosening the screws caused the target container to come off without the cathode. Otherwise nothing unusual was seen. The anode wire connections seem very robust, dragging the target around with the multipin disconnected, flipping it up and down, etc and the anode wire stayed attached. Though we saw lots of outgassing on this target, things looked the normal level of dirty. There was no buildup between PE and EE.

ELOG V2.9.2-2455