  2730   Wednesday, December 04, 2024, 09:00 David WangFacilitiesStandard OperationTM2 all water lines on TM2 have been purged.all water lines on TM2 have been purged.
Refilled them(except HS ) with 60psi nitrogen
for module silo storage before next year
  
  2731   Wednesday, December 04, 2024, 10:40 Adam NewsomeSouth Hot-CellStandard OperationTM2 TM2 move - SHC to siloTM2 was remotely moved from the South Hot
Cell to SW Silo. Reading at SHC = 89.8 mSv/h.
The move was smooth. 
  
  2736   Wednesday, December 18, 2024, 12:18 Adam NewsomeSpent Target VaultStandard Operation  Five Pails Transferred from Main Vault to Mini VaultFive pails were transferred from main vault
to mini vault. Note that there was already
one pail in the mini vault, so at present
 MiniVault_2024-12-18.pdf 
  2737   Wednesday, December 18, 2024, 14:17 Adam NewsomePail Handling ToolMaintenance  Pail Handling Tool - InspectionAn informal inspection of the main Pail
Handling Tool was performed today as the
final one for the year. Note that the main
 ISAC_Pail_Handling_Tool_Inspection_Record_-_2024.pdf 
  2738   Friday, January 03, 2025, 09:59 Adam NewsomeFacilitiesStandard Operation  Safety Walkaround complete - ISAC Hot Cells, Target HallA safety walkaround was completed for the
ISAC Hot Cells and Target Hall Areas.
The resulting spreadsheet can be
  
  2744   Thursday, January 09, 2025, 11:08 David WangFacilitiesMaintenance  ITH:MP1 is deteriorating by watching on ITH:CG1 and CG2 readingsITH:MP1 is deteriorating by watching on
ITH:CG1 and CG2 readings and investigation
in pit. A fault 17644 has been issued. this
  
  2751   Monday, January 20, 2025, 11:33 Adam NewsomeWaste Package/ShipStandard Operation   F-308 flask loading - six flasks loaded Today (2025-01-20), six flasks were loaded
in preparation for   shipment with the following
targets: C#4, TiC#5, Ta#64,Ta#62, Nb#10,
 Target_Index_2025-01-20.xlsm 
  2752   Tuesday, January 21, 2025, 10:46 David WangITE/ITWStandard Operation  ITW/ITE pit general annual cleaning up.ITW/ITE pit general annual cleaning up
were done. all concrete floor and TM equipment
surface are vacuum  cleaned. HV cage
  
  2753   Wednesday, January 22, 2025, 10:29 Frank SongFaraday CageMaintenance  Annual clean up for ITE/ITW Faraday cages  David and I cleaned both cages in
ISAC1 electric room, all done.
  