Entry  Monday, September 23, 2024, 11:26, David Wang, South Hot-Cell, Standard Operation, TM3, , TM3 window line has been leak checked.  

TM3 window line has been leak checked after containment box removal and installation for insulator installation on water cup C.   No leak.

Entry  Monday, September 23, 2024, 11:31, David Wang, South Hot-Cell, Development, TM3, , 10 pins lectrical check result after insulator is installed on water cap C.  

10 pins lectrical check result after insulator is installed on water cap C.

pin 14 to 60kv bias has 20 Kohm @250V Megga check. The rest check on ohmmeter and megga @250 are either OLor over 25Mohm which are good.

Entry  Monday, September 23, 2024, 16:06, Aaron Tam, South Hot-Cell, Repair, TM3, , Insulator Addition to Water block c02c089c-d2f0-4ddb-9f06-3dd8b8d05afa.jfif0fd6eb03-7d82-48af-8ef7-99fd481bf1aa.jfif14247104-53dc-4b00-852d-3a860c4baeb8.jfif

 September 23, 2024 - C. Fisher 

  • Containment box removed
  • Insulator installed
  • New window line VCR seals installed
  • Dropped bolt from TiC#8 removed
  • Containment box reinstalled

September 23, 2024 - A. Tam

  • Containment box cover reinstalled 

Photos attached 

Entry  Tuesday, September 24, 2024, 09:37, Frank Song, ITE/ITW, Standard Operation, , , shielding blocks transfer 

 5 shielding blocks have been moved from ITE to ITW.

Entry  Wednesday, September 25, 2024, 07:25, David Wang, Cooling, Maintenance, , , HALCW O2 level sensor maintenance.  

HALCW O2 level sensor annual maintenance is done. sensor membrane has been changed and electrolyte has been refilled. gauge is calibrated. It works normal after the job.

Entry  Wednesday, September 25, 2024, 09:12, David Wang, South Hot-Cell, Maintenance, TM3, , Tm3 has been moved from SHC to silo. 

Tm3 has been moved  from SHC to silo. the move is smooth.

Entry  Friday, September 27, 2024, 07:29, David Wang, Conditioning Station, Repair, , , TCS water system resistivity analyzer has been repaired. 

TCS water system resistivity analyzer has been repaired. Two diodes and one capacitor on PS board were broken. They were replaced. Installed analyzer back and tested it in system. it works fine. Operator closed e-fault, removed force on TS5, and enabled alarm on TS5 and TC1.

Entry  Tuesday, October 01, 2024, 10:55, David Wang, South Hot-Cell, Standard Operation, TM2, , TM2 has been moved from ITE to SHC. 

TM2 has been moved from ITE to SHC. Peter did the move with Travis on help.  The move is smooth.

Entry  Tuesday, October 08, 2024, 11:45, David Wang, South Hot-Cell, Standard Operation, TM2, , Tm2 electrical check with Ta#68 installed at SHC.  TM2_Ta#68_electrical_check.pdf

ABCD was dead shorted to 60kv bias during the first time measurement after target installation. Target was removed and reinstalled again with new VCR seals by Ferran.  during target removal process, short disappeared when Aaron remove bolts on CD tube heaters terminal.  leak check and electrical check result are good after second time target installation. 

Entry  Thursday, October 10, 2024, 12:20, Adam Newsome, Facilities, Standard Operation, , , Safety Walkaround complete - ISAC Hot Cells, Target Hall 

A safety walkaround was completed for the ISAC Hot Cells and Target Hall Areas.

The resulting spreadsheet can be found on DocuShare as Document-242733.

Main deficiencies identified:

  • Hot Cells:
    • Phone not working at North hot cell operator station
  • Target Hall:
    • Uncertain if NHC and SHC ventilation pressure gauges have recently been inspected

Action has been taken on all deficiencies.

Entry  Friday, October 11, 2024, 15:59, Aaron Tam, Facilities, Repair, , , ISAC B2 North Hot Cell Phone Fixed 

 Resolution comment / Commentaire de résolution:

     Fixed issue by changing patch cord that was connected to the switch from patch panel.

Emile V

Entry  Tuesday, October 15, 2024, 12:57, Frank Song, ITW/ITE, Standard Operation, , , shielding blocks transfer 

 5 shielding blocks are transferred from ITW to ITE, Target Area is secured again after moving.

Entry  Thursday, October 24, 2024, 10:37, David Wang, Conditioning Station, Standard Operation, , , TCS water system functionnal test.  

TCS water system has been started for functional test. System parameters including  pressure, all temperature sensors, flow rate sensors, resistivity are ok. I will watch on chiller CP1/2/3 in rest of the week and make sure chiller CP1/2/ 3 auto stage in/out work fine.

Entry  Monday, November 18, 2024, 12:18, Aaron Tam, South Hot-Cell, Repair, , , SHC West Manipulator Repair  

 November 14, 2024 - Aaron Tam w/ Chad Fisher 

Following ID: 2716   
"Nov. 8, 2024 - Aaron Tam 
Tong cable snapped when attempting to remove multipin connector bracket"

Repair went as follows:

  • weighted clip attached to tong return side to tension/keep tapes on pulleys
  • Manipulator was pinned from both sides (Pinning from master side first makes it easier to position slave side)
  • clamps were used to suspend all tapes and cables near the relay bracket 
  • extension tube limit clamps were moved to the top to stop it from dropping when Z motion tapes disconnected
  • Z motion tapes/tension adjusting screws taken off master carriage and suspended with equalizing weight ~10+ lbs)
  • Extension tube limit clamps and extension tube lowered give space to expose multiplier later 
  • Wrist joint and handle removed as a unit 
  • extension tube to multiplier screws taken out
  • Extension tube raised to expose multiplier - using extension tube to wrist joint positioning clamp to keep it in place 
  • Old cable removed
  • new cable installed

installation in reverse with spare master handle 

Notes:

Spare master wrist joint was missing gears that connect wrist drums 

  • this had to be disassembled and installed with gears from old wrist joint

Handle ratcheting pawl spring was not oriented properly, so this had to be disassembled and reinstalled properly (in the process one spring was lost Part#: A-5800)
 

 

 

 

Entry  Monday, November 25, 2024, 09:56, Adam Newsome, South Hot-Cell, Standard Operation, TM3, , TM3 move - silo to SHC 

TM3 was moved from silo to SHC with no target. Move successful.

Entry  Tuesday, November 26, 2024, 13:54, Adam Newsome, Conditioning Station, Standard Operation, TM3, , TM3 move - SHC to TCS 

TM3 was moved from SHC to TCS with UCx#47. The move was smooth.

Entry  Tuesday, December 03, 2024, 10:51, Adam Newsome, South Hot-Cell, Standard Operation, TM2, , TM2 move - ITE to SHC 

TM2 was moved from ITE to SHC with Ta#68 target. During the move, a railing was lightly bumped by the corner of the module - no obvious damage or issues have been observed. Otherwise, the move was smooth.

Entry  Tuesday, December 03, 2024, 12:28, Adam Newsome, South Hot-Cell, Standard Operation, TM2, , TM3 move - TCS to ITE 

TM3 was moved with UCx#47 from TCS to ITE. The move was smooth.

Entry  Wednesday, December 04, 2024, 09:00, David Wang, Facilities, Standard Operation, TM2, , all water lines on TM2 have been purged. 

all water lines on TM2 have been purged. Refilled them(except HS ) with 60psi nitrogen for module silo storage before next year using. 

Entry  Wednesday, December 04, 2024, 10:40, Adam Newsome, South Hot-Cell, Standard Operation, TM2, , TM2 move - SHC to silo 

TM2 was remotely moved from the South Hot Cell to SW Silo. Reading at SHC = 89.8 mSv/h. The move was smooth.