  RH-ISAC, Page 136 of 140  Not logged in ELOG logo
ID Date Author Category Type Module Target/Number Subjectdown
  1249   Thursday, June 02, 2016, 11:59 David WangSouth Hot-CellRepairTM3 5K mega test on TM3

I did a 5KV mega test on TM3.  Only5Mohm @5kV between coli line PQ and chassis(ground). It confirmed the close gap between P,Q and GE. Other lines are ok. See attachment.

Attachment 1: 5K_mega_check_on_TM3.pdf
5K_mega_check_on_TM3.pdf
  1250   Thursday, June 02, 2016, 18:04 Aurelia LaxdalSouth Hot-CellRepairTM3 5K mega test on TM3

David Wang wrote:

I did a 5KV mega test on TM3.  Only5Mohm @5kV between coli line PQ and chassis(ground). It confirmed the close gap between P,Q and GE. Other lines are ok. See attachment.

See attachment for sparking signs of the water lines mentioned  above (Coil and Ground Electrode lines) in TM3 Source Tray.

Attachment 1: DSC_0821.JPG
DSC_0821.JPG
Attachment 2: DSC_0822.JPG
DSC_0822.JPG
  1252   Friday, June 03, 2016, 16:04 Aurelia LaxdalSouth Hot-CellRepairTM3 5K mega test on TM3

Aurelia Laxdal wrote:

David Wang wrote:

I did a 5KV mega test on TM3.  Only5Mohm @5kV between coli line PQ and chassis(ground). It confirmed the close gap between P,Q and GE. Other lines are ok. See attachment.

See attachment for sparking signs of the water lines mentioned  above (Coil and Ground Electrode lines) in TM3 Source Tray.

PLEASE NOTE: the resistance values for A and B on David's attachment are not correct since these measurements were done after Chad removed the target and the heat-shield bracket was moved, so consequently the water lines were not at their nominal locations. Once they were back in plac,e David took another measurement and the resistance values for A and B showed also 3,000 MOhm (as it was for most of the lines). The only lines that still showed a low resistance were the Coil lines. 

  330   Monday, May 06, 2013, 15:45 Bevan MossConditioning StationRepairTM3 55 pin connector removed

Travis and I removed the 55 pin connector from the service cap today. The feed through was left in place as a new design for the replacement has yet to be designed. It was not possible to test if the cables could be pulled easily as I believe there is still 1 cable tie in the containment box. The wires were cut flush with the top of the copper tube in case Chad cannot remove them via the hot cell. Other items removed include several cable ties and a clamp used to hold a cable tie. The side panels on the service cap we difficult to remove so copper never sieze was added when they were re-installed.  I have attached some pictures from before and after a complete record can be found in the TM3 docushare folder.

Attachment 1: 20130506_55_pin_conector_removal_IMG_3530.JPG
20130506_55_pin_conector_removal_IMG_3530.JPG
Attachment 2: 20130506_55_pin_conector_removal_IMG_3525.JPG
20130506_55_pin_conector_removal_IMG_3525.JPG
Attachment 3: 20130506_55_pin_conector_removal_IMG_3532.JPG
20130506_55_pin_conector_removal_IMG_3532.JPG
Attachment 4: 20130506_55_pin_conector_removal_IMG_3535.JPG
20130506_55_pin_conector_removal_IMG_3535.JPG
  1212   Thursday, April 14, 2016, 12:56 David WangITWStandard OperationTM1 5 shielding blocks have been moved to ITW.

The ITW is configured to take proton beam.

  447   Wednesday, September 11, 2013, 09:35 David WangITWStandard OperationTM1UCx5 shielding blocks have been moved to ITW

I moved 5 shielding blocks to ITW this morning .I checked the water signals in electrical room before the moving, and everything is fine. The argon venting systemin ITW and electrical room is ready also.

  581   Monday, January 20, 2014, 13:35 David WangITEStandard OperationTM4 5 shielding blocks had been moved out of ITE

5 SHIELDING BLOCKS HAD BEEN MOVED OUT OF ITE.AIR SAMPLE AND SWIPED FIRST BLOCK AND ITE PIT.NOTHING HAD BEEN FOUND ON ALPHA MONITOR AND OTHER TWO MONITORS.

  399   Tuesday, July 09, 2013, 14:26 David WangITWStandard OperationTM1UCx5 shielding blocks had been transferred from ITE to ITW

5 shielding blocks had been  transferred from ITE to ITW.  The  ITW is configured to take proton beam.

  1943   Friday, June 14, 2019, 08:15 David WangITEStandard OperationTM2 5 shielding blocks are moved to ITE.

ITE is configured to take proton beam.

  2042   Tuesday, January 07, 2020, 09:37 David WangITWStandard Operation  5 shielding blocks are moved out of ITW top.

5 shielding blocks are moved out of itw top.

  374   Tuesday, June 04, 2013, 12:36 David WangITEStandard OperationTM4 5 shielding blocks are transferred from ITW to ITE

Dan an I  transferred 5 shielding blocks from ITW to ITE. The ITE is configured to take proton beam.

  700   Tuesday, July 08, 2014, 09:57 David WangITEStandard OperationTM3 5 Shielding blocks have been transferred from ITW to ITE.

5 Shielding blocks have been transferred from ITW to ITE. The ITE is configured to take proton beam.

  734   Wednesday, August 20, 2014, 10:25 David WangITEStandard OperationTM4 5 Shielding blocks have been transferred from ITW to ITE.

5 Shielding blocks have been transferred from ITW to ITE. ITE  is configured to take proton beam.
 

  801   Tuesday, November 25, 2014, 12:45 David WangITEStandard OperationTM4UCx115 Shielding blocks have been transferred from ITW to ITE.

5 Shielding blocks have been transferred from ITW to ITE. The ITE is configured to take proton beam.

  884   Friday, April 10, 2015, 15:40 David WangITEStandard OperationTM4 5 Shielding blocks have been transferred from ITW to ITE.

5 shielding  blocks have been transferred to ITE. The ITE is configured to take proton beam.

  954   Friday, June 19, 2015, 11:52 David WangITEStandard OperationTM4SiC #315 Shielding blocks have been transferred from ITW to ITE.

5 shielding blocks have been transferred from ITW to ITE. The ITE is configured to take proton beam.

  1091   Tuesday, October 06, 2015, 12:50 David WangITEStandard OperationTM4Ta#465 Shielding blocks have been transferred from ITW to ITE.

The ITE is configured to take proton beam.

  1092   Tuesday, October 06, 2015, 12:50 David WangITEStandard OperationTM4Ta#465 Shielding blocks have been transferred from ITW to ITE.

The ITE is configured to take proton beam.

  1268   Monday, June 27, 2016, 13:45 David WangITEStandard Operation  5 Shielding blocks have been transferred from ITW to ITE.

ITE is configured to take proton beam.

  1319   Monday, August 15, 2016, 10:08 David WangITEStandard OperationTM4UC#175 Shielding blocks have been transferred from ITW to ITE.

Dan and I transferred 5 shielding blocks from ITW to ITE. The ITE is configured to take proton beam.