Friday, April 28, 2023, 21:39, David Wang, Conditioning Station, Standard Operation, , , TCS cooling water system was started and tested this Wednesday
|
TCS cooling water system was started and tested this Wednesday. Chiller compressor 2 and 3 was in operation cycle twice without issue. TCS:TK2 was refilled
to 28 inches. Water system works fine. system was switched off after test. |
Tuesday, May 02, 2023, 17:18, David Wang, ITE, Standard Operation, , , ITE 4 turbopumps are started for preoperation check.
|
ITE TP3,4, 1S,and 4S were started successfully this afternoon. All pump current draws were below 1.5A . IG1S was switched on. I have no local controller
so TP1 and TP2 on TM4 at MSP can not be checked. IG1S was hard to switch on at first. It timed out and showed error 09 code. I removed the
connector back cap, and it could be switched on after. I will look on this issue. |
Wednesday, May 03, 2023, 11:04, Adam Newsome, Crane, Maintenance, , , Pail Handling Tool - Annual Inspection
|
The pail handling tool which is used to move 5 gallon pails around the target hall was inspected by A. Newsome, N. Jorgenson, and E. Lahe. The main tool
as well as spare were checked for the following items. The tools are in good, working condition. It is noted that some fasteners on the hook assembly were
slightly loose, but have been tightened. |
Wednesday, May 03, 2023, 13:22, David Wang, ITE, Standard Operation, , , Argon vented ITE station.
|
Argon vented ITE station. ITEVV1S and ITGT SV3 were closed after venting. |
Friday, May 12, 2023, 09:56, Adam Newsome, Spent Target Vault, Standard Operation, , , Emergency Close Mechanism Test
|
The emergency close mechanism for the Storage Vault door was tested by Travis Cave, Nadia
Jorgenson, Adam Newsome, and Jason Zhang. The door was opened to its fully open limit, then closed with the emergency system.
The test was successful. |
Tuesday, May 30, 2023, 14:15, David Wang, ITW, Standard Operation, , , ITW water signal interlock check is done.
|
ITW water signal interlock check is done. All ITW water signals including HS, EE, Coil , Ta, Tu, MSP, C-window, HVC1, HVC2, 2A-dump, 2A -shielding plug,
2A-tank, 2A-window, and 2A-collimator are checked. All water signal interlock work fine. |
Tuesday, May 30, 2023, 14:19, David Wang, ITE/ITW, Standard Operation, , , BL2A MAA primary beam exclusion area ASU test.
|
MAA ASU test have been done following document 154779. All three tests in document are passed. DCR Jas has all test documents.
This test includes the functional test on TH emergency roof hatch which is located at the west end of TH roof. The hatch could be opened and closed
properly from TH inside. |
Tuesday, June 06, 2023, 15:10, Antoniette Yap, Spent Target Vault, Maintenance, , , Annual Inspection of Main and Mini Storage Vaults
|
The annual inspection of the mini-storage vault and main storage vault was completed June 23, 2023. The following items were checked:
Cabling and cable management
Connectors
Controls box - internal wiring and components, functionality
Limit switches - functionality, wiring, mounting
Motor
Bearings
Set screws
Miscellaneous |
Monday, June 12, 2023, 07:36, David Wang, Conditioning Station, Standard Operation, , , TCS water filters annual change.
|
Plant group changed TCS water filters last Friday. 4 filters on resin can inet /outlet sides and filters(4 in one cartridge house)on pump return line
have been changed. Triumf maintenance tags on filters have been updated. No water leak after job. The TCS TK2 water level dropped from 20" to
16" because of the job. I will refill the level to 28" today. |
Tuesday, June 20, 2023, 12:37, Adam Newsome, Assembly/Bench Test, Development, , , Modifications to wire ropes for pails within existing F-308s 6x
|
Based on a request from CNL (attached), modifications were made to the wire ropes protruding through the tops of F-308s to add a crimped loop which acts
as a lifting feature. Tests were performed (report attached) on 10 sample units to validate the strength of these loops, since each loop could not be tested
in-situ once the pails were already packed in F-308s. CNL has reviewed and approved the test report. |
Wednesday, June 21, 2023, 09:51, Travis Cave, Spent Target Vault, Standard Operation, , TiC#5, Spent Target Move
|
TiC#5 moved to the spent target vault from the north hot cell. Placed in pail#279 in spot 3A, 40mSv/h when removed from NHC. See attached PDF for
further details. |
Wednesday, June 21, 2023, 14:39, Adam Newsome, Safe Module Parking, Maintenance, , , Annual electrical and mechanical inspection of Safe Module Parking
|
An annual electrical and mechanical inspection was performed on the SMP today by Adam Newsome, Travis Cave, Eric Lahe, Maico Dalla Valle, Antoniette
Yap, and Jason Zhang as per Work Permit I2023-06-21-4. The following items were checked:
Check condition of wiring for physical/radiation/UV damage
OK, no signs of significant damage
|
Wednesday, July 12, 2023, 22:21, Carla Babcock, North Hot-Cell, Standard Operation, , TiC#5, TiC#5 post irradiation inspection results
|
The TiC#5 post irradiation inspection was done on Wed. June 14 and Mon. June 19. This target didn't have any obvious issues but it didn't produce much
beam. The inspection revealed that the container was quite embrittled and showed significant damage, though it was not broken. The FEBIAD grid looked fine,
despite the large anode current draw (indicating that current was flowing elsewhere). The gas line looked fine though the gas injection to this target |
Tuesday, July 25, 2023, 16:25, Carla Babcock, North Hot-Cell, Standard Operation, , SiC#45, SiC#45 post irradiation inspection
|
Looked at SiC#45 in the hot cell. Looked very clean, no deposits on the heat shield or other components. Target also looked very straight. Only issue
we saw was sparking marks on the EE side that faces the ground electrode, in several spots. This target had a bout of sparking when ramping up the protons,
so I guess that was the location. Will look for matching spark marks on the ground electrode next time TM4 is in the hot cell. Forgot to take picutres... |
Friday, July 28, 2023, 10:09, Adam Newsome, Spent Target Vault, Maintenance, , , Main Storage Vault: Bearing Lubrication
|
Bearings for the main storage vault door were lubricated on 2023-07-28. It is unknown when this was last done. It is suggested that this be a recurring
maintenance task every two years. |
Friday, July 28, 2023, 10:21, Adam Newsome, Spent Target Vault, Maintenance, , , Mini Storage Vault: Bearing Lubrication
|
The bearings on the mini storage vault were lubricated. It is suspected that this has never been done. It is suggested that this be performed every two
years.
A draft procedure will be created for this job, but at a high level, this process involves: |
Tuesday, August 01, 2023, 09:06, Adam Newsome, Crane, Development, , , Measuring Tape and Camera Removed from Target Hall Crane
|
In an effort to clean up the camera installation on top of the ISAC target hall crane to resolve a fault, the position measuring tape and its associated
camera were removed from the target hall crane on July 31, 2023.
|
Thursday, August 03, 2023, 12:24, Jason Zhang, Crane, Development, , , Cleanup of camera installation on target hall crane, installation of replacement laser
|
The cleanup of the ISAC Target Hall crane and installation of the new SICK
laser which replaced the IBEO laser for the EW crane position was completed on Aug 03 2023.
The clean up tasks which were completed: (Removal of tape viewing camera, Removal of tape, Installation of extension |
Wednesday, August 23, 2023, 10:45, Travis Cave, Spent Target Vault, Standard Operation, , TiC#6, Spent Target Move
|
TiC #6 moved from north hot cell to spent target vault placed in pail #232 put in spot 6A and the field was 151mSv/hr when removed from the north
hot cell. See attached PDF for details about spent target vault. |
Friday, September 01, 2023, 10:36, Adam Newsome, Spent Target Vault, Standard Operation, , UCx#42, Spent Target Move
|
UCx #42 moved from North Hot Cell to Storage Vault in Pail #282. Placed in slot 6B. Tray 6 is now full. Pail measured at 34.9 mSv/h at ~1 m upon
removal from the hot cell. See attached updated spreadsheet. |
|