Entry  Tuesday, September 25, 2018, 07:54, David Wang, Conditioning Station, Repair, TM3, , TM3 is connected for HV test at TCS. 
water loops are by passed on top. All bias, EE, and  EL are tied together. Started water system.
Entry  Wednesday, September 26, 2018, 07:14, David Wang, Conditioning Station, Repair, TM3, , TM3 HV test at TCS. 
I did a HV test on TM3 at TCS yesterday. HV Ramp up speed: 1KV per 5 minutes when below 30KV,1KV per 10 minutes from 30-36KV. There is no major spark
below36 KV .  I could see  lots small and big vacuum response on IG1 and PNG2 when conditioning from 30-36 KV, especially when closing to 36
KV.  However, At 36.4 KV, There is a big continuous spark occurred. It could not be stopped until I lowed the HV to 14KV. I have to ramp up from 14
Entry  Thursday, September 27, 2018, 13:58, Travis Cave, Conditioning Station, Standard Operation, TM3, no target, Module move 
 TM#3 has been moved from the conditioning station to the centre east silo. This will be its new home after the silo switcher-roo.
Entry  Tuesday, October 09, 2018, 12:32, David Wang, Conditioning Station, Repair, TM4, , TM4 steers 4 pin feedthrough CF flange 
TM4 Steers 4 pin feedthrough CF flange is replaced due an inside feed through insulator broken. CF 25 cooper seal is replaced with a new one as well.
Travis did anelectrical check. after replacement. Everything looks fine.
 
Entry  Wednesday, October 10, 2018, 10:50, Travis Cave, Conditioning Station, Standard Operation, TM4, Ta#57, Electrical Check TM#4_UC#24_Electrical_Check_SHC.pdfTM#4_Elec_Chk_No_Target_Oct-3-2018.pdfTM#4_Elec_Chk_SHC_Ta#57.pdf
 The various electrical check done on TM#4 after the UC run and before the start of the Ta run.
Entry  Friday, October 26, 2018, 09:44, Travis Cave, Conditioning Station, Standard Operation, , , Exit Module moved 
The west exit #2 module has been moved from the south hot cell to the conditioning station.
Entry  Monday, October 29, 2018, 10:43, David Wang, Conditioning Station, Repair, , , ITW exit 2 leak check at TCS. 
I did a leak check this morning on exit 2 module at TCS. LD base  leak rate is 4.00XE-9atm.cc/sec, Base pressure is 0.00 X E-4 torr. All seals,
bellows, and flanges are checked. The new FC5 bellow is good. There is a big leak up to 2X E-6 atm.c/sec has been found on IG1S side panel . The panel
itself  will be replaced this time. Machine shop is working on it.. Two small leaks in E-9  atm.cc/sec range have been found on the  o-ring
Entry  Wednesday, October 31, 2018, 14:20, Travis Cave, Conditioning Station, Standard Operation, TM2, UC#25, Module move 
TM#2 with UC#25 has been moved from the south hot cell to the conditioning station.
Entry  Thursday, November 01, 2018, 11:42, David Wang, Conditioning Station, Standard Operation, TM2, UCx 25., TM2 HS line helium pressure test at TCS and helium spray at SHC.. 
Chad and I did  leak check on TM2 HS line at SHC yesterday. Base LR 0.0XE-9 atm.cc/sec.   No response on LD. during helium spray.  
Today , I did helium pressure test at TCS. base LR 0.0xe-9atm.cc/sec. applied 70psi helium for 3 minute. leak rate slowly climbed to2.2 Xe-7 atm.cc/sec
ate stopped there.  The result is close to before.
Entry  Monday, November 05, 2018, 14:27, Anders Mjos, Conditioning Station, Standard Operation, TM2, UC#25, Target module disconnected 
Frank and Anders disconnected the water and electrical connections this afternoon after the target was conditioned over the weekend. The heater ramping
program ran with the wrong gauge selected, causing the vacuum to go higher than planned. The module will be moved to ITW tomorrow.
Entry  Wednesday, November 28, 2018, 06:39, David Wang, Conditioning Station, Standard Operation, , , Disconnection checklist LpTa #56 LpTa#56_disconnection_checklist.pdf
TM4 was disconnected in ITE. Checklist list in attachment.
Entry  Wednesday, November 28, 2018, 13:38, Travis Cave, Conditioning Station, Standard Operation, TM4, UC#26, Module move 
 TM#4 with UC#26 has been moved from the south hot cell to the conditioning station.
Entry  Wednesday, December 19, 2018, 14:41, Anders Mjos, Conditioning Station, Standard Operation, , No target, Installed Shield Block on TCS 
Frank and Anders installed lid on TCS and started vacuum system yesterday. To run over the Holidays. Retrieved dose badge from operational storage area.
Measured field to be ~ 10 mSv/h at ~9am. Beam went off about 8:30am.
Entry  Wednesday, January 02, 2019, 10:26, Anders Mjos, Conditioning Station, Standard Operation, , , Restarrted TP1S 
Found pumps off after the holidays. Restarted roughing pump and TP1S
Entry  Wednesday, January 09, 2019, 06:26, David Wang, Conditioning Station, Standard Operation, , , TCS vacuum pumps have been stopped. 
The tCS will be vented soon for TM2 move later this week.
Entry  Thursday, January 10, 2019, 09:26, Travis Cave, Conditioning Station, Standard Operation, TM2, no target, Module move 
 TM#2 has been moved from the south hot cell to the conditioning station.
Entry  Thursday, January 10, 2019, 10:45, David Wang, Conditioning Station, Standard Operation, TM2, , TM2 is under vacum at TCS. 
TCS: TP1, TP2 and TP1S are started. 
Entry  Friday, January 11, 2019, 13:17, David Wang, Conditioning Station, Standard Operation, TM2, , TCS and TM2 vacuum system are switched off for this Sunday power outage.  
I will restart all pumps Monday morning.   
Entry  Monday, January 14, 2019, 07:07, David Wang, Conditioning Station, Maintenance, TM2, , Restarted TCS vacuum system . 
No issue.
Entry  Monday, January 28, 2019, 10:41, David Wang, Conditioning Station, Repair, TM2, , TM2 water lines helium pressure test at TCS 
leak detector base LR: 0.0Xe-9atm.cc/sec. helium 70 psi. test time : 3 minutes for each circuit.The results in atm.cc/sec are Ta+(A):1.8  XE-8.
TA-(B):0.0xE-9. Tu-(C):1.2XE-7. TU+(D):1.6XE-7. Coil 2 (PQ):0.0XE-9. Coil 1 (RU):0.0XE-9. MSP:2.2XE-7. EE:1.0XE-7. HS:N/A. Window:5.8XE-9