Message ID: 1801     Entry time: Tuesday, October 09, 2018, 12:32
Author: David Wang 
Category: Conditioning Station 
Type: Repair 
Module: TM4 
Target/Number:  
Subject: TM4 steers 4 pin feedthrough CF flange 

TM4 Steers 4 pin feedthrough CF flange is replaced due an inside feed through insulator broken. CF 25 cooper seal is replaced with a new one as well. Travis did anelectrical check. after replacement. Everything looks fine.

 

Note only a megger check was performed on the affected steering lines. Open load was measured on all lines. (Travis Cave)