  ID Date Authordown Category Type Module Target/Number Subject Text Attachments
  1587   Tuesday, July 18, 2017, 16:53 Anders MjosConditioning StationDevelopmentTM3No targetConditioning TM3Conditioning continues today with resistors
removed from the HV cable
Tuesday, July 18, 2017, 16:53: BIAS
  
  1594   Thursday, August 03, 2017, 17:08 Anders MjosConditioning StationRepairTM2 Power bump Thursday, August 03, 2017, 17:08:
Restarting vacuum and water system
  
  1597   Tuesday, August 15, 2017, 09:27 Anders MjosSouth Hot-CellStandard OperationTM2SiC#36Electrical Check of target in SHC

    

       
            
  
  1598   Tuesday, August 15, 2017, 09:30 Anders MjosITWStandard OperationTM2Ta#53TM2 radiation fields

    

       
            
  
  1601   Friday, August 25, 2017, 16:33 Anders MjosConditioning StationRepair  Testing HV after cooling line repair The BIAS voltage was brought up to
70 kV today and held there for 1h. No sparking
observed.
 2017-08-25_HV_Water_Line_Test.xlsx 
  1622   Thursday, September 21, 2017, 16:26 Anders MjosSouth Hot-CellStandard OperationTM2 Inspection of Source TrayChad and Anders inspected the Source Tray
today using the camera in the hot cell. A
dark spot was observed on one of the four
 TM2_Source_Tray_EE_Insulator.pdf 
  1631   Thursday, September 28, 2017, 15:34 Anders MjosConditioning StationDevelopmentTM2 Changes to MP3 startup Due to problems with the regulating
valve WPV1, the VFD (Variable Frequency Drive)
for the pump has been programmed to do a
  
  1632   Thursday, September 28, 2017, 17:44 Anders MjosConditioning StationStandard OperationTM2Ta#54Conditioning Ta#54Thursday, September 28, 2017
Cooling water not yet connected to
TM.
 Ta#54.docxTa#54_BIAS_current_vs_voltage.xlsx 
  1634   Thursday, October 05, 2017, 11:04 Anders MjosITWMaintenance  Installation of new valve for module move ventilationDavid installed the new ball valve and
connections for the SAS project module move
ventilation. SASP0482. Drawing reference
  
  1637   Friday, October 06, 2017, 13:25 Anders MjosConditioning StationRepair  HV Test HV was brought up to 70 kV for 1
h without sparks to test the new water installation.
 2017-10-06_HV_Water_Line_Test.xlsx 
  1646   Wednesday, October 18, 2017, 14:54 Anders MjosAssembly/Bench TestStandard Operation  Source tray assembly electrical checkSource tray meggered today by Anders and
Keith
GND - MSP OL @ 1000V
 Steerer_Connections_2017-10-18.pdf 
  1648   Thursday, October 19, 2017, 14:20 Anders MjosAssembly/Bench TestStandard Operation  Source tray inspection Two minor chips in the main 60 kV
insulators on the source tray was inspected
today by Anders, Tom and Aurelia. The chips
 Left_Insulator.jpgRight_Insulator.jpg 
  1649   Thursday, October 19, 2017, 14:20 Anders MjosConditioning StationStandard OperationTM4SiC#37SiC#37 ConditioningThursday, October 19, 2017, 14:20: EE configured
for conditioning. HV cage locked up
Thursday, October 19, 2017, 16:46:
 SiC#37_BIAS_current_vs_voltage.xlsxSiC#37.docx 
  1652   Thursday, October 26, 2017, 09:56 Anders MjosITERepairTM4SiC#37Leak on multi pin connector feedthroughOn maintenance day Tuesday, the roughing
of the target station could not go below
1.5 Torr. A brief troubleshooting on Tuesday
  
  1655   Thursday, November 09, 2017, 08:46 Anders MjosConditioning StationRepair  Communication fiber replaced for HV PLC After extensive troubleshooting the
communication fiber was found to be damaged
and has been replaced by Gelo.
  
  1658   Thursday, November 09, 2017, 10:39 Anders MjosConditioning StationStandard OperationTM2Ta#55Conditioning Ta#55Thursday, November 09, 2017, 10:40: BIAS
/ EL to 30 / 15 kV. 400 uA on BIAS
Bias was stable for 1 hour. Handed
  
  1665   Wednesday, December 06, 2017, 09:33 Anders MjosConditioning StationMaintenance  Running chiller for maintenance tech Dakine is on site to do maintenance
on the chiller. The tech requested the chiller
to operate.
  
  1666   Wednesday, December 13, 2017, 15:32 Anders MjosAssembly/Bench TestMaintenanceTM2 Source Tray inspectionThe Source tray was inspected in the RH
shop today by Anders, Friedhelm and Jens.
The routing of the lines are satisfactory,
  
  1668   Tuesday, December 19, 2017, 10:41 Anders MjosCraneMaintenance  Crane powered downThe target hall crane has been powered
down by Don today in preparation for the
power shutdown over the Holidays.
  
  1669   Thursday, December 21, 2017, 15:11 Anders MjosConditioning StationMaintenance  Powered down devicesPowered down mechanical pumps in ISAC-I
Experimental hall, vacuum gauge and turbo
pump controllers in ISAC-I B2 North Hot Cell
  